B ALTIMORE GAS AND i
ELECTRIC CHARLES CENTER + R O. BOX 1475
- BALTIMORE, MARYLAND 21203 JostPN A.TIERNAN vice PatstotNt NUCLEAR ENEROY June 9,1988 U. S. Nuclear Regulatory Commission Washington, DC 20555 ATTENTION:
Document Control Desk
SUBJECT:
Calvert Cliffs Nuclear Power Plant Unit Nos.1 & 2; Docket Nos. 50-317 & $0-318 Request for Additional Information Concerning BG&E Responses to Generic Letter 83-28. Item 2.2.2
REFERENCE:
(a) Letter from Mr. S. A. McNeil (NRC) to Mr. J. A. Tiernan (BG&E),
dated April 25, 1988, same subject Gentlemen:
This is L in response to Reference (a).
Enclosure (1) addresses the additional
[
information you requested regarding item 2.2.2 of Generic Letter 83-28, "Required Actions Based on Generic implications of Salem ATWS Events."
Should you have any further questions regarding this matter, we will be pleased t:
discuss them with you.
Very truly f'&f0 W JAT/DLS/ dim Enclosure ec:
D. A. Brune, Esquire J. E.
Silberg, Esquire R. A.Capra, NRC kg[
S. A.McNeil, NRC W. T. Russell, NRC D. C.Trimble, NRC i\\
8806170233 880609 PDR ADOCK 05000317 P
d,e ENCLOSURE (1)
ADDITIONAL INFORMATION CONCERNING ITEM 2.2.2 OF GENERIC LETTER 83-28 1.
NRC Reauest Please - provide a description of the additional vendor interface programs that you dett mined would be appropriate and practicable.
BGAE Response We have identified and contacted nine vendors that we determined would be desirable to establish an interface program with. A list of these vendors and the equipment they supply us is provided below. We are experiencing difficulties obtaining timely vendor response and support, and have thus far received initial responses from only six vendors. We are proceeding with defining individual programs for some vendors and we are continuing to follow-up our communication *.
with the others. The interface programs will be individually tailored to the equipment and the vendor.
Vendor Eauioment
- ARMCO Charging Pumps
- BINGIIAM INTERNATIONAL llPSI Pumps
- BYRON JACKSON Reactor Coolant Pumps Auxiliary Feed Pumps
- DRESSER RAND Auxiliary Feed Pump Turbines EXIDE Vital AC System (Inverters)
FAIRBANKS - MORSE Emergency Diesel Generators Drip-Proof Synchronous Alternator
- GENERAL ELECTRIC Reactor Trip Switchgear
- INGERSOLL - RAND LPSI Pumps WESTINGIIOUSE 480 Volt Circuit Breakers
= Response Received 2.
NRC Reauest Please provide a commitment to estblishing and maintaining these additional vendor interface programs by a certain date.
BG&E Response Due to the aforementioned difficulties in getting timely responses from
- vendors, these interface programs are still in the early stages of development. These vendors are not under our control and have little incentive to proceed aggressively in establishing these programs. We have set a
target date for ourselves to have these programs established by December 31, 1988. We cannot consider this a commitment, though, because of this vendor dependence.
- -