Text
_
Mr. J mes Knubel Chisf NuclxtOfficer November' 13, 1998 Pow:r Authority of tha State of New York 123 Main Street White Plains, NY 10601
SUBJECT:
JAMES A. FITZPATRICK NUCLEAR POWER PLANT - RESPONSE TO GENERIC LETTER 95-07," PRESSURE LOCKING AND THERMAL BINDING OF SAFETY-RELATED POWER-OPERATED GATE VALVES,"(TAC NO. M93464)
Dear Mr. Knubel:
On August 17,1995, the NRC issued Generic Letter (GL) 95-07, " Pressure Locking and Thermal Binding of Safety-Related Power-Operated Gate Valves," requesting that licensees take actions to ensure that safety-related power-operated gate valves that are susceptible to pressure locking or thermal binding are capable of performing their safety functions.
The New York Power Authority (NYPA, also known as the Power Authority of the State of New York) responded to GL 95-07 in letters dated October 16,1995, and February 13 and March 8, 1996, for the James A. FitzPatrick Nuclear Power Plant. The NRC staff requested additional information on May 29,1996, which was provided by NYPA on June 27,1996.
The NRC staff has reviewed these submittals and finds that NYPA has adequately addressed the actions requested in GL 95-07, as discussed in the enclosed safety evaluation.
If you have any questions regarding this matter, please contact me at (301) 415-1470.
Sincerely, ORIGINAL SIGNED BY:
Joseph F. Williams, Project Manager Project Directorate I-1 Division of Reactor Projects - l/11 Office of Nuclear Reactor Regulation i
Docket No. 50-333
Enclosure:
As stated cc w/ encl: See next page DISTRIBUTION:
Docket File S. Tingen PUBLIC I
PDI-1 R/F J. Zwolinski i
S[i J. Williams 4
T. Harris (e-mail SE to TLH3) j h hi M [
ACRS C. Hehl, RI DOCUMENT NAME: G:\\FITZ\\M93464.LTR To receive a copy of this document, indicate in the box: "C" = Copy without attachment / enclosure "E" = Copy with !
cttichment/ enclosure "N" = No copy 0FFICE PM:PD! 1
[j lE LA:PDlQ M l
D:PDI 1,,d l
l l
l NAME JWittiams/rst M SLitt W SBajwa 8 ' K 11/3/98 d
11/lb/98 11/ j f, /98 DATE 9e11180210 9e1113
'ficial Record Copy PDR ADOCK 05000333 P
PDR b
p ar UNITED STATES J
]
g NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 30856 4001 e..
+
November 13, 1998 i
Mr. James Knubel Chief Nuclear Officer Power Authority of the State of New York 123 Main Street White Plains, NY 10601 l
SUBJECT:
JAMES A. FITZPATRICK NUCLEAR POWER PLANT - RESPONSE TO GENERIC LETTER 95-07," PRESSURE LOCKING AND THERMAL BINDING OF SAFETY.
i RELATED POWER-OPERATED GATE VALVES," (TAC NO. M93464)
Dear Mr. Knubel:
j On August 17,1995, the NRC issued Generic Letter (GL) 95-07, " Pressure Locking and Thermal Binding of Safety-Related Power-Operated Gate Valves," requesting that licensees take actions to ensure that safety-related power-operated gate valves that are susceptible to pressure locking or thermal binding are capable of performing their safety functions.
l The New York Power Authority (NYPA, also known as the Power Authority of the State of New York) responded to GL 95-07 in letters dated October _16,1995, and February 13 and March 8, l
1996, for the James A. FitzPatrick Nuclear Power Plant. The NRC staff requested additional information on May 29,1996, which was provided by NYPA on June 27,1996.
The NRC staff has reviewed these submittals and finds that NYPA has adequately addressed the actions requested in GL 95-07, as discussed in the enclosed safety evaluation.
l if you have any questions regarding this matter, please contact me at (301) 415-1470.
Sincerely, Joseph F. Williams, Project Manager Project Directorate I-1 Division of Reactor Projects - 1/11 Office of Nuclear Reactor Regulation Docket No. 50-333
Enclosure:
As stated cc w/ encl: See next page
.:-z
.. _ _ _ _ _.. ~ _ _ _ _. _ _ _... _ _ -. _ _ _ _. _ _ _ _.
}
James Knubel James A. FitzPatrick Nuclear Power Authority of the State Power Plant of New York cc:
Mr. Gerald C. Goldstein Mr. F. William Valentino, President Assistant General Counsel-New York State Energy, Research, Power Authority of the State and Development Authority of New York Corporate Plaza West.
1633 Broadway 286 Washington Avenue Extension New York, NY 10019 Albany, NY 12203-6399 Resident inspector's Office Mr. Richard L. Patch, Director U. S. Nuclear Regulatory Ccmmission Quality Assurance P.O. Box 136 Power Authority of the State Lycoming, NY 13093 of New York 123 Main Street Mr. Harry P. Salmon, Jr.
White Plains, NY 10601 Vice President - Engineering Power Authority of the State Mr. Gerard Goering of New York 28112 Bayview Drive 123 Main Street Red Wing, MN 55066
- White Plains, NY 10601 Mr. James Gagliardo Ms. Charlene D. Faison Safety Review Committee Director Nuclear Licensing 708 Castlewood Avenue Power Authority of the State Arlington,TX 76012 of New York
' 123 Main Street Mr. Arthur Zaremba, Licensing Manager White Plains, NY 10601 James A. FitzPatrick Nuclear Power Plant Supervisor P.O. Box 41 Town of Scriba Lycoming, NY 13093 Route 8, Box 382 Oswego, NY 13126 Mr. Paul Eddy New York State Dept. of Mr. Eugene W. Zeltmann Public Service President and Chief Operating
. 3 Empire State Plaza,10th Floor Officer Albany, NY 12223 Power Authority of the State of New York Michael J. Colomb 99 Washington Ave., Suite No. 2005 Site Executive Officer Albany, NY 12210-2820 James A. FitzPatrick Nuclear Power Plant P.O. Box 41 Charles Donaldson, Esquire Lycoming, NY 13093 Assistant Attomey General New York Department of Law 120 Broadway New York, NY 10271
' Regional Administrator, Region i U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406