Northern States Power Company 414 Nicollet Mall Minneapohs. Minnesota 55401 Telephone (612) 330 5500 February 10, 1988 IE Bulletin 87-02 t
Director of Nuclear Reactor Regulation U S Nuclear'Rogulatory Commission Attn:
Document Control Desk Washington, DC 20555 PRAIRIE ISLAND NUCLEAR GENERATING PLANT Docket Nos. 50-282 License Nos. DPR-42 50-306 DPR-60 Supplemental Reeponse to NRC Compliance Bulletin 87-02 Ref: (a) Letter from C E Larson, NSP, to Director of NRR, "Response to NRC Compliance Bulletin 87-02," January 26, 1988 The NRC Office of NRR Project Manager for Prairie Island has informed us that copies of Reference (a) are missing page 55.
A copy of the missing page is attached.
We apologize for any inconvenience caused by this problem.
DM Mu F ~~
C E Larson Vice President Nuclear Generation c: Regional Administrator, Region III, NRC Sr Resident Inspector, NRC NRR Project Manager, NRC G Charnoff Attachment i
1 j
\\
fe'I 88o217o067 eso21o PCR ADOCK 05000282 1;\\
G PDR
3 0
twin city testing comormoon p:,5' 662 CROMWELL N/ENUE f*
ST. PAUL MN 55114 y
r 5.,
PHCNE 612/645 3601 OF: GDfICAL ANALYSIS. TENSILE TEST. AND HARDNESS EVALUATION OF FASTDfERS 4142 88-0337 DATE: January 8, 1988 LABORATORY No-PAGE: Fourteen HARDNESS TES'l RESULTS:
(cont)
The hardness test results of Samples PIB1, PI Core, PIB5, and PIB10 Core, do not confom to the hardness requirements listed in their respective material specifications. %e rest of the hardness results do confom to those requirements.
Due to the failure of these samples, a retest was conducted on them at the request of Donald J Brosche of Northern States Power Company. D e retest results are shown below:
Sample Identifi-Test Date Reading Reading Reading Reading Average cation Location
, of Test No 1 No 2._
No 3 No 4 Hardness PIL; Side of bolt head 12-29-87 58.0 65.0 68.0 68.5 64.5 HR30N
- PIB1 Shank near 1-8-88 51.0 51.5 50.5 52.5 51.5 HR30N threaded end PIB1 Core 12-21-87 25.0 22.5 22.5 24.0 23.5 HRC PIB3 Core 1-4-88 18.5 18.5 17.5 18.5 18.5 HRC
- PIBS Side of bolt head 12-21-87 35.5 36.0 3G.0 36.5 36.0 PRC i
PIB10 Core 12-21-87 22.5 25.5 22.0 25.0 24.0 HRC
- These samples were wet ground approximately 1/32" in prior to retest.
The hardness retest results do not confom to the hardness requirements listed in their respective material specifications.
D e hardness tests were conducted between December 11, 1987, and January 8, 1988, according to AS'Df:A370. E18, F606, SAE:J429 as J417.
RDfARFS :
The test material is being returned to Northern States bwer Company with a copy of this report.
TWIN CITY TESTING CORPORATION
%W Derrick J Swanson, M.E.
Metallurgy & Welding Section Supervisor Product Testing Division DJS/rw/88-337 III.0,'Ja*.* '17".".'*.00.5:J.' Ts*At"O".'N'. /#."a* ",'14*A".7JO"'fllO*,*'.T.'.0;. ****l.".".*: 'O'/. /.'.**.!1"