MONTHYEARML20275A3342020-09-30030 September 2020 Comment (4675) E-mail Regarding Holtec-CISF Draft EIS ML20275A3242020-09-29029 September 2020 Comment (4674) E-mail Regarding Holtec-CISF Draft EIS ML20272A0432020-09-25025 September 2020 Comment (4672) E-mail Regarding Holtec-CISF Draft EIS ML20269A4542020-09-24024 September 2020 Comment (4665) E-mail Regarding Holtec-CISF Draft EIS ML20272A0422020-09-24024 September 2020 Comment (4671) E-mail Regarding Holtec-CISF Draft EIS ML20272A0412020-09-24024 September 2020 Comment (4670) E-mail Regarding Holtec-CISF Draft EIS ML20269A4642020-09-24024 September 2020 Comment (4669) E-mail Regarding Holtec-CISF Draft EIS ML20269A4632020-09-24024 September 2020 Comment (4668) E-mail Regarding Holtec-CISF Draft EIS ML20269A4612020-09-24024 September 2020 Comment (4667) E-mail Regarding Holtec-CISF Draft EIS ML20269A4552020-09-24024 September 2020 Comment (4666) E-mail Regarding Holtec-CISF Draft EIS ML20269A4532020-09-24024 September 2020 Comment (4664) E-mail Regarding Holtec-CISF Draft EIS ML20269A4492020-09-23023 September 2020 Comment (4660) E-mail Regarding Holtec-CISF Draft EIS ML20269A4142020-09-23023 September 2020 Comment (4646) E-mail Regarding Holtec-CISF Draft EIS ML20267A1902020-09-23023 September 2020 Comment (111) from Pia Salazar on Holtec International HI-STORE Consolidated Interim Storage Facility Project ML20269A3742020-09-23023 September 2020 Comment (4632) E-mail Regarding Holtec-CISF Draft EIS ML20267A1922020-09-23023 September 2020 Comment (112) from Angela Dominguez on Holtec International HI-STORE Consolidated Interim Storage Facility Project ML20267A2042020-09-23023 September 2020 Comment (113) from Zoilo Dominguez on Holtec International HI-STORE Consolidated Interim Storage Facility Project ML20269A3982020-09-23023 September 2020 Comment (4642) E-mail Regarding Holtec-CISF Draft EIS ML20267A1752020-09-23023 September 2020 Comment (105) from Lonnie Clark on Holtec International HI-STORE Consolidated Interim Storage Facility Project ML20269A3972020-09-23023 September 2020 Comment (4641) E-mail Regarding Holtec-CISF Draft EIS ML20269A3622020-09-23023 September 2020 Comment (4627) E-mail Regarding Holtec-CISF Draft EIS ML20269A4152020-09-23023 September 2020 Comment (4647) E-mail Regarding Holtec-CISF Draft EIS ML20269A4502020-09-23023 September 2020 Comment (4661) E-mail Regarding Holtec-CISF Draft EIS ML20269A3892020-09-23023 September 2020 Comment (4637) E-mail Regarding Holtec-CISF Draft EIS ML20269A4202020-09-23023 September 2020 Comment (4649) E-mail Regarding Holtec-CISF Draft EIS ML20269A4522020-09-23023 September 2020 Comment (4663) E-mail Regarding Holtec-CISF Draft EIS ML20269A4512020-09-23023 September 2020 Comment (4662) E-mail Regarding Holtec-CISF Draft EIS ML20269A4452020-09-23023 September 2020 Comment (4659) E-mail Regarding Holtec-CISF Draft EIS ML20269A4442020-09-23023 September 2020 Comment (4658) E-mail Regarding Holtec-CISF Draft EIS ML20269A4432020-09-23023 September 2020 Comment (4657) E-mail Regarding Holtec-CISF Draft EIS ML20269A4422020-09-23023 September 2020 Comment (4656) E-mail Regarding Holtec-CISF Draft EIS ML20269A4332020-09-23023 September 2020 Comment (4655) E-mail Regarding Holtec-CISF Draft EIS ML20269A4322020-09-23023 September 2020 Comment (4654) E-mail Regarding Holtec-CISF Draft EIS ML20269A4312020-09-23023 September 2020 Comment (4653) E-mail Regarding Holtec-CISF Draft EIS ML20269A4242020-09-23023 September 2020 Comment (4652) E-mail Regarding Holtec-CISF Draft EIS ML20269A4222020-09-23023 September 2020 Comment (4651) E-mail Regarding Holtec-CISF Draft EIS ML20269A4212020-09-23023 September 2020 Comment (4650) E-mail Regarding Holtec-CISF Draft EIS ML20269A4122020-09-23023 September 2020 Comment (4645) E-mail Regarding Holtec-CISF Draft EIS ML20267A1882020-09-23023 September 2020 Comment (110) from Jesus Salazar on Holtec International HI-STORE Consolidated Interim Storage Facility Project ML20267A1792020-09-23023 September 2020 Comment (108) from Erica Gray on Holtec International HI-STORE Consolidated Interim Storage Facility Project ML20269A3342020-09-23023 September 2020 Comment (4621) E-mail Regarding Holtec-CISF Draft EIS ML20269A3352020-09-23023 September 2020 Comment (4622) E-mail Regarding Holtec-CISF Draft EIS ML20269A3362020-09-23023 September 2020 Comment (4623) E-mail Regarding Holtec-CISF Draft EIS ML20269A3612020-09-23023 September 2020 Comment (4626) E-mail Regarding Holtec-CISF Draft EIS ML20269A3632020-09-23023 September 2020 Comment (4628) E-mail Regarding Holtec-CISF Draft EIS ML20269A3642020-09-23023 September 2020 Comment (4629) E-mail Regarding Holtec-CISF Draft EIS ML20269A3652020-09-23023 September 2020 Comment (4630) E-mail Regarding Holtec-CISF Draft EIS ML20267A1612020-09-23023 September 2020 Comment (101) from Karen Pope on Holtec International HI-STORE Consolidated Interim Storage Facility Project ML20269A3942020-09-23023 September 2020 Comment (4640) E-mail Regarding Holtec-CISF Draft EIS ML20269A4032020-09-23023 September 2020 Comment (4644) E-mail Regarding Holtec-CISF Draft EIS 2020-09-30
[Table view] |
Text
From: Loveall, Rhonda <rhonda.loveall@dnr.mo.gov>
Sent: Friday, June 19, 2020 5:25 PM To: Holtec-CISFEIS Resource Cc: Drake, Tiffany; Grabner, Taylor
Subject:
[External_Sender] Holtec EIS Comment Letter Attachments: 20200619 Holtec EIS comment letter signed.pdf Please see the attached letter. If you have any questions you may reach Tiffany Drake at 573-526-9830.
Thank you.
Rhonda S. Loveall Administrative Specialist MDNR l Environmental Remediation Program l Federal Facilities PO Box 176 l Jefferson City, MO 65102-0176 573.751.3907 Phone Rhonda.Loveall@dnr.mo.gov Wed like your feedback on the service you received from the Missouri Department of Natural Resources. Please consider taking a few minutes to complete the departments Customer Satisfaction Survey at https://www.surveymonkey.com/r/MoDNRsurvey. Thank you.
Federal Register Notice: 85FR16150 Comment Number: 1998 Mail Envelope Properties (a0eab08e1eca476b9ed8b2da495231b2)
Subject:
[External_Sender] Holtec EIS Comment Letter Sent Date: 6/19/2020 5:25:22 PM Received Date: 6/19/2020 5:25:26 PM From: Loveall, Rhonda Created By: rhonda.loveall@dnr.mo.gov Recipients:
Post Office: dnr.mo.gov Files Size Date & Time MESSAGE 635 6/19/2020 5:25:26 PM 20200619 Holtec EIS comment letter signed.pdf 223290 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received:
June 19, 2020 Office of Administration Mail Stop: TWFN-7-A60M Attn: Program Management Announcements and Editing Staff U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 RE: Draft Environmental Impact Statement for Holtec Internationals Consolidated Interim Storage Facility Project (Docket ID NRC-2018-0052)
To Whom It May Concern:
The Missouri Department of Natural Resources (Department) appreciates the opportunity to review the Draft Environmental Impact Statement (EIS) for Holtec Internationals Consolidated Interim Storage Facility Project. The Department offers the following comments for consideration.
- In section 1.3.1, NRC discusses how The Nuclear Waste Policy Act of 1982 required the Federal government to site, build and operate a geologic repository for high-level radioactive waste and spent fuel by the mid-1990s. However, multiple factors have contributed to delays and it is now predicted that a repository may be available by 2048.
NRC does not discuss what would happen if delays continue and a permanent repository does not become available by the end of the lifespan of the Holtec International Interim Storage Facility.
- In section 2.2.1.2, NRC mentions the proposed Holtec HI-STORM UMAX Storage System would be capable of storing the spent nuclear fuel (SNF) from all existing SNF storage systems. However, it then says the storage cavity is large enough to accommodate almost every canister type in use in the United States. NRC should include a discussion on how Holtec will address canisters too large for the storage cavity.
- Section 2.2.1.7 does not currently address radiological or rail safety inspections of the waste. Some states, including Missouri, have statutes that allow for inspections on shipments that exceed a certain level of radioactivity. The EIS should include a discussion of how inspections would occur during transit, and how the site will coordinate with states that perform inspections.
We appreciate the opportunity to provide comments for the Draft Environmental Impact Statement for Holtec Internationals Consolidated Interim Storage Facility Project. If you have any questions or need further clarification, please call me at (573) 526-9830. Address any written correspondence to my attention at Missouri Department of Natural Resources, P.O. Box 176, Jefferson City, MO 65102.
Sincerely, ENVIRONMENTAL REMEDIATION PROGRAM Digitally signed by Tiffany Tiffany Drake Drake Date: 2020.06.19 14:13:13
-05'00' Tiffany Drake Remediation and Radiological Assessment Unit Chief TD:tgr