Category:INTERNAL OR EXTERNAL MEMORANDUM
MONTHYEARML20195G4251999-06-0707 June 1999 Notification of 990617 Meeting with Licensee in Rockville,Md to Discuss Licensing Requirement on Keff ML20203B1991999-02-0404 February 1999 Notification of 990216 Meeting with W Electric Corp in Rockville,Md to Discuss Changes Proposed in Rev 10 of License Application ML20217A8871998-03-19019 March 1998 Notification of 980331 Meeting W/Westinghouse Electric Corp in Columbia,Sc,To Discuss Licensing Issues Raised by Westinghouse ML20248J6341997-11-20020 November 1997 Notification of 980109 Meeting W/W in Rockville,Md to Discuss Licensing Issues Raised by W ML20137X9381997-04-11011 April 1997 Notification of 970415-17 Meeting W/W in Columbia,Sc for Licensing Visit - Process Tour ML20134C0611996-09-20020 September 1996 Forwards Short Paper Summarizing Observations & Conclusions Reached by Team of Staff Members,Who Recently Visited Westinghouse ML20198D0661992-05-12012 May 1992 Requests Assistance in Preparation of SER for License Amend in June 1992 Re Rev 2 to Site Emergency Plan,Section 3 ML20058F9231990-11-0707 November 1990 Advises of Completion of Review of Westinghouse 900702 Amend Application Requesting Change to Existing K(Eff) Limit for One Station at Columbia Fuel Fabrication Facility.Limit Would Be Raised from 0.95 to 0.98 ML20248E3281989-10-0202 October 1989 Documents That Neither Environ Assessment Nor Environ Impact Statement Needed for Proposed Rev to Radiological Contingency Plan.Effectiveness of Plan Not Reduced by Revs ML20245G3191989-04-25025 April 1989 Discusses 890417 Telcon W/W Goodwin & E Reitler Re Westinghouse Safety Assessment.Suggests That Concerns About Fees Be Addressed to Senior Mgt Either in Region II or NMSS ML20151Z6471988-08-25025 August 1988 Advises That Westinghouse 880812 Annual Rev to Radiological Contingency Plan Met Listed Conditions & That Neither Environ Assessment Nor Environ Impact Statement Warranted for Subj Proposed Action ML20207F5321988-08-17017 August 1988 Advises That Region II Repts on Westinghouse Fnmc Plan Changes Submitted Under Provision of 10CFR70.32(c) Technically Sound.Revised License Condition Will Be Issued to Westinghouse.Memo Encl.Memo Withheld (Ref 10CFR2.790) ML20150E0271988-07-0808 July 1988 Discusses Categorical Exclusion for Revised Radiological Contingency Plan.Neither Environ Assessment Nor Environ Impact Statement Warranted for Proposed Action ML20237K9241987-08-25025 August 1987 Informs That Environ Assessment & EIS Unnecessary for 870723 Application & 870814 Suppl to Amend License SNM-1107 Re Calcium Fluoride Processing ML20237K0021987-08-14014 August 1987 Advises That Vendor 870626 Application for Amend to License SNM-1107,authorizing Use of Radioactive Matls in Southwest Columbia Site Expansion Acceptable.No Environ Assessment or EIS Warranted ML20237J9871987-08-14014 August 1987 Advises That Vendor 870619 Application for Amend to License SNM-1107,authorizing Use of Radioactive Matls at Southeast Extension of Columbia Site Acceptable.No Environ Assessment or EIS Warranted ML20234B6541987-06-29029 June 1987 Advises That 870415 Application for Amend to License SNM-1107,changing License Conditions Re UF6 Handling Controls Does Not Warrant Environ Assessment Nor EIS ML20214J4391987-05-20020 May 1987 Advises That Environ Assessment & EIS Not Warranted for Westinghouse Request for Amend to License SNM-1107, Authorizing Release of Spent Hydrofluoric Acid for Reuse Under Controlled Conditions at Two Designated Facilities ML20213G2981987-05-12012 May 1987 Discusses Categorical Exclusion for 870424 Request for Amend to License SNM-1107 to Authorize Release of Calcium Fluoride Containing Trace Amounts of Enriched U.Amounts Below 30 Pci/G Limit for Unrestricted Release ML20209E6781987-04-27027 April 1987 Advises That Neither Environ Assessment or EIS Necessary for 870401 Application for Amend to License SNM-1107, Incorporating Leak Test Requirements for Sealed Plutonium Sources ML20207R1201987-03-0606 March 1987 Advises of Categorical Exclusion for 860922 Amend 4 to License SNM-1107,revising Columbia Site Emergency Plan. Neither Environ Assessment Nor EIS Warranted for Proposed Action ML20212L1041987-03-0505 March 1987 Responds to 861002 Suggestion That Position on Acceptance Criteria for Determinations of Representative Air Sampling Be Documented in Branch Technical Position.Different Methods Should Be Combined w/site-specific Characteristics ML20215L9421987-03-0202 March 1987 Forwards Author Feeder Rept Re 870114-16 Onsite Team Assessment.Preliminary Findings Include Two Potential Items of Noncompliance & Two Safety Issues That Should Be Pursued by Region II ML20209B8531987-01-27027 January 1987 Advises That Advanced Nuclear Fuels Corp Does Not Use Vacuum Pumps for UF6.C-E,GE & Westinghouse Use Vacuum Pumps Only on UF6 Cold Trap Sys.Oil in Vacuum Pumps DOE-approved ML20213E2511986-10-0202 October 1986 Requests Interpretation of What Constitutes Appropriate Air Sampling Techniques & Appropriate Acceptance Criteria to Resolve Concerns Re License Renewal & Provide Clarification for Licensees ML20209D6311986-09-0303 September 1986 Concludes That Listed Conditions Re 860808 Application to Amend License SNM-1107 on Positive Pressure Gloveboxes Have Been Met.Neither Environ Assessment Nor EIS Warranted NUREG-1198, Forwards Questionnaire & Results of Telcon Surveys Conducted on 860801-04,per NUREG-1198,in Response to Recipient Request1986-08-0707 August 1986 Forwards Questionnaire & Results of Telcon Surveys Conducted on 860801-04,per NUREG-1198,in Response to Recipient Request ML20198S9611986-05-28028 May 1986 Advises That Environ Assessment or EIS Unwarranted for Westinghouse 860423 Application for Amend to License SNM-1107 to Grant Limited Exemption from Continuous Surveillance Described in Section 4.2 ML20128M8751985-07-18018 July 1985 Discusses Categorical Exclusion for Amend Request Re Addition of Two Uranyl Nitrate Storage Tanks.Neither Environ Assessment Nor EIS Required ML20128C1291985-06-19019 June 1985 Submits Items of Interest.Meetings on 850618,13 & 13 w/C-E, Duquesne Light Co & Westinghouse,Respectively Re Licensing Actions Summarized.Doe Draft Transportation Business Plan Received for Comment ML20062D3271982-07-27027 July 1982 Discusses Vendor Intent to Release 1,875 Lb Molybdenum Scrap After 820721.Release Acceptable ML20141G8321978-05-26026 May 1978 Advises That Fees Normally Charged for Review & Approval of Matls Control & Accounting Programs Being Waived Due to 2-yr Licensing Delay ML20248G2311968-10-14014 October 1968 Provides Comments Re Us Nuclear Corp,Docket 7001151,proposed Packaging for Shipment of Pu-238-Be Neutron Sources to Mound Laboratory 1999-06-07
[Table view] Category:MEMORANDUMS-CORRESPONDENCE
MONTHYEARML20195G4251999-06-0707 June 1999 Notification of 990617 Meeting with Licensee in Rockville,Md to Discuss Licensing Requirement on Keff ML20203B1991999-02-0404 February 1999 Notification of 990216 Meeting with W Electric Corp in Rockville,Md to Discuss Changes Proposed in Rev 10 of License Application ML20217A8871998-03-19019 March 1998 Notification of 980331 Meeting W/Westinghouse Electric Corp in Columbia,Sc,To Discuss Licensing Issues Raised by Westinghouse ML20248J6341997-11-20020 November 1997 Notification of 980109 Meeting W/W in Rockville,Md to Discuss Licensing Issues Raised by W ML20137X9381997-04-11011 April 1997 Notification of 970415-17 Meeting W/W in Columbia,Sc for Licensing Visit - Process Tour ML20134C0611996-09-20020 September 1996 Forwards Short Paper Summarizing Observations & Conclusions Reached by Team of Staff Members,Who Recently Visited Westinghouse ML20198D0661992-05-12012 May 1992 Requests Assistance in Preparation of SER for License Amend in June 1992 Re Rev 2 to Site Emergency Plan,Section 3 ML20058F9231990-11-0707 November 1990 Advises of Completion of Review of Westinghouse 900702 Amend Application Requesting Change to Existing K(Eff) Limit for One Station at Columbia Fuel Fabrication Facility.Limit Would Be Raised from 0.95 to 0.98 ML20248E3281989-10-0202 October 1989 Documents That Neither Environ Assessment Nor Environ Impact Statement Needed for Proposed Rev to Radiological Contingency Plan.Effectiveness of Plan Not Reduced by Revs ML20245G3191989-04-25025 April 1989 Discusses 890417 Telcon W/W Goodwin & E Reitler Re Westinghouse Safety Assessment.Suggests That Concerns About Fees Be Addressed to Senior Mgt Either in Region II or NMSS ML20151Z6471988-08-25025 August 1988 Advises That Westinghouse 880812 Annual Rev to Radiological Contingency Plan Met Listed Conditions & That Neither Environ Assessment Nor Environ Impact Statement Warranted for Subj Proposed Action ML20207F5321988-08-17017 August 1988 Advises That Region II Repts on Westinghouse Fnmc Plan Changes Submitted Under Provision of 10CFR70.32(c) Technically Sound.Revised License Condition Will Be Issued to Westinghouse.Memo Encl.Memo Withheld (Ref 10CFR2.790) ML20150E0271988-07-0808 July 1988 Discusses Categorical Exclusion for Revised Radiological Contingency Plan.Neither Environ Assessment Nor Environ Impact Statement Warranted for Proposed Action ML20237K9241987-08-25025 August 1987 Informs That Environ Assessment & EIS Unnecessary for 870723 Application & 870814 Suppl to Amend License SNM-1107 Re Calcium Fluoride Processing ML20237K0021987-08-14014 August 1987 Advises That Vendor 870626 Application for Amend to License SNM-1107,authorizing Use of Radioactive Matls in Southwest Columbia Site Expansion Acceptable.No Environ Assessment or EIS Warranted ML20237J9871987-08-14014 August 1987 Advises That Vendor 870619 Application for Amend to License SNM-1107,authorizing Use of Radioactive Matls at Southeast Extension of Columbia Site Acceptable.No Environ Assessment or EIS Warranted ML20234B6541987-06-29029 June 1987 Advises That 870415 Application for Amend to License SNM-1107,changing License Conditions Re UF6 Handling Controls Does Not Warrant Environ Assessment Nor EIS ML20214J4391987-05-20020 May 1987 Advises That Environ Assessment & EIS Not Warranted for Westinghouse Request for Amend to License SNM-1107, Authorizing Release of Spent Hydrofluoric Acid for Reuse Under Controlled Conditions at Two Designated Facilities ML20213G2981987-05-12012 May 1987 Discusses Categorical Exclusion for 870424 Request for Amend to License SNM-1107 to Authorize Release of Calcium Fluoride Containing Trace Amounts of Enriched U.Amounts Below 30 Pci/G Limit for Unrestricted Release ML20209E6781987-04-27027 April 1987 Advises That Neither Environ Assessment or EIS Necessary for 870401 Application for Amend to License SNM-1107, Incorporating Leak Test Requirements for Sealed Plutonium Sources ML20207R1201987-03-0606 March 1987 Advises of Categorical Exclusion for 860922 Amend 4 to License SNM-1107,revising Columbia Site Emergency Plan. Neither Environ Assessment Nor EIS Warranted for Proposed Action ML20212L1041987-03-0505 March 1987 Responds to 861002 Suggestion That Position on Acceptance Criteria for Determinations of Representative Air Sampling Be Documented in Branch Technical Position.Different Methods Should Be Combined w/site-specific Characteristics ML20215L9421987-03-0202 March 1987 Forwards Author Feeder Rept Re 870114-16 Onsite Team Assessment.Preliminary Findings Include Two Potential Items of Noncompliance & Two Safety Issues That Should Be Pursued by Region II ML20209B8531987-01-27027 January 1987 Advises That Advanced Nuclear Fuels Corp Does Not Use Vacuum Pumps for UF6.C-E,GE & Westinghouse Use Vacuum Pumps Only on UF6 Cold Trap Sys.Oil in Vacuum Pumps DOE-approved ML20213E2511986-10-0202 October 1986 Requests Interpretation of What Constitutes Appropriate Air Sampling Techniques & Appropriate Acceptance Criteria to Resolve Concerns Re License Renewal & Provide Clarification for Licensees ML20209D6311986-09-0303 September 1986 Concludes That Listed Conditions Re 860808 Application to Amend License SNM-1107 on Positive Pressure Gloveboxes Have Been Met.Neither Environ Assessment Nor EIS Warranted NUREG-1198, Forwards Questionnaire & Results of Telcon Surveys Conducted on 860801-04,per NUREG-1198,in Response to Recipient Request1986-08-0707 August 1986 Forwards Questionnaire & Results of Telcon Surveys Conducted on 860801-04,per NUREG-1198,in Response to Recipient Request ML20198S9611986-05-28028 May 1986 Advises That Environ Assessment or EIS Unwarranted for Westinghouse 860423 Application for Amend to License SNM-1107 to Grant Limited Exemption from Continuous Surveillance Described in Section 4.2 ML20128M8751985-07-18018 July 1985 Discusses Categorical Exclusion for Amend Request Re Addition of Two Uranyl Nitrate Storage Tanks.Neither Environ Assessment Nor EIS Required ML20128C1291985-06-19019 June 1985 Submits Items of Interest.Meetings on 850618,13 & 13 w/C-E, Duquesne Light Co & Westinghouse,Respectively Re Licensing Actions Summarized.Doe Draft Transportation Business Plan Received for Comment ML20062D3271982-07-27027 July 1982 Discusses Vendor Intent to Release 1,875 Lb Molybdenum Scrap After 820721.Release Acceptable ML20141G8321978-05-26026 May 1978 Advises That Fees Normally Charged for Review & Approval of Matls Control & Accounting Programs Being Waived Due to 2-yr Licensing Delay ML20248G2311968-10-14014 October 1968 Provides Comments Re Us Nuclear Corp,Docket 7001151,proposed Packaging for Shipment of Pu-238-Be Neutron Sources to Mound Laboratory 1999-06-07
[Table view] |
Text
4
.. MEETING NOTICE June 7, 1999
< Licensee: Westinghouse Electric Company, LLC (WELCO)
Columbia Fuel Fabrication Division Docket: 70-1151 Date and Time: June 17,1999,1:00 p.m.
Location: U. S. Nuclear Regulatory Commission Two White Flint North 11545 Rockville Pike Room T-8 A-1 Rockville, MD 20850 Purpose of Meeting: To discuss licensing requirement on Keff.
NRC Attendees: Charles Gaskin, NMSS/FCSS Harry Felsher, NMSS/FCSS
' Other Attendees: W. L. Goodwin, WELCO R. W. Williams, WELCO N. Kent, WELCO NOTE: Meetings between the NRC staff and licensees are open for interested members of the public to attend as observers pursuant to " Staff Meetings Open to the Public Final Policy Statement, 59 Federal Reaister 48340, 9/20/94."
Contact:
Charles E. Gaskin,301-415-8116 4 Attendance at this meeting by other than those listed above should be made known by 10:00 a.m. EST June 16,1999, via phone to above contact.
cc: C. Paperiello, NMSS M. Virgilio, NMSS
{ 9 E. Ten Eyck, FCSS J. Piccone, FCSS J j
W. Goodwin (FAX COPY)
D. Ayers, Ril (copy e-mailed) f h (h- gJUP inn I E. McAlpine, Rll (copy e-mailed)
I,0 h
Distribution: \
Docket 70-1151 PUBLIC NRC File Center Region 11 NMSS r/f FCSS r/f LIB r/f HFelsher Madams IG:\ lib \WECmtg2.wpd] *See previous concurrence i LIB LIB LIB l OFC .
NAME CGaskin:mm/bv PShea9 fl CEmekh DATE '5/27/99 N /59 4/ 7 /99 9906160050 990607 PDR ADOCK 07001151 C PDR
p .
1, pm EE g $t UNITED STATES I j
i
- NUCLEAR REGULATORY COMMISSION
" WASHINGTON, D.C. 2066H001 t
l l \q 8 June 7, 1999 f- - MEETING NOTICE 1
\
l Licensee: Westinghouse Electric Company, LLC (WELCO)
Columbia Fuel Fabrication Division Docket: 70-1151 Date and Time: June 17,1999,1:00 p.m. l l Location: U. S,. Nuclear Regulatory Commission
! Two' White Flint North l 11545 Rockville Pike l
Room T-8 A-1 Rockville, MD 20850 i Purpose of Meeting: To discuss licensing requirement on Keff.
l NRC Attendees: Charles Gaskin, NMSS/FCSS )
Harry Felsher, NMSS/FCSS ;
l Other Attendees: W. L. Goodwin, WELCO l R. W. Williams, WELCO l N. Kent, WELCO !
NOTE: Meetings between the NRC staff and licensees are open for i interested members of the public to attend as observers pursuant to " Staff Meetings Open to the Public Final Policy Statement, 59 Federal Reaister 48340,9/20/94."
Contact:
Charles E. Gaskin,301-415-8116 Attendance at this meeting by other than those listed above should be made known by 10:00 a.m. EST June 16,1999, via phone to above contact.
cc: C. Paperiello, NMSS M. Virgilio, NMSS E. Ten Eyck, FCSS J. Piccone, FCSS W. Goodwin (FAX COPY)
D. Ayers, Ril (copy e-mailed)
E. McAlpine, Rll (copy e-mailed)
(
l P-
F~ ,
1-
, , c' MEETING NOTICE l . Licensee: Westinghouse ElectrL Company, LLC (WELCO)
Columbia Fuel Fabrication Division Docket: 70-1151
, Date and Time: June 17,1999,1:00 P.M.
1 Location: U. S. Nuclear Regulatory Commission Two White Flint North l 11545 Rockville Pike Room T-8 A-1 - I Rockville, MD 20850
[
Purpose of Meeting: To discuss licensing requirement on I I Charles Gaskin, NMSS/FCSS NRC Attendees:
Harry Felsher, NMSS/FCSS Other Attendees: W. L. Goodwin, WELCO/
R. W. Williams, WELCO N. Kent, WELCO
/
NOTE: Meetings between'the NRC staff and licensees are open for interested merpbers of the public to attend as observers pursuant to " Staff Meetings Open to the Public Final Policy Statement, 59 Federal Realster 48340, 9/20/94."
Contact:
Charle . Gaskin,301/415-8116 I Att dance at this meeting by other than those listed above
.sfiould be made known by 10:00 a.m. EST June 16,1999, via phone to above contact.
cc: C. Paperiell MS SS M.
E. Ten Virgilio, Eyck, NpFCSS_ !
J. Piccone/ FCSS W. Goodfin (FAX COPY)
D. Ayers, Ril (copy e-mailed) i E. McAlpine, Ril (copy e-mailed) i
/-
Distribtition:
Docket 70-1151 PUBLIC NRC File Center Region ll _
NMSS r/f FCSS r/f LIB r/f HFelsher Madams
'G:\ lib \WECmtg2.wpd] _
OFC LIB LIB LIB NAME C khm PShea CEmeigh DATE 5/2 7/99 5/ /99 5/ /99 l
O