Company of Colorado 2420 W. 26th Avenue, Suite 100D, Denver, Colorado 80211 M;y 28, 1986 Fort St. Vrain Unit No. 1 P-86393 Director of Nuclear Reactor Regulation 1
U. S. Nuclear Regulatory Commission Washington, D.C.
20555 Attn: Mr. H.N. Berkow, Director Standardization and Special Projects Directorate Docket No. 50-267
SUBJECT:
10CFR50 Appendix R Fire Protection Modification
REFERENCES:
- 1) PSC Letter, Lee to Johnson, dated April 1, 1985 (P-85113)
- 2) PSC Letter, Lee to Johnson, dated September 3, 1985 (P-85305)
- 3) PSC Letter, Warembourg to Berkow, dated,
January 21, 1986 (P-86014)
Dear Mr. Berkow:
In previous correspondence (Reference 3), PSC has informed the NRC of the construction progress of the Fire Detection. System being installed at Fort St. Vrain. The installation of the Fire Detection System was scheduled to be completed on June 1, 1986. Due to delays by the manufacturer and supplier of the Fire Detection System, PSC will be unable to meet the scheduled completion date of June 1,1986.
kDk [hjCK 41 86052a 1
00000267 F
P-86393 Pagn 2 May 28, 1986 PSC will ' continue to follow this matter closely and expects to have the Fire Detection System installed and in service prior to plant start-up in September, 1986.
If you have any questions concerning this subject, please contact Mr. M. H. Holmes at (303) 480-6960.
Very truly yours, D /Y-TYwbf D.W.Warembourg,Mdager Nuclear Engineering Division DW/KB:pa
.