Forwards Copy of Final Survey Plan General Atomics Intends to Implement to Demonstrate That Former Site of Hot Cell Facility Meets NRC & State of CA-approved Criteria for Release to Unrestricted Use
ML20155K474
Person / Time
Site: 07000734
Issue date: 10/30/1998
From: Asmussen K
GENERAL ATOMICS (FORMERLY GA TECHNOLOGIES, INC./GENER
To: Gaskin C
NRC OFFICE OF NUCLEAR MATERIAL SAFETY & SAFEGUARDS (NMSS)
Shared Package
ML20155K476 List:
References
NUDOCS 9811130259
Download: ML20155K474 (1)


Text

70- 7H

+ annsna eroaacs j

i October 30,1998 l

SNM-2999 VIA EXPRESS MdIL SERVICE l

Mr. Charles E. Gaskin l

Licensing Section 1/ Licensing Branch l

Division of Fuel Cycle Safety I

and Safeguards, NMSS U S. Nuclear Regulatory Commission l

Weshington, DC 20555

Subject:

SNM License No. SNM-696; Hot Cell Decommissioning; Submittal of Final Radiological Survey Plan 1

l

Dear Mr. Gaskin:

l Enclosed, for NRC review and approval, is a copy of the final survey plan General l

Atomics (GA) intends to implement to demonstrate that the former site of its Hot Cell Facility meets the NRC-and State of California-approved criteria for release to unrestricted use.

i This final radiological survey plan was prepared taking into account the additional knowledge obtained during the actual decontamination and demolition phases of the Hot Cell Facility (HCF) decommissioning effort, and therefore represents a more focused and situation specific plan than that discussed in GA's Hot Cell Facility Decommissioning Plan (latest revision dated January 1998). The enclosed plan incorporates and integrates the necessary and appropriate criteria from Chapter 4, " Planned Final Radiation Survey," of the HCF Decommissioning Plan with a five (5) meter triangular grid into a complete, stand alone final survey document. Accordingly, this plan supersedes Chapter 4 in specifying how compliance with the release criteria will be demonstrated.

GA is working to a schedule with a goal of being ready to commence a final survey on the Hot Cell Facility site during the first week of January 1999. Your timely attention to our request for approval of the enclosed plan will be greatly appreciated and allow GA to pursue its schedule for completion of this project.

After the fact, GA will, for purposes of clarification, revise its Hot Cell Facility Decommis-sioning Plan to reflect the approval of the enclosed final survey plan.

If you have any questions regarding the above, please do not hesitate to call Ms. Laura Gonzales at (619) 455-2758, or me at (619) 455-2823.

. j' Very truly yours, b [.

F 9811130259 981030 PDR ADOCK 07000734 Keith E. Asmussen, Ph.D.

C PDRj Director, l.icensing, Safety and Nuclear Compliance

Enclosure:

" Final Survey Plan for General Atomics's Hot Cell Facility Area" (2 copies) cc: Mr. Wayne Britz, U.S. NRC, Region IV (1 copy) 3550 GENERAL ATOMICS COURT, SAN DIEGO, CA 92121-1194 P.O BOX 85608. SAN DIEGO, CA92186-9784 (619)455-3000