Final ASP Analysis - Dresden 2 (LER 237-79-034)
ML20168A460
Person / Time
Site: Dresden 
Issue date: 06/16/2020
From: Christopher Hunter
NRC/RES/DRA/PRB
To:
Littlejohn J (301) 415-0428
References
LER 1979-034-00
Download: ML20168A460 (4)


Text

PRECURSOR DESCRIPTION AND DATA NSIC Accession Number:

150051 Date:

May 30, 1979

Title:

Failure of Two Diesel Generators at Dresden 2 The failure sequence was:

1. The unit 2 diesel generator had failed for reasons unspecified.
2. An operability test of unit 2/3 was immediately performed, however, it failed to start.
3. The reactor was placed in cold shutdown.

Corrective action:

1. The starting logic was modified.

Design purpose of failed system or component:

Emergency Power provides a.c. power when of fsite power is unavailable.

Unavailability of system per WASH 1400: Emergency Power:

I x 10-3 /Di Unavailability of component per WASH 1400:

  • Diesel Generator Failure to Start:

3 x 10-3 /1)

Umavailabilities are in units of per demand D-1.

Failure rates are in units of per hour HR71.

IDiesel Generator #2 An Operability Test Of The Reactor Was Placed Had Failed Unit 2/3 Also Failed In Cold Shutdown Potential Severe Core Damage No No, no LOOP No NSIC 150051 -

Actual Occurrence of Failure of Two Diesels at Dresden 2

Loss of Reactor Diesel Reactor Made Sub-RCIC/1HPCI ADS/LPCI Ln Potential Sequence Offsite Scram Start and critical by the Initiates CS TemSevere No.

Power Load SBLCS Or Rods Are Initiates Core Cr Manually Driven In jCoig Damage

~~

No1 Yes 2

No 3

Yes 4

Yes 5

H()No 6

EYes 7

Yes 8

No 9

Yes 10 No 11 Yes 12 Yes 13 C )Yes 14 Yes 15 NSIC 150051 -

Sequence of Interest for Failure of Two Diesel Generators at Dresden 2

CATEGORIZATION OF ACCIDENT SEQUENCE PRECURSORS NSIC ACCESSION NUMBER: 150051 DATE OF LER:

June 12, 1979 DATE OF EVENT:

May 30, 1979 SYSTEM INVOLVED:

Emergency Power COMPONENT INVOLVED: Diesel Generators CAUSE:

Failure of the air starter motor SEQUENCE OF INTEREST:

Loss of offsite power ACTUAL OCCURRENCE:

Failure of two diesels REACTOR NAM~E:

Dresden 2 DOCKET NUMBER:

50-237 REACTOR TYPE:

BWR DESIGN ELECTRICAL RATING:

794 MWe REACTOR AGE:

9.4 yr VENDOR:

General Electric ARCHITECT-ENGINEERS:

Sargent and Lundy OPERATORS:,

Commonwealth Edison LOCATION:

Nine miles East of Morris, Ill.

DURATION:

360(a) hours SAFETY FEATURE TYPE OF FAILURE:

(a) inadequate perfozinace; (b) failed to start; (3 made inoperable; (d) ___________

DlISCOVERY METHOD:

Test COMMENT: