ML20196A452

From kanterella
Jump to navigation Jump to search
Responds to Violations Noted in Insp Rept 50-155/87-22. Corrective Actions:Rev to Shutdown Procedure to Stroke Valve MO-7071 When Reactor Pressure Below 50 Psig During Plant Shutdowns Proposed
ML20196A452
Person / Time
Site: Big Rock Point File:Consumers Energy icon.png
Issue date: 02/01/1988
From: Frisch R
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
NUDOCS 8802050053
Download: ML20196A452 (2)


Text

-

l Consumers POW 8r L

ME AUGANIAM'S MtdNiftE55 General officos: 1945 West Parnall Road, Jack son, MI 49201. (517) 788-0550 l

February 1, M88 l

i Nuclear Regulatory Commission Document Control Desk l

Washington, DC 20555 DOCKET 50-155 - LICENSE DPR BIG ROCK POINT PLANT -

STR0KE TESTING OF MO-7071 Inspection Report No. 50-155/87022 identified a NRC concern that while l

performing T30-22 valve MO-7071 was being tested in a manner which did not i

assure that maximum differential pressurr existed across the valve during l

testing. During performance of T30-22, at that time, it was noted that back l

1eakage through the "telltale" between MO-7070 and VPI-303 provided evidence l

that the piping between VPI-303 and MO-7071 was depressurizing (via leakage through V?I-303) and this resulted in MO-7071 being tested against maximum l

differential pressure in the reverse direction. Consumers Power Company committed to revise the test procedure as discussed with the inspectors and to submit a copy of the revised test procedure within sixty days.

A change was made to T30-22 to include the following step:

"Verify that pressure between check valve VPI-303 and MO-7071 has bled off by observing the following: With MO-7071 open observe the flow from the telltale between MO-7070 and MO-7071. Then, after closure of M0-7071, observe that the flow from the telltale decreased l

indicating depressurization of the spool piece between VPI-303 and M0-7071."

The following observations were made recently while performing the revised T30-22 which requires additional action; 1.

MO-7070 was opened and a steady stream was noted from the telitale.

2.

M0-7070 was closed and the stream from the telltale stopped completely.

3.

MO-7071 was opened and no flow through the telltale was noted.

1 1

4.

M0-7071 was closed with no change in flow noted, f0

'h OC02as-0033-n04 8802050053 800201 l

PDR ADOCK 05000155 G

PDR

~.

~...

o Nuclear Regulatory Commission 2'

Big Rock Point Plant i

Stroke Testing of MO-7071 February 1,- 1988 i

The abo *;e sequence indicates that check valve VPI-303 is holding and pressure is being trapped between VPI-303 and MO-7071.

Under this condition the valve i

may be required to function with a large differential pressure across the valve (Reactor pressure trapped between the valves and atmosphere pressure in the Reactor vessel) during an accident condition.

It is believed that the i

first test of M0-7071 after a start-up already shows that the valve will stroke with this large differential pressure. This is due to the fact that there should be no pressure between VPI-303 and MO-7071 af ter start-up.

Since it has been discovered that the change to T30-22 previously discussed with the NRC has been found to not perform its intended purpose it is proposed to change the shutdown procedure to stroke M0-7071 when the reactor pressure is less than 50 psig during plant shutdowns. To demonstrate operability, this

~

will permit stroking MO-7071 with a large differential pressure trapped between MO-7071 and VPI-303 as would be the case during an accident condition.

I This change will be implenented during the next refueling shutdown currently scheduled for April 1988.

t

, {].

i l

WhN l

Ralp R Frisch i

j Senior Licensing Analyst i

i CC Administrator, Region III, NRC i

NRC Resident Inspector - Big Rock Point Plant i

d I

1 i

i l

1 1

l OCO288-0033-NLO4 a

n

-