.4' Federal Emergency Management Agency l
RegionlV i
3003 Chamblee-TuckerRd Atlanta,CA 30341 O
O September 8, 1998 Mr. Luis Reyes Regional Administrator - RII Nuclear Regulatory Commission
~61 Forsyth Street, SW, Suite 23T85 Atlanta, Georgia 30323
Dear Mr. Reyes:
Enclosed is a copy of the final exercise report for the May 20, 1998, post plume phase exercise of the offsite radiological emergency response plans site-specific to the
~ Hatch Nuclear Power Plant.
This report addresses the evaluation of the plans and preparedness for the State of 1
Georgia and the counties within the 50-mile Ingestion 4
Emergency Planning Zone.
The State of Georgia, Appling County and Wayne County participated in the exercise.
The final exercise report was prepared by the Federal Emergency Management Agency Region IV staff.
Copies of this report will be forwarded to the State of Georgia, FEMA Headquarters, and NRC Headquarters by my staff.
There were no Deficiencies or Areas Requiring Corrective Actions identified during the exercise.
Based on the results of the May 20, 1r98, exercise, the offsite radiological emergency response plans and preparedness for the State of Georgia and the affected local jurisdictions l
site-specific to the Hatch Nuclear Power Plant can be implemented and are adequate to provide reasonable assurance that appropriate measures can be taken offsite to protect the health and safety of the public in the event of a radiological
[
emergency at.the site.
The Title 44 CFR, Part 350, approval of the offsite radiological emergency respcnse plans.and preparedness for the State of Georgia offsite radiological emergency 9810290175 981021
~
PDR ADOCK 05000321 F
4 I response plans and preparedness site-specific to the Hatch Nuclear Power Plant, granted on May 5, 1991 will remain in effect.
If you should hcVe any questions, please contact Don Cornell at 770/220-5470.
Sincerely, 0\\ John B.
openhaver Regional Director Enclosure cc: Ms. Ianessa Quinn, Acting Chief FEMA HQ, SL-PT-EX-RG Mr. Charles L. Miller, Chief U. S. Nuclear Regulatory Commission Washington, DC l