Text

b m f4 O Commonwealth Edison Quad Cities Nuclear Power Station 22710 206 Avenue North p%1ITYECUTIt,G Cordova, Illinois 61242 Telephone 309/654-2241 gjf.i!

,ag g i Xf.r ais

g(Z~

JJK-86-012

  1. " [

&- W M-hr.Z FILE R ~

May 13, 1986 Mr. James G. Keppler Regional Administrator Region III Office U. S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, IL 60137

Dear Mr. Keppler:

Enclosed please find the Inservice Inspection Summary Report submitted to you in accordance with the requirements of the ASME,Section XI, Article IWA-6000. This report covers the Inservice Inspection activities conducted during the eighth refueling outage of Unit 1.

Please direct any questions you may have regarding this report to Ken Medulan, ISI Coordinator, at 309-654-2241, ext. 2154.

Respectfully, COMMONWEALTH EDISON COMPANY QUAD-CITIES NUCLEAR POWER STATION J. J. Kopacz Technical Staff Supervisor JJK:KKM:bb Enclosure 06052{DOCg 05h54 03 06 g