MEMORANDUM TO'. Charles W. Emeigh, Acting Chief t G p
Licensing Branch Division of Fuel Cycle Safety and Safeguards, NMSS THRU:
Dan Martin, Section Chiefe i
1 Licensing Section 2 :
i
. Licensing Branch i
L Division of Fuel Cycle Safety.
. and Safeguards, NMSS l
' FROM:
' Paul W. Lain.
';Av Licensing Secti j
Licensing Branch i
Division of Fuel Cycle Safety
]
and Safeguards
SUBJECT:
SITE VISIT TO SIEMENS POWER CORPORATION,
- SNM-1227, RICHLAND, WASHINGTON On August 17 and 18,1998, Melanie Galloway and Paul Lain of the Licensing Branch and Merritt (Nick) Baker and Makuteswara (Srini) Srinivasan of the Tank Waste Remediation System Section visited Siemens Power Corporation (SPC) in Richland, Washington. The purpose of the visit was to familiarize NRC personnel with SPC management and the fuel cycle facility.
. Upon arrival on the afternoon of August 17, the NRC personnel met with Mr. Femreite, Vice President of Manufacturing, Mr. Kilian, Manager of Manufacturing Engineering, Mr. Vaughan, Manager of Safety, Security, and Licensing, Mr. Bentley, Manager of Plant Operations, and
~ Mr. Maas, Manager of Regulatory Compliance. Mr. Femreite gave an overview of SPC world.
wide operations.-The rest of the aftemoon was allotted to visit with each Manager to discuss their area of oversight.
On August 18, Mr. Maas provided an overall facility tour and arranged a supervisor from each facility to provide the details of their facility's operation. The following facilities were visited:
UO Building Operations (Chemical Operations, Ceramic Operations, Rod Fabrications, 2
and Bundle / Cage Operations)
I Dry Conversion Facility g
- UF. Cylinder Storage Area and Cylinder Recertification Facility I
Operations Scrap. Warehouse -
Ammonia Recovery Facility go Dangerous Waste Storage Pad f
Lagoons and Lagoon Uranium Recovery / Solids Processing Facility (LUR/SPF) g Solid Waste Uranium Recovery (SWUR) Facility (Incinerator)
Modular Extraction / Recovery Facility (MERF) p m es r 3 ga prggrg gy 9811160241 981103 '
PDR. ADOCK 0700125 C
PDR d3er.'-T e-
?
yfr.-
ng 1
9 y
w-
-4ee r
v'-.
-6 w.
y-----ewt--
.-weu w-g
-4
-w
-m-rem-*
m
.~
_. -. _ - _ _ - - = _ _ _ _ _. ~
s Charles W. Emeigh 2
4 During the tour, the dry conversion facility was running two of the four conversion lines, the LUR/SPF was operational, and one of the wet process lines was recovering uranium from scrap material. The location of the April fire in the UO, Building was noted along with a brief summary of the event. The tour of the MERF noted that considerable wiring is still necessary before the facility will be operational, Distribution g:/spc_ trip.pwl Docket 70-1257&JIPUBLICZP;:.NRC File Conter!!
NMSS R/F FCLB R/F FCSS R/F Region IV
- see previous concurrence OFC FCLB*
FCLB*
FCLB*
NAME Plain PShea DMartin DATE 10/22/98 10/30/98 11/3/98 l
l l
I a
4
5 s:
Charles W. Emeigh 2
During the tour, the dry conversion facility was running two of the four conversion lines, the LUR/SPF was operational, and one of the wet process lines was recovering uranium from scrap material. The location of the April fire in the UO, Building was noted along with a brief summary of the event. The tour of the MERF noted that considerable wiring is still necessary before the facility will be operational.