GPU Nuclear. Inc.
('
Houte 441 South NUCLEAR Post Office Box 480 Middletown. PA 17057 0480 Tel 717 944 7621 November 12, 1998 1920-98-20655 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 Gentlemen:
j
Subject:
Three Mile Island Nuclear Station, Unit 1 (TMI-1)
Docket 'No. 50-289 Operating License No. DPR-50 Schedule for Responding to the NRC's Request for Additional Information (RAI) Regarding Generic Letter (GL) 97-01, " Degradation of Control Rod i
Drive Mechanism Nozzle and Other Head Penetrations" The Nuclear Energy Institute (NEI) has informed GPU Nuclear of a September 29,1998 l
meeting in which the Alloy 6001ssue Task Group (ITG) of the EPRI Materials Reliability Project met with the NRC staff to discuss plans for industry coordination to develop a generic response to a major portion of the NRC's RAls regarding GL 97-01. The purpose of this letter is to confirm our understanding that the NRC has agreed to extend the plant response submittal date to January 15,1999, if additional time is needed to incorporate the generic response into the plant specific responses. Since the TMI-l response is currently due by November 26,1998 l
and the generic responses will not be available until December 11,1998, GPU Nuclear will l
need additional time to complete our response which we intead to provide no later than ianuary 15,1999.
Sincerely, I
+5
,.;]'
Ja es W. Langen ac Vice President and rector, TMI
.MRK
/
cc: Administrator, NRC Region I TMI Senior NRC Resident Inspector h0 TMI-l Senior NRC Project Manager
\\'