ML20195H393

From kanterella
Jump to navigation Jump to search
Responds to Violations Noted in Insp Repts 50-266/87-07 & 50-301/87-07.Corrective Actions:Encl Technical Evaluation of Fire Damper Tests at Point Beach Nuclear Plant, Developed
ML20195H393
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 01/13/1988
From: Fay C
WISCONSIN ELECTRIC POWER CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
CON-NRC-88-003, CON-NRC-88-3 VPNPD-88-022, VPNPD-88-22, NUDOCS 8801190294
Download: ML20195H393 (22)


Text

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _.

'O I

WiSC0nSin Electnc roua courasr 231 W.WCHIGAN.P.O BOX 2046.WLWAUKEE.W153201 (414)277 2345 VPNPD-88-022 NRC-88-003 January 13, 1988 U.

S. NUCLEAR REGULATORY COMMISSION Document Control Desk Washington, D.

C.

20555 Gentlemen:

DOCKETS 50-266 AND 50-301 TECHNICAL EVALUATION OF F7.RE DAMPER TESTS POINT BEACH NUCLEAR PLANTS, UNITS 1 AND 2 In response to Inspection Report 50-266/87007(DRS);

50-301-87007(DRS), which we roccived with your letter dated July 7, 1987, we are providing our Technical Evaluation of Fire Damper Tests at Point Beach Nuclear Plant.

During development of the Technical Evaluation, we determined that a damper closure verification test would be required.

Preparation of a test procedure and scheduling of the test so as not to interfere with the Fall 1987 outage manpower requirements delayed our verification of the Technical Evaluation and submittal for Region III review.

We believe that our submittal of the enclosed Technical Evaluation fulfills our commitment for open item (266/87007-06;301/87007-06), Paragraph 3.c of the Inspection Report.

Please contact us if you have any questions regarding this submittal.

Very truly

ours,

(?lU C. W.

Fay '

Vice President Nuclear Power Attachments Copies to NRC Resident Inspector NRC Regional Administrator - Region III l

( ' l,g 8801190294 880113 PDR ADOCK 05000266 oco o _ _ __ _

i TECHNICAL EVALUATION 0F FIRE DAMPER TESTS AT POINT BEACH NUCLEAR PLANT t

l

1.0 INTRODUCTION

l During routine safety inspections between February 23 and June 26, 1987, the inspector requested that the licensee provide justification regarding i

the test methodology utilized to demonstrate that fire dampers will close 4

under normal air flow.

Provision of the requested justification was identified as open item 266/87007-06; 301/87007-06 in the July 7, 1987 inspection report.

This Technical Evaluation is prepared in response to the inspector's request.

1

2. 0 PURPOSE I

The purpose of this evaluation is to demonstrate that the methodology used to test fire damper closure under normal air flow provides adequate assurar that the dampers will function as required to maintain fire c

barrier integrity.

4 3.0 SCOPE i

I The PBNP Fire Damper Summary is a list of fire dampers which are lo ated l

in the boundaries of fire areas containing Appendix R safe shutdown l

components.

This evaluation covers fire dampers which are identified in I

~ -

+-

r-w

-..yw.v--w-,, - -, - -,,,

the summary as having been tested under normal air flow conditions.

The sumicary is attached as Table FD-1.

4.0 BASIS In a previous evaluation we determined that it was not practical to expect large multisection dampers to close against normal air flow.

Multisection dampers have been tested statically and a Standing Order has been issued for PBNP operators to shut down ventilation for the affected zone if a fire is detected in fire zones separated by such dampers.

The Fire Damper Test Guidelines dated 03-04-86 were used to test fire dampers under normal air flow.

The guidelines are intended to be generic and do not describe a standard test configuration with specific dimensional tolerances.

However, we believe that a sufficient quantity of dampers were tested ir t conservative air flow configuration to demonstrate that the dampers will operate as intended.

A fire damper is tested one time under normal air flow conditions for design verification.

The initial normal air flow test was conducted on dampers which have been in service between 0 and 17 years without any noticed effect from aging.

Ten percent of the fire dampers listeo in Table FD-1 will be tested statically every 18 months to provide continued damper operability.

Should more than 15% of the dampers tested fail to close, an additional 10% of t,, listed dampers shall be tested until the quantity of failed dampers is less than 15% of the quantity tested.

An engineering review shall also be conducted to evaluate the reasons for damper failure.

r--

5.0 EVALUATION 5.1 Installed Configurations The relative location of components in a ventilation system can affect the outcome of fire damper testing.

The components to be considered are the fan, fire damper, inspection port and ventila-tion grill.

By reviewing fire dampers installed at PBNP, we have determined that seven types of installed contigurations exist.

These configurations are shown on Figure FD-1.

5.2 Flow Characteristics We have evaluated the flow characteristics for each fire damper

' which is expected to close under normal air flow conditions.

These characteristics are listed in Table FO-2.

Since pressure drop across the damper has the major effect on damper closure capability, we conclude that if a damper of a given configuration has been success-fully tested at a specific pressure drop, all dampers of the same configuration which are subject to the same or lesser pressure drops will also be operable under normal air flow conditions.

5.3 Other Effects Several fire dampers have been functionally tested as part of Halon fire suppression system discharge testing.

This testing provides added assurance that these dampers will function as designed.

Where

(

f a datper which is expected to close against normal air flow is in-stalled-in a branch parallel to a multi section damper located in the same fire zone, the damper will operate because the fan which is common to both dampers will be shutdown.

These-effects are also identified in Table FD-2.

5.4 Fi pre FD-1 Evaluation 2

a) lietail (a) depicts fire dampers which are located in the fire barrier without connecting ductwork.

This configuration can be tested from either side of the fire barrier without affecting air flow through the damper.

Therefore we concluded that dampers which are installed in accordance with Detail (a) and which have been tested under normal air flow conditions are operable, b) Detail (b) depicts fire dampers which are located in one branch of a multibranch duct system.

These fire dampers and fire dampers which are installed in the other branches are not exposed to a common fire area.

Therefore, during damper closure an air flow i

path alternate to the affected damper is assured.

During a test i

an open inspection port would increase air flow through the damper in a conservative manner.

A successful test under this condition demonstrates damper operability.

Reaching into the duct to actuate or observe damper closure would obstruct flow in a noncon-servative manner.

For this condition, flow would increase through

].

the alternate branch just as it would for damper closure under normal air flow conditions and the effect on the total ventilation

t p-n-.

,n-

,.e c.-

a

i systea perforaance would b2 negligible.

Thsrefore, we concluded that dampers which are installed in accordance with Detail (b) are tested equivalent to normal air flow conditions and are operable.

Damper qualification by pressure drop exposure is not applicable to Detail (b) configurations.

c) Detail (c) depicts fire dampers which are located in one branch of a multibranch duct system.

These fire dampers and fire dampers which are installed in the other branches are not exposed to a common fire area.

Therefore during damper closure an air flow path alternate to the affected damper is assured.

During a test an open inspection port would increase air flow through the damper in a conservative manner.

A successful test under this condition f

derr.onstrates damper operability Reaching into the duct to actuate t

or observe damper closure would obstruct flow in a nonconservative manner.

For this condition, flow would increase through the

[

alternate branch just as it would for damper closure under normal i

air flow conditions and the effect on the total ventilation system i

performance would be negligible.

Therefore, we conclude that i

dampers which are installed in accordance with Detail (c) are tested equivalent to normal air flow conditions and are operable.

l Damper qualification by pressure drop exposure is not applicable t

i to Detail (c) configurations, d) Detail (d) depicts fire dampers which are located downstream of all ventilation openings and inspection ports.

During a test an j

open inspection port would increase air flow through the damper in a conservative manner, A successful test under this condition

[

I l

J l

demonstrates damper operability.

Reaching into the duct to actuate or observe damper closure would obstruct flow in a noncon-servative manner.

The sizes of the duct, inspection port and obstruction are variables which determine the conservatism of air flow during damper testing.

These variables would have to be known and evaluated for individual damper tests in order to achieve a positive determination.

Altornatively, we have reevaluated the actual configuration for individual dampers which are installed in accordance with Detail (d).

The damper and inspection port arrangement for dampers 21 and 22 is shown on Figure FD-2a.

Because of the inspection port locations, these dampers would be tested without obstructing the air flow.

Because of the right angle turn in the normal flow path and the location of the inspection port, any opening during testing would result in conservative additional air flow.

Therefore we conclude that dampers 21 and 22 are operable.

The arrangement for damper 35 is shown on Figure FD-2b.

This damper can also be tested without obstructing the air flow.

Because of the right angle turn in the normal flow path and the location of the inspection port, any opening during testing would result in conservative additional air flow.

Therefore, we conclude that damper 35 is operable.

e) Detail (e) depicts fire dampers which are located upstream of all ventilation openings and inspection ports.

During testing an open inspection port, would increase air flow through the damper in a conservative manner.

A successful test under this condition demonstrates damper operability.

Reaching irito the duct to

actuate or observe closure would obstruct flow in a nonconservative manner.

The sizes of the duct, inspection port and obstruction are variables which determine the conservatism of air flow during damper testing.

These variables would have to be known and eval-uated for individual damper tests in order to achieve a positive determination.

Alternatively we have reevaluated the actual configuration for fire dampers which are installed in accordance with Detail (e).

The damper and inspection port arrangement for damper 34 is shown on Figure FD-2c.

Because of the proximity of the inspection port to the fire damper, this damper can be tested without obstructing the air flow.

Therefore we concluded that damper 34 is operable, f) Detail (f) depicts fire dampers which are located between the inspection port and the ventilation grill upstream of the fan.

The inspect e t port is the only Cuct opening between the damper and the fan.

An open inspection port or an obstruction in the duct would decrease air flow through the damper in a nonconservative manner.

Dampers 31, S2 and 33 are installed in accordance with Detail (f).

The installed configuration is identical for these dampers except for damper size.

The configuration for damper 33 is shown on Figure FE-2d.

The purpose of these fire dampers is to protect the interior of the control building from an exposure fire on the roof.

The dampers are installed below normally closed shut-off dampers which were removed for fire damper installation and testing.

Testing without the normal shutoff damper resistance to flow was conservative.

The fact that these dampers were tested

?

with air flow was a conservative action because the design function of these dampers is to close under a no air flow condi-tion.

Therefore, we concluded that dampers 31, 32 and 33 are operable.

t-While this evaluation has demonstrated the operability of fire dampers listed above, it does not provide justification for future installations.

In the future, installation of fire dampers which must close against air flow should not be installed in accordance l

with detail (f).

i i

g) Detail (g) depcits fire dampers which are located between the inspection port and the ventilation grill down stream from the fan.

The inspection port is the only duct opening between the fan and the damper.

An open inspection port or an obstruction in the duct would decrease air flow through the damper in a nonconservative i

manner.

Dampers 11A, 12A, 13A, 14A, 15A and 16A are installed i

in accordance with detail (g).

The configuration for damper 11A, s

which is exposed to the largest pressure drop requirement is shown on Figure FO-2e.

We have retested this damper with the inspec-tion port opening sealed except for passage of the damper trip wire.

The damper closed successfully.

Therefore we concluded that dampers installed in accordance with detail (g) which must close against an air flow pressure drop less than.264 inches of water are operable.

In the future, fire dampers which must close against higher air flow pressure drops should not be installed in accordance with detail (g).

r I

.s

6.0 CONCLUSION

i This Technical Evaluation demonstrates that fire dampers installed at PBNP prior to January 1, 1988, which are expected to close against normal 3

air flow, have been tested in a manner which provides adequate assurance that the dampers will operate as required.

Fire dampers which are installed after January 1,1988 shall be installed in accordanco with Figures FD-2a, b or e or shall be tested in accordance with Operating Instruction 01-88, Fire Dampers.

i l

-=

TABLE FD-1 I

PBNP FIRE DAMPER STUDY Damper Install.

Penetra-Survey HVAC Damper Fusible Test Fan Off Associated Associated No.

Docu.

tion No.

Owg.

Dwg.

Rating Rating Condition or other Fan Area 4

1 MR 83-151 51 M-7-4-40 M-116 3 Hour 212F Norm Air flow N/A W30A&B U1 Chg. Pump Rm 2

MR 83-151 El M-7-4-41 M-116 3 Hour 212F Norm Air Flow N/A W30A&B U1 Chg. Pucp Rm 3

MR 83-151 S1 M-7-4-39 M-116 3 Hour 212F-Norm Air Flow N/A W30A&B U1 Chg. Pump Rm 4

MR 83-151 N1 M-7-4-38 M-116 3 Hour 212F Norm Air Flow N/A W30A&B U1 Chg. Pump Rm 5

MR 83-151 N1 M-2007-6-47 M-122 3 Hour 212F Norm Air Flow N/A W30A&B U2 Chg. Pump Rm 6

MR 83-151 51 M-2007-6-48 M-122 3 Hour 212F Norm Air Flow N/A W30A&B U2 Chg. Pump Rn 7

MR 83-151 S1 M-2007-6-49 M-122 3 Hour 212F Norm Air Flow N/A W30A&B U2 Chg. Pump Rm 8

MR 83-151 51 M-2007-6-50 M-122 3 Ho.r 212F Norm Air Flow N/A W30A&B U2 Chg. Pump Rm 9

MR 83-151 E5 M-7-4-14 M-116 3 Hour 212F Static MR 86-127 IW98 PAB El 8 Area 4 10 MR 83-151 F1 M-7-4-47 M-116 3 Hour 212F Static MR 86-127 IW9B PAB El 8 Area 4 11 MR 83-151 E7 M-7-4-14 M-116 3 Hour 212F Static MR 86-127 IW9C PAB El 8 Area 4 12 MR 83-151 N

M-5-4-1 M-116 3 Hour 212F Static MR 86-127 IW9C PAB El 8 Area 4 13 MR 83-151 E2 M-7-4-11 M-116 2 Hour 212F Static MR 86-127 1W90 PAB El 8 Area 4 14 MR 83-151 F31 M-0-40 M-116 3 Hour 212F Static MR 86-127 IW9D PAB El 8 Area 4 15 MR 83-151 El M-2007-6-15 M-122 3 Hour 212F Static MR 86-127 2W9C Cryogenic Rm 16 MR 83-151 F1 M-2007-6-46-3 M-122 3 Hour 212F Static MR 86-127 2W9C Cryogenic Rs 17 NR 83-151 52 M-7-4-13 M-116 3 Hour 212F Static MR 86-127 W30A&B PAB El 8 Area 4

'6 MR 83-151 513 M-7-4-13 M-116 3 Hour 212F Static MR 86-127 W27A&B PAB E1 8 Area 4 19 MR 83-151 518 M-7-4-13 M-116 3 Hour 212F Static MR 86-127 W32 PAB El 8 Area 4 20 MR 83-151 W3 M-7-4-15 M-116 3 Hour 212F Static MR 86-127 W30A&B PAB El 8 Area 4 21 MR 83-151 N1 M-7-3-67 M-111 3 Hour 212F Norm Air Flow N/A W10A Battery Rm 22 MR 83-151 N1 M-7-3-69 M-111 3 Hour 212F Norm Air Flow N/A W108 Battery Rs 23 MR 85-015-1 M

M-5-4-1 M-116 3 Hour 165F Static MR 86-127 W27A&B PAB El 8 Area 4 24 MR 85-015-1 G

M-5-4-1 M-116 3 Hour 165F Norm Air Flow N/A W27A&B PAB El 8 Area 4 25 MR 85-015-1 F9 M-1-3-53 M-109 3 Hour 165F Static MR 86-127 W13A1&A2 HVAC Equip Rm 26 MR 85-015-1 F1 M-0-39 M-110 3 Hour 165F Static MR 86-127 W13A1&A2 HVAC Equip Rm 27 MR 85-015-1 F9 M-1-3-53 M-109 3 Hour 286 Static MR 86-127 W13A1&A2 Control Rm 28 MR 85-015-1 F1 M-0-39 M-110 3 Hour 286 Static MR 86-127 W13A1&A2 Control Rm 29 MR 85-015-1 F9 M-1-3-53 M-109 3 Hour 165F Static MR 86-127 W13Bl&B2 HVAC Equip Rm 30 MR 85-015-1 F9 M-1-3-53 M-103 3 Hour 286 Static MR 86-127 W1381&B2 HVAC Equip Rm 31 MR 85-015-2 C19 M10-3-54 M-5004 3 Hour 286 Norm Air Flow N/A W13C Cont. Bldg. Roof:

32 MR 85-015-2 C18 M10-3-54 M-5004 3 Hour 286 Norm Air Flow N/A W13C Cont. Bldg. Roof!

33 MP. 85-015-2 C17 M-10-3-54 M-5004 3 Hour 286 Norm Air Flow N/A W13C Cont. Bldg. Roof) 34 MR 85-015-3 F7 M-1-3-53 M-109 3 Hour 165F Norm Air flow N/A WIS Control Rm

TABLE FD-1 (Cont'd. )

i PBNP FIRE DAMPER STUDY Damper Install.

Penetra-Survey HVAC Damper Fusible Test Fan Off Associated Associated No.

Docu.

tion No.

Dwg.

Dwg.

Rating Rating Condition or other Fan Area 35 MR 85-015-3 N6 M-7-3-15 M-111 3 Hour 165F Norm Air flow N/A Wil Air Comp Rm 36 MR 85-015-3 Si M-1-3-50 M-109 3 Hour 165F Norm Air Flow N/A W13Bl&B2 Comp Rm 37 MR 85-015-4 52 M-1-3-50 M-109 3 Hour 165F Norm Air Flow N/A W13Bl&B2 Comp Rm 1A MR 613 57 M-7-3-9 M-111 3 Hour 160F Norm Air Flow N/A N/A El 8 Bat Rs [

2A MR 613 53 M-7-3-10 H-111 3 Hour 160F Norm Air Flow N/A N/A El 8 Bat Rm C 3A MR 613 56 M-7-3-3 M-111 3 Hour 160F Norm Air Flow N/A N/A El 8 AFP Rm O 4A MR 613 E13 M-7-3-4 3 Hour 160F Norm Air Flow N/A N/A E1 8 AFP Ro [

SA MR 613 W8 M-7-3-22 3 Hour 160F Norm Air Flow N/A N/A El 8 AFP Rm O 6A MR 613 E49 M-7-3-23-1 M-111 3 Hour 160F Norm Air Flow N/A N/A El 8 AFP Rm 0 7A MR 613 E48 M-7-3-23-2 M-111 3 Hour 160F Norm Air Flow N/A N/A El 8 AFP Rm 0 8A MR 622 N5 M-5-3-31 N/A 3 Hour 160F N/A N/A N/A CR North Wind 9/.

MR 622 512 M-5-3-32 N/A 3 Hour 160F N/A N/A N/A CR South Wind 10A MR 622 E7 M-5-3-33 N/A 3 Hour 160F N/A N/A N/A CR East Windo 11A Orig.Constr F12 M-5-3-30 M-110 1.5 Hour 160F Norm Air Flow N/A HX65A DG Rm Heating 12A Orig.Constr F11 M-5-3-30 M-110 1.5 Hour 160F Norm Air Flow N/A HX65A DG Rm Heating 13A Orig.Constr F8 M-5-3-30 M-110 1.5 Hour 160F Norm Air Flow N/A HX65B DG Rm Heating 14A Orig.Constr F7 M-5-3-30 M-110 1.5 Hour 160F Norm Air Flow N/A HX65B DG Rm Heating 15A Orig.Constr F2 M-5-3-30 M-110' 1.5 Hour 160F Norm Air Flow N/A HX78 Air Comp Rm Heating 16A Orig.Constr F1 M-5-3-30 M-110 1.5 Hour 160F Norm Air Flow N/A HX78 Air Comp Rm Heating 17A Orig.Constr F14 M-5-3-30 M-110 1.5 Hour 165F Static N/A W12A DG Air Exhaus IBA Orig.Constr F14 M-5-3-30 M-110 1.5 Hour 165F Static N/A W12A DG Air Exhaus 19A Orig.Constr F14 M-5-3-30 M-110 1.5 Hour 165F Static N/A W128 DG Air Exhaus 20A Orig.Constr F14 M-5-3-30 M-110 1.5 Hour 165F Static N/A W12B DG Air Exhau2 21A Orig.Constr F13 M-5-3-30 M-110 1.5 Hour 165F Static N/A W12C DG Air Exhaus 22A Orig.Constr F13 M-5-3-50 M-110 1.5 Hour 165F Static N/A W12C DG Air Exhaus 23A Orig.Constr F13 M-5-3-30 M-110 1.5 Hour 165F Static N/A W120 DG Air Exhaus 24A Orig.Constr F13 M-5-3-30 M-110 1.5 Hour 165F Static N/A W12D DG Air Exhaus 25A MR 784 58 M-2005-6-37 EB45A-5 3 Hour 160F Norm Air Flow N/A AHU1A&lB White Invert 26A MR 784 E7 M-2005-6-38B EB45A-5 3 Hour 160F Norm Air Flow N/A AHU1A&lS White Invert 27A MR 784 C14 M-2005-6-44B EB45A-5 3 Hour 160F Norm Air Flow N/A AHULA&la Yellow InverG 28A MR 784 CIS M-2005-6-448 EB45A-5 3 Hour 160F Norm Air Flow N/A ANU1A&lB Yellow InverQ 29A MR 784 E7 M-2005-6-388 EB45A-5 3 Hour 160F Norm Air Flow N/A AHU1A&lB DIOS Bat Rm

. TABLE FD-1 (Cont'd.)

PBND FIRE DAMPER STUDY Damper Install.

Penetra-Survey HVAC Damper Fusible Test Fan Off Associated Associated No.

Docu.

tion No.

Dwg.

Dwg.

Rating Rating Condition or other Fan Area l

30A MR 784 N12 M-2005-6-18 EB45A-5 3 Hour 160F Norm Air Flow N/A AHU1A&lB DIOS Bat Rm 31A MR 784 54 M-2005-6-41 EB45A-5 3 Hour 160F Norm Air Flow N/A AHU1A&l8 D106 Bat Rm 32A MR 784 E22 M-2005-6-20 EB45A-5 3 Hour 160F Norm Air Flow N/A AHU1A&lB 0106 Bat Rm

)

l i

TABLE FD-2 Damper Size Air Flow Velocity Press. Drop Section

. Velocity Press. Drop FD-1 Configuration No.

In.

cfm fpm In. Water In.

fpm In. Water Installed Evaluated [

a

)

l 1

16x34 7460 1975

.120 16x17 3950

.433 b

b 2

18x34 8260 1944

.120 18x17 3887

.433 b

b 3

20x34 9060 1919

.120 20x17 3836

.400 b

b 4

20x36 9860 1972

.120 20x18 3944

.433 b

b j

5 6x12 300 600

.012 6x12 600

.012 b

b 6

8x18 1000 1000

.030 8x18 1000

.030 b

b 3

7 12x18 1700 1134

.034 12x18 1134

.034 b

b 8

12x24 2400 1200

.037 12x24 1200

.037 b

b 21 I?x12 470 470

.019 12x12 470

.019-d a,d 22 12x12 470 470

.319 12x12 470

.019-d a,d 24 14x30 4050 1388

.054 14x30 1388

.054 c

a(2)'

31 30x30 12000 1920

.120 30x30 1920

.120 f

f 32 30x30 12000 1920

.120 30x30 1920

.120 f

f 33 18x30 12000 3200

.296 18x30 3200

.296.

f

.f-34 6x18 550 734

.017 6x18 734

.017 e

a,e 35 22x25 2200 576

.012 22x25 576

.012 d

a,d

~

36 18x36 5500 1222

.037 18x36 1222

.037-b b

3 37 18x30 5500 1467

.060 18x30 1467

.060 c

c 1A 12x24 470 235

.002 12x24 235

.002 a

a 2A 12x24 470 235

.002 12x24 235

.002 a

a

- (1) 3A 18x24 940 313

.003 18x24 313

.003 a

a l

4A 12x12 300 300

,003 12x12 300

.003 a

a(1)

SA 12x12 300 300

.003 12x12 300

.003 a

a(1) 6A 20x30 3750 900

.025 20x30 900

.025 c

c(1) 7A 30x36 2810 375

.005 30x36 375

.005-a a(1) i 11A 12x12 1500 1500

.060 12x12 3000

.264 g

g 12A 12x12 1500 1500

.060 12x12 3000

.264 g

g 13A 12x12 1500 1500

.060 12x12 3000-

.264 g.

g 14A 12x12 1500 1500

.060 12x12 3000

.264 g

g.

15A 12x12 1150 1150

.034 12x12 2300

.124 g

9 16A 12x12 1150 1150

.034 12x12 2300

.124 g

g i

25A 16x24 3230 1210

.037 16x24 1210

.037 b

b 26A 8x24 3230 2422

.147 8x24 2422 147 b

b 27A 12x20 2550 1530

.055 12x20 1530

.065 b

b 28A 16x16 2550 1435

.057 16x16 1435

.057 b

b

TABLE FD-2 (Cont'd.)

~

Damper Size Air Flow Velocity Press. Drop Section Velocity Press. Drop FD-1 f.'nfiguration.

No.

In.

cfm fpm In. Water In.

fpm In. Water Installed: Fvaluated" 29A 12x12 1840 1840

.090 12x12 1840

.090 b

b 30A 12x16 1840 1380

.054 12x16 1380

.054 a

a-31A 12x16 15?0 1140

.034 12x16 1140

.034 b-b 32A 12x12 1520 1520

.065 12x12 1520

.065 a

a (1) Damper functionally tested during Halon fire suppression system discharge tests.

(2) Shutdown of fans W-27A&B enhances damper operability.

' x FIGURE FD-l Legend O ra n IS'

&l damper

' _ ' in spect ion pcr t E grtlI

( a) s lll

/

131 x

/

F

( b)

(c) q lsl f

Isl

//

ii

,i (d)

(e) g 131 81

/,

k (f)

(g)

FIGURE F D-2 a LEGEND f)

WALL kN 3-HR FIRE BLkRIE R n. F A N.

03

{

BACK DRLF T DAMPER l2l FI R E !>4 M P E R I AG PECTICU PCRT

/

- g-1z"

/

/

/

f NN

/

1

(

[,

, -(

) \\

.< flEh_

b>

j i

i l

/

\\Ns i

q"

.,q fg, x

g

,c'

)

/

J 5!DE FROUT E L E VA T ION E L EVATI QU EQR.21 (04 - 83)

FIG URE FD-2b i

LEGEND

/y WALL 060 FAl4 FIRE DAMPE F INS PECTIOt) PDRT J

f

,' /,

-usu av

/

//

/

/

/

,' /

j 7

N

[

1 FLO W N

\\

j N

kb so" i

/

/

1

/

l ',/

y 42' A

/

a'

,/

,/

s nr E mu r E L E 'iAT 131:

ELE',hiION EQO.21 (04 83)

FIG UR E FD-2c L E G E tJ.?

/

FLCOR

\\ '\\j F l H r. DAM P E R lh EF ECTl01) PORT t

t r

)

no g

i x 0c cc 12."

=

)

0 m

(u 1

/,-

-/,/

o/

y\\! ',',. x 4

~~ ~~~~~~~

/ 3s

,/

/

/

./

7 1

4-6 ",

18" i

f

$lDE FRDtlT ELEVAT10//

E L E VATI0l/

l EQQ-21 (N-83)

x x.,

4 FIG UR E FD 2 d LEGEND

\\/

[,

FLOCR ib A StiUTOF: DAM F E R s/j FIR E DAM PE R INSPE CTION PORT 3

e l

l i

9

=o, FLOW TO TAN t

m N

e 16" l

u

\\

e H

I 1

e 30" E

is" i

l.

.-. _.,~~~~,~- _

}

_f

_s s s s s s s s 1 i

e

,~

)-

V1 t

/

l l

l SIDE FRoni E L E VI, T10 fl E L E VI,T t0N 1

eon.n l

h

~

FIGUR E FD-2 e L E G E 1, D f,j FLO.7P

[\\]

FIF:E PA MPE R

}

INSFE C TICl) POR T 4

/

I 2 ".li a.

18 S n.

O' g"

A r-2 PP l'vN l#C i l

i r

l I

z 1

e i

C ct i2" dia A6" 1

Sc h. 40 c

E 1

/

/

y. -

/

s s

4

[

I f.

1 j

t v

0IUU F R ol:T E L E '/h il'I, EL E V ATION E OO-21 (04 - 83)