ML20195E923

From kanterella
Jump to navigation Jump to search
Informs That Response to IE Bulletin 85-003 Will Be Provided 60 Days After NRC Acceptance of BWR Owners Group Methodology,To Be Completed by 860901
ML20195E923
Person / Time
Site: Peach Bottom  
Issue date: 06/02/1986
From: Kemper J
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
To: Muller D
Office of Nuclear Reactor Regulation
References
IEB-85-003, IEB-85-3, NUDOCS 8606090287
Download: ML20195E923 (1)


Text

r y

o 9

PHILADELPHIA ELECTRIC COMPANY 2301 M ARKET STREET P.O. BOX 6699 PHIL ADELPHI A. PA.19101 (2151841-4502 V IC E-PR ESID E N T

..mm..

.--o

<>=a c"

June 2, 1986 Docket No. 50-277 50-278 Mr. D. R. Muller, Director BWR Project Directorate //2 U. S. Nuclear Regulatory Commission Washington, DC 20555

SUBJECT:

Peach Bottom Atomic Power Station, Units 2 & 3 1.E.Bulletin 85-03

REFERENCE:

I.E. Bulletin No. 85-03 " Motor-Operated Valve Common Mode Failures During Plant Transients Due to Improper Switch Settings" FILE:

GOVT 1-1 NRC (IEB-85-03)

Dear Mr. Muller:

1.E.Bulletin 85-03 described " Motor-operated Valve common Mode Failures During Plant Transients Due to Improper Switch Settings".

This bulletin requested a response to Item a and the program and completion schedule for Items b through d.

We are working with the BWROG Committee on I.E.Bulletin 85-03 to develop a scope of systems, range of events, and associated set of assumptions to assure a thorough and consistent reply to this Bulletin for Peach Bottom 2 and 3.

The BWROG Committee on I.E.Bulletin 85-03 is scheduled to complete its existing scope of work by September 1, 1986. We plan to provide the Philadelphia Electric Co. response within 60 days after NRC acceptance of the BWROG Committee methodology addressing the concerns of I.E.Bulletin 85-03.

This response is in accordance with the conversation between D.

R. Helwig, Philadelphia Electric Company (PECo), and R. H. Vollmer, NRC, I&E on May 22, 1986. As discussed in that conversation, this response has been delayed beyond the original due date.

We. apologize for any inconvenience which may have been caused by this delay.

"*** 7' 8606090287 860602 PDR ADOCK 05000277

[/d PDR Y

- A t

I O HDH/mb/05298601