ML20155J286

From kanterella
Jump to navigation Jump to search
Forwards Inservice Insp Summary Rept, Re Activities Conducted During Eight Refueling Outage
ML20155J286
Person / Time
Site: Quad Cities Constellation icon.png
Issue date: 05/13/1986
From: Kopacz J
COMMONWEALTH EDISON CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML20155J289 List:
References
JJK-86-012, JJK-86-12, NUDOCS 8605230083
Download: ML20155J286 (1)


Text

'

b m f4 Quad Cities Nuclear Power Station O Commonwealth Edison 22710 206 Avenue North Cordova, Illinois 61242 Telephone 309/654-2241 p%1ITYECUTIt,G gjf.i!

Xf.r a

,ag g i JJK-86-012 #" [ '

is ;g(Z~

&- W M-hr. Z ,

FILE R ~

May 13, 1986 Mr. James G. Keppler Regional Administrator Region III Office U. S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, IL 60137

Dear Mr. Keppler:

Enclosed please find the Inservice Inspection Summary Report submitted to you in accordance with the requirements of the ASME,Section XI, Article IWA-6000. This report covers the Inservice Inspection activities conducted during the eighth refueling outage of Unit 1.

Please direct any questions you may have regarding this report to Ken Medulan, ISI Coordinator, at 309-654-2241, ext. 2154.

Respectfully, COMMONWEALTH EDISON COMPANY QUAD-CITIES NUCLEAR POWER STATION J. J. Kopacz Technical Staff Supervisor JJK:KKM:bb Enclosure 03 06 54 06052{DOCg 05hg PDR O

MAY I 61986 t

!! ! T2C/