N aua 7p YP
((
[
UNITED STATES 7p-7F M y
j NUCLEAR REGULATORY COMMISSION a
e WASHINGTON, D.C. 20555-0001 g
November 3, 1998 MEMORANDUM TO:
Robert C. Pierson, Chief Special Projects Branch Division f I ycle Safety and Safeguards FROM:
Y a
-araz, ort h Project Manager Enrichment Section Special Projects Branch Division of Fuel Cycle Safety and Safeguards
SUBJECT:
MEETING
SUMMARY
- PORTSMOUTH AND PADUCAH GASEOUS DIFFUSION PLANT COMPLIANCE PLAN ISSUE COMPLETION Recent NRC inspections and self assessments performed by the U.S. Enrichment Corporation (USEC) have indicated that certain Compliance Plan (CP) Issues / Items for the Portsmouth Gaseous Diffusion Plant (PORTS) may not have been adequately completed or closed. On October 15,1998, NRC staff met with staff from USEC and the Department of Energy (DOE) to discuss the issue of USEC's inadequate completion of CP issues / Items. NRC staff indicated that NRC inspections would assess the adequacy of USEC's CP issue /ltem completions and that enforcement actions for inadequately completed CP lssues/ Items would be based on the safety significance, proposed corrective actions, self-or NRC identification or the existence of a programmatic breakdown.
NRC staff indicated that it expects USEC to:
l 1.
Assess all PORTS CP issues / Items for adequate completions. Propose a schedule for the PORTS CP lssue/ Item completion assessment task to the NRC. The Paducah O
Gaseous Diffusion Plant (PGDP) would do a similar evaluation or propose criteria for determining which PGDP CP issue / Item completions need to be assessed.
/
Iv f4 u
2.
Propose criteria to the NRC for (a) defining completion of CP lssues/ Items and (b) determining when a previously completed / closed CP lssuelltem needs to be reopened.
3.
Propose a Justification for Continued Operation (JCO) immediately after identifying an inadequately completed CP issuelltem.
4.
By way of a Certificate amendment, immediately reopen CP issues / Items that have already been identified as being inadequately t ompleted/ closed and are likely to meet the criteria of 2(b) above. Continue to reopen CP issues / Items as the assessment identifies CP lssues/ Items which meet the criteria of 2(b) above.
9811090166 981103 PDR ADOCK 07007001-
{
C PDR k a.a a a, an
8 o Mr. Robert C. Pierson,
USEC staff emphatically stated their preference not to reopen CP lssues/ltems. NRC staff responded by stating its need to accurately represent the status of the issues and to maintain the regulatory framework for compliance provided by the CP.
DOE staff involved in developing the CP and closing issues whose completion dates occurred I
before March 3,1997, indicated that they independently confirmed the completion of the action items in a completed CP issue in a literal sense and that they did not determind the adequacy of the completed action items. For example, if a CP issue action item required USEC to develop a procedure with certain key elements, then DOE confirmed the existence of the procedure and the inclusion of the key elements in the procedure but not the adequacy of the key elements. DOE also indicated that it will be able to review in a timely manner, any changes to the CP proposed by USEC.
USEC committed to respond with appropriate criteria within two weeks of the meeting.
Attachment:
List of Attendees Dockets 70-7001 and 70-7002 l
l l
l l
l l
l
e, MEETING OF U.S. NUCLEAR REGULATORY COMMISSION AND UNITED STATES ENRICHMENT CORPORATION October 15, 1998 Co ~ M 4 -a. fh ~ lrcta 4 km / CL+ w NAME AFFILIATION PHONE kww M4
/dAC-[.SP.S 30/ v/.r~-f//3 Lt. M e r E c k ksR.c-1 % e Soi-m s -7z it bu 0e \\lavlh 06E/WO Y2 7 -2 yl4W7 4
6 VE.
To E LLE U S D.__
301-564 -325o
.1 o-H N Tit Tatn n LHV 3 3o)- m - 9 239 Sh4 e, Q0+ h USTL 36I-364 -3951 doe, R L)c.cj4 M[DTC 123 - 2.y/ - y 7 '/5 i
Tc h sstesA Adom ses. %ss-s,w o kbr J Y ner Ule'C-D90.)H7-37/0 M 3.hhmtB 06E/PonIsMKA h40h97-Olo MEtpe kattowe r>R.c / s9 6 2x/4ts-72R bab 9M.Sv WILT
/590 Sa1 - 915 llR n') e.~ r > H ce n NRc /J M 2 et ws vial, NAThC.yM NIWoLbERG UR C [OCo C 3oI t//f-/4t/)
mou w u mi nec /os
.w -. m e - a,a AtdThr-A-Ethar-TrA-raiu.auc4e w cree
- oi-4Es - h ATTACHMENT
l
- Mr. Robert C. Pierson USEC staff emphatically stated their preference not to reopen CP issues / Items. NRC staff responded by stating its need to accurately represent the status of the issues and to maintain the regulatory framework for compliance provided by the CP.
DOE staff involved in developing the CP and closing issues whose completion dates occurred l
before March 3,1997, indicated that they independently confirmed the completion of the action items in a completed CP issue in a literal sense and that they did not determine the adequacy of l
the completed action items. For example, if a CP lssue action item required USEC to develop a procedure with certain key elements, then DOE confirmed the existence of the procedure and the inclusi:,1 of the key elements in the procedure bu. mt the adequacy of the key elements. DOE also indicated that it will be able to review in a timely manner, any changes to the CP proposed by USEC.
1 USEC committed to respond with appropriate criteria within two weeks of the meeting.
Attachment:
List of Attendees Dockets 70-7001 and 70-7002 l
DISTRIBUTION:
Dockets 70-7001 and 70-7002 NRC File Center PUBLIC NMSS r/f FCSS r/f SPB r/f TReidinger, Rlll KWinsberg, OGC DHartland, Rlll KO'Brien, Rlll WTroskoski, FCOB PHiland, Rlli JDavis YChen CCox LTenEyck WBrach CBlanchard, Rlli JJacobsen, Rlli
- See previous concurrence i
OFC
- SPB E
- SPB E
- SPB E
SPB h
SPM
'iVlhelihy Rhrson l
NAME YFaraz:ij DHoadley MHorn l
DATE 10/27/98 10/28/98 10/29/98 N/ $0/98 h/
/98 C = COVER E = COVER & ENCLOSURE N = NO COPY l
g:\\mtsmcpcl.yhf OFFICIAL RECORD COPY l
1 l
i e
Mr. Robert C. Pierson i DOE s ff involved in developing the CP and closing issues whose completion dates occurred j
before rch 3,1997, indicated that they independently confirmed the completion of the action items in a mpleted CP issue in a literal sense and that they did not determine the adequacy of the complet action items. For example, if a CP issue action item required USEC to develop a procedure wit certain key elements, then DOE confirmed the existence of the procedure and the
{
inclusion of the y elements in the procedure but not the adequacy of the key elements. DOE also indicated tha they will be able to review in a timely manner, any changes to the CP proposed by USEC.
Attachment:
List of Att dees
)
Dockets 70-7001 and 70-7 2
(
DISTRIBUTION:
Dockets 70-7001 and 70-7002 NRC File Center PUBLIC MSS r/f FCSS r/f SPB r/f TReidinger, Rlll KWinsberg, OGC artland, Rlll j
KO'Brien, Rlli WTroskoski, FCOB PHiland, Rill JDavis YChen C LTenEyck WBrach
- See previous concurrence j
SPk OFC
- SPB
$PB 6
SPB C
SPB NAME YFaraz:ij hoadley MHorN MGalloway RPierkn
/98\\
DATE 10/27/98 0/2.%/98
/d / #1/98
/
/98
/
C = COVER E = COVER & ENCLOSURE N = NO COPY g:\\mtsmcpcl.yhf OFFICIAL RECORD COPY j
. -.. ~
e.-
i s
. Robert C. Pierson DOE st involved in developing the CP and closing issues whose completion dates occurred before Ma 3,1997, indicated that they independently confirmed the completion of the action items in a co leted CP lasue in a literal sense and that they did not determine the adequacy of the completed a 'on items. For example, if a CP issue action item required USEC to develop a procedure with ce
- key elements, then DOE confirmed the existense of the procedure and
- the inclusion of the ke lements in the procedure but not the adequacy of the key elements.
DOE also indicated that t will be able to review in a timely manner, any changes to the CP proposed by USEC.
Attachment:
List of Attendees Dockets 70-7001 and 70 7002 j
DISTRIBUTION:
Dockets 70-7001 and 70-7002 NRC File Center PUBLIC NMSS r/f FCSS r/f SPB r/f TReidinger, Rill KWinsberg, OGC DHartland, Rlli KO' Brian, Rlll WTroskoski, FCOB PHiland, Rlli JDavis YChen CCox LTenEyck WBrach
- See previous concurrence OFC SPB E
SPB SPB SPB SPB YFaraz:ijN l
NAME NDHoadley MHorn MGalloway RPierson DATE lo / 2 7/98 10
/98
/
/98
/
/98
/
/98 l
C = COVER
'E = COVER & ENCLOSURE N = NO COPY g:\\mtsmcpcl.yhf OFFICIAL RECORD COPY t