MONTHYEARML20211K8611999-09-0101 September 1999 Informs That There Has Been Some Confusion Re Recently Issued ODCM Generic Section Rev Which Needs to Be Clarified. Clarifications Are Listed ML20210P1361999-08-0404 August 1999 Notification of 990817 Meeting with Util in Rockville, Maryland to Discuss Status of Licensing Actions Submitted by Comm Ed & Plan for Proposed Licensing Workshop ML20210C7061999-07-16016 July 1999 Forwards Facility Submitted Outline & Initial Exam Submittal for Operator Licensing Exams Administered During Wk of 990607 ML20209H2231999-07-16016 July 1999 Forwards Operator Licensing Exam Repts 50-456/99-301(OL) & 50-457/99-301(OL) of Exam Administered During Wk of 990607 ML20206Q2751999-05-13013 May 1999 Forwards Official Case File for DPO-99-1,request of Review of Concerns Related to TS Setpoints & Allowable Value for Instrumentation Under Formal DPO Procedures,For Disposition in Accordance with Provisions of NRC MD 10.159 ML20206E9331999-05-0303 May 1999 Notification of 990524 Meeting with Commonwealth Edison,Co in Rockville,Md to Discuss Technical Issues Related to Proposed re-rack of SFPs at Braidwood Station & Byron Station ML20206Q3211999-02-19019 February 1999 Responds to e-mail Message Sent on 980202,re Status of Staff Actions on Recipient Dpv.With Regard to Dpv Concerning Dynamic Testing of Instrument Channels at Braidwood,Staff Pursuing Resolution of Issue with Licensee ML20206Q3391999-01-0505 January 1999 Provides Update on Status of Resolution of follow-up Actions from Resolution of Dpv on Dynamic Testing of Instrumentation at Braidwood Station ML20155E7361998-11-0202 November 1998 Forwards NRC Operator Licensing Exam Repts 50-456/98-305 & 50-457/98-305 for Tests Administered on 980914 ML20154G2361998-10-0707 October 1998 Responds to Memo Sent on 981002 Re Resolution of follow-up Actions for NRR Differing Professional View Panel on Dynamic Testing of Instrumentation at Plant ML20196D7921998-10-0202 October 1998 Forwards Comments Related to Staff Responses to follow-up Actions Re Dynamic Testing of Instrument Channels at Braidwood ML20196D7801998-09-21021 September 1998 Informs That Staff Completed Review of follow-up Actions Identified in Memo from Bw Sheron to Ba Boger, on Dymanic Testing of Instrumentation Channels at Braidwood ML20151V2951998-09-0202 September 1998 Informs That Braidwood Station Concurs with Encl Proposed 980904 Util Response to NRC Re IPEEE ML20197C8041998-09-0202 September 1998 Informs That Braidwood Station Concurs with Proposed Encl Response to NRC Re RPV Integrity at Braidwood & Byron Stations ML20197C8301998-09-0101 September 1998 Informs That Rev 2 to Calculation BYR98-109/BRW-98-339-E Has Been Reviewed & Found Acceptable for Transmittal to Nrc. Draft Util Ltr Re Thermo-Lag Ampacity Derating Factor Calculation,Encl ML20237D4331998-08-21021 August 1998 Notification of 980903 & 04 Meetings W/Util in Rockville,Md to Discuss Technical Issues Related to Byron & Braidwood Improved Std TSs Conversion,Including Section 3.3,beyond Scope Issues,Closeout Packages & Amends to Current TSs ML20196D7211998-08-0404 August 1998 Responds to 980720 Memo from Sj Collins to Lj Callan Re When & How Mesac Approved.Licensee Installed Mirco Electronic Surveillance & Calibration (Mesac) Sys Measurement & Test Equipment as Backup Sys to Normal M&TE ML20196D7711998-07-22022 July 1998 Discusses Staff Review of Braidwood Mesac System ML20249A2231998-06-12012 June 1998 Notification of 980625-26 Meeting W/Util in Rockville,Md to Discuss Technical Issues Re Byron & Braidwood Improved Std TSs Conversion ML20216B6731998-05-11011 May 1998 Discusses Closure of TAC M94439 for Braidwood,Unit 1,steam Generator Replacement ML20217P0131998-04-29029 April 1998 Forwards NRC Approved Operator Licensing Exam (Facility Outline & Initial Exam Submittal & as-given Operating Exam) for Tests Administered During Wk of 980413 ML20217P0731998-04-29029 April 1998 Forwards NRC Operator Licensing Exam Repts 50-456/98-304(OL) & 50-457/98-304(OL) (Including Completed & Graded Tests) for Tests Administered on 980413-15 ML20217E3881998-04-23023 April 1998 Notification of 980506 & 07 Meetings W/Util in Rockville,Md to Discuss Technical Issues Re Plants Improved STS Conversion ML20216H3401998-03-17017 March 1998 Notification of 980331-0402 Meeting W/Util in Rockville,Md to Discuss Reviewer Comments on Byron & Braidwood Improved Std TS Submittal ML20216H6971998-03-17017 March 1998 Notification of 980326 Meeting W/Commonwealth Edison Co in Lisle,Il to Discuss Comed Request to Consolidate near-site Emergency Operations Facility Into Single Central EOF ML20203G8551998-02-23023 February 1998 Notification of 980305 Meeting W/Util in Rockville,Md to Discuss Status of Byron & Braidwood Licensing Issues ML20198G4921998-01-0707 January 1998 Forwards Facility Submitted Outline,Initial Exam Submittal & as Given Operating Exam for Test Administered During Wk of 971006 at Plant ML20198J6881998-01-0707 January 1998 Forwards NRC Operator Licensing Exam Rept w/as-given Written Exam for Tests Administered During Wk of 971006 at Plant ML20202E5831997-11-25025 November 1997 Notification of 971215 Meeting W/Commonwealth Edison Co in Rockville,Md to Review Schedule for Listed Plants Improved Std TS Conversion & Supplemental Submittals ML20203C3621997-11-25025 November 1997 Revised Notification W/New Starting Time of Meeting W/Ceco on 971215 in Rockville,Maryland to Discuss Review Schedule Byron & Braidwood Improved TS Conversion & Supplemental Submittals ML20202D2221997-11-25025 November 1997 Notification of Meeting W/Ceco on 971211 in Rockville,Md to Discuss Proposed Mod to Methodology for Estimating SG Tube Leakage Attributable to Outer Diameter Stress Corrosion Crack Indications Restricted from Burst for Plant SGs ML20236N5111997-10-22022 October 1997 Fowards Staff Response to 960912 TIA Re Containment Spray Additive Sys Conformance W/Design Basis & Tss.Analysis Concluded That 2,400-2,600 Ppm in RWST Acceptable ML20217K8271997-10-16016 October 1997 Notification of 971024 Meeting W/Util to Discuss Results of Comed Investigation Into Sensitivity of Proposed voltage- Dependent Growth Rates to Binning Strategy for ODSCC Indicators ML20212A1501997-10-15015 October 1997 Forwards Response for NRC RAI Re SG Interim Plugging Criteria 90 Day Rept for Braidwood,Unit 1 Sixth Refuel Outage (A1R06).Station Concurs W/Response as Proposed for CE ML20217D4261997-09-30030 September 1997 Informs of Scheduled Visits W/Nuclear Services at Gpu on Nov 14th & Visit at Commonwealth Edison on Dec 3rd & Would Like to Receive Any Info Available.Supporting Documentation Encl ML20217B3901997-09-23023 September 1997 Forwards Questions Re Ceco Submittal of Revised SG Tube Rupture Analysis for Byron,Unit 1 & Braidwood,Unit 1 ML20149L1901997-07-22022 July 1997 Notification of 970723 Meeting W/Commonwealth Edison Co in Rockville,Md to Discuss Results of Spring 1997,Braidwood,1 SG Tube Eddy Current Insp.Time of Meeting Rescheduled ML20149F2731997-07-0303 July 1997 Notification of 970723 Meeting W/Util in Rockville,Md to Discuss Results of Spring 1997 Plant,Unit 1 SG Tube Eddy Current Insp Including Determination of Impact of Data ML20138D2781997-04-28028 April 1997 Notification of 970430 Meeting W/Util in Rockville,Md to Discuss Results of EC Insps of Plant SGs Conducted During Present Refueling Outage IA-97-178, Forwards Partially Withheld Background Briefing Package in Preparation for 970425 Meeting Between Comed & Commission1997-04-18018 April 1997 Forwards Partially Withheld Background Briefing Package in Preparation for 970425 Meeting Between Comed & Commission ML20217D5461997-04-18018 April 1997 Forwards Partially Withheld Background Briefing Package in Preparation for 970425 Meeting Between Comed & Commission ML20147J2391997-04-0909 April 1997 Notification of Meeting on 970416 W/Util in Rockville,Md to Discuss Overall Response & Present Addl Details Re Performance Indicators Used to Monitor Performance Stations ML20236N0071997-04-0707 April 1997 Responds to Request for TS Interpretation on Containment Vent & Drain Valves at Braidwood ML20138J7671997-02-0505 February 1997 Informs That NRC Plans to Administer Generic Fundamentals Exam Section of Written Operator Licenseing Exam on 970409. Ltr W/Copy to Chief,Operator Licensing Branch Must Be Submitted to Listed Address in Order to Register Personnel ML20149M6901997-01-19019 January 1997 Notification of 970128 Meeting W/Commonwealth Edison Co to Discuss Licensee Proposed Program for Use of Mixed Oxide Fuel ML20133J5811997-01-15015 January 1997 Notification of 970122 Meeting W/Util in Rockville,Md to Discuss Licensee Status of Program for Replacement & Operation of New SG at Byron 1 & Braidwood 1 ML20133J4821997-01-15015 January 1997 Notification of 970123 Meeting W/Licensees in Rockville,Md to Discuss Contents of Plants TS Conversion Submittal, Provide Staff Comments Based on Initial Screening Review & Discuss Review Schedule ML20196D8881997-01-0202 January 1997 Provides Results of Review of Dpv That Was Expressed in 961017 Memo Re Dynamic Testing of Instrumentation Channels at Braidwood ML20196D8011997-01-0202 January 1997 Forwards NRR Ad Hoc Dpv Review of Recipient Differing Professional View Re Dynamic Testing of Instrumentation Channels at Braidwood,Per 961017 Memo ML20196D8671997-01-0202 January 1997 Submits Review of Ad Hoc NRR Dpv Review Panel Re 961017 Memo Dpv on Dynamic Testing of Instrumentation Channels at Braidwood 1999-09-01
[Table view] Category:MEMORANDUMS-CORRESPONDENCE
MONTHYEARML20211K8611999-09-0101 September 1999 Informs That There Has Been Some Confusion Re Recently Issued ODCM Generic Section Rev Which Needs to Be Clarified. Clarifications Are Listed ML20210P1361999-08-0404 August 1999 Notification of 990817 Meeting with Util in Rockville, Maryland to Discuss Status of Licensing Actions Submitted by Comm Ed & Plan for Proposed Licensing Workshop ML20209H2231999-07-16016 July 1999 Forwards Operator Licensing Exam Repts 50-456/99-301(OL) & 50-457/99-301(OL) of Exam Administered During Wk of 990607 ML20210C7061999-07-16016 July 1999 Forwards Facility Submitted Outline & Initial Exam Submittal for Operator Licensing Exams Administered During Wk of 990607 ML20206Q2751999-05-13013 May 1999 Forwards Official Case File for DPO-99-1,request of Review of Concerns Related to TS Setpoints & Allowable Value for Instrumentation Under Formal DPO Procedures,For Disposition in Accordance with Provisions of NRC MD 10.159 ML20206E9331999-05-0303 May 1999 Notification of 990524 Meeting with Commonwealth Edison,Co in Rockville,Md to Discuss Technical Issues Related to Proposed re-rack of SFPs at Braidwood Station & Byron Station ML20206Q3211999-02-19019 February 1999 Responds to e-mail Message Sent on 980202,re Status of Staff Actions on Recipient Dpv.With Regard to Dpv Concerning Dynamic Testing of Instrument Channels at Braidwood,Staff Pursuing Resolution of Issue with Licensee ML20206Q3391999-01-0505 January 1999 Provides Update on Status of Resolution of follow-up Actions from Resolution of Dpv on Dynamic Testing of Instrumentation at Braidwood Station ML20155E7361998-11-0202 November 1998 Forwards NRC Operator Licensing Exam Repts 50-456/98-305 & 50-457/98-305 for Tests Administered on 980914 ML20154G2361998-10-0707 October 1998 Responds to Memo Sent on 981002 Re Resolution of follow-up Actions for NRR Differing Professional View Panel on Dynamic Testing of Instrumentation at Plant ML20196D7921998-10-0202 October 1998 Forwards Comments Related to Staff Responses to follow-up Actions Re Dynamic Testing of Instrument Channels at Braidwood ML20196D7801998-09-21021 September 1998 Informs That Staff Completed Review of follow-up Actions Identified in Memo from Bw Sheron to Ba Boger, on Dymanic Testing of Instrumentation Channels at Braidwood ML20197C8041998-09-0202 September 1998 Informs That Braidwood Station Concurs with Proposed Encl Response to NRC Re RPV Integrity at Braidwood & Byron Stations ML20151V2951998-09-0202 September 1998 Informs That Braidwood Station Concurs with Encl Proposed 980904 Util Response to NRC Re IPEEE ML20197C8301998-09-0101 September 1998 Informs That Rev 2 to Calculation BYR98-109/BRW-98-339-E Has Been Reviewed & Found Acceptable for Transmittal to Nrc. Draft Util Ltr Re Thermo-Lag Ampacity Derating Factor Calculation,Encl ML20237D4331998-08-21021 August 1998 Notification of 980903 & 04 Meetings W/Util in Rockville,Md to Discuss Technical Issues Related to Byron & Braidwood Improved Std TSs Conversion,Including Section 3.3,beyond Scope Issues,Closeout Packages & Amends to Current TSs ML20196D7211998-08-0404 August 1998 Responds to 980720 Memo from Sj Collins to Lj Callan Re When & How Mesac Approved.Licensee Installed Mirco Electronic Surveillance & Calibration (Mesac) Sys Measurement & Test Equipment as Backup Sys to Normal M&TE ML20196D7711998-07-22022 July 1998 Discusses Staff Review of Braidwood Mesac System ML20249A2231998-06-12012 June 1998 Notification of 980625-26 Meeting W/Util in Rockville,Md to Discuss Technical Issues Re Byron & Braidwood Improved Std TSs Conversion ML20216B6731998-05-11011 May 1998 Discusses Closure of TAC M94439 for Braidwood,Unit 1,steam Generator Replacement ML20217P0731998-04-29029 April 1998 Forwards NRC Operator Licensing Exam Repts 50-456/98-304(OL) & 50-457/98-304(OL) (Including Completed & Graded Tests) for Tests Administered on 980413-15 ML20217P0131998-04-29029 April 1998 Forwards NRC Approved Operator Licensing Exam (Facility Outline & Initial Exam Submittal & as-given Operating Exam) for Tests Administered During Wk of 980413 ML20217E3881998-04-23023 April 1998 Notification of 980506 & 07 Meetings W/Util in Rockville,Md to Discuss Technical Issues Re Plants Improved STS Conversion ML20216H3401998-03-17017 March 1998 Notification of 980331-0402 Meeting W/Util in Rockville,Md to Discuss Reviewer Comments on Byron & Braidwood Improved Std TS Submittal ML20216H6971998-03-17017 March 1998 Notification of 980326 Meeting W/Commonwealth Edison Co in Lisle,Il to Discuss Comed Request to Consolidate near-site Emergency Operations Facility Into Single Central EOF ML20203G8551998-02-23023 February 1998 Notification of 980305 Meeting W/Util in Rockville,Md to Discuss Status of Byron & Braidwood Licensing Issues ML20198J6881998-01-0707 January 1998 Forwards NRC Operator Licensing Exam Rept w/as-given Written Exam for Tests Administered During Wk of 971006 at Plant ML20198G4921998-01-0707 January 1998 Forwards Facility Submitted Outline,Initial Exam Submittal & as Given Operating Exam for Test Administered During Wk of 971006 at Plant ML20202D2221997-11-25025 November 1997 Notification of Meeting W/Ceco on 971211 in Rockville,Md to Discuss Proposed Mod to Methodology for Estimating SG Tube Leakage Attributable to Outer Diameter Stress Corrosion Crack Indications Restricted from Burst for Plant SGs ML20202E5831997-11-25025 November 1997 Notification of 971215 Meeting W/Commonwealth Edison Co in Rockville,Md to Review Schedule for Listed Plants Improved Std TS Conversion & Supplemental Submittals ML20203C3621997-11-25025 November 1997 Revised Notification W/New Starting Time of Meeting W/Ceco on 971215 in Rockville,Maryland to Discuss Review Schedule Byron & Braidwood Improved TS Conversion & Supplemental Submittals ML20236N5111997-10-22022 October 1997 Fowards Staff Response to 960912 TIA Re Containment Spray Additive Sys Conformance W/Design Basis & Tss.Analysis Concluded That 2,400-2,600 Ppm in RWST Acceptable ML20217K8271997-10-16016 October 1997 Notification of 971024 Meeting W/Util to Discuss Results of Comed Investigation Into Sensitivity of Proposed voltage- Dependent Growth Rates to Binning Strategy for ODSCC Indicators ML20212A1501997-10-15015 October 1997 Forwards Response for NRC RAI Re SG Interim Plugging Criteria 90 Day Rept for Braidwood,Unit 1 Sixth Refuel Outage (A1R06).Station Concurs W/Response as Proposed for CE ML20217D4261997-09-30030 September 1997 Informs of Scheduled Visits W/Nuclear Services at Gpu on Nov 14th & Visit at Commonwealth Edison on Dec 3rd & Would Like to Receive Any Info Available.Supporting Documentation Encl ML20217B3901997-09-23023 September 1997 Forwards Questions Re Ceco Submittal of Revised SG Tube Rupture Analysis for Byron,Unit 1 & Braidwood,Unit 1 ML20149L1901997-07-22022 July 1997 Notification of 970723 Meeting W/Commonwealth Edison Co in Rockville,Md to Discuss Results of Spring 1997,Braidwood,1 SG Tube Eddy Current Insp.Time of Meeting Rescheduled ML20149F2731997-07-0303 July 1997 Notification of 970723 Meeting W/Util in Rockville,Md to Discuss Results of Spring 1997 Plant,Unit 1 SG Tube Eddy Current Insp Including Determination of Impact of Data ML20138D2781997-04-28028 April 1997 Notification of 970430 Meeting W/Util in Rockville,Md to Discuss Results of EC Insps of Plant SGs Conducted During Present Refueling Outage ML20217D5461997-04-18018 April 1997 Forwards Partially Withheld Background Briefing Package in Preparation for 970425 Meeting Between Comed & Commission IA-97-178, Forwards Partially Withheld Background Briefing Package in Preparation for 970425 Meeting Between Comed & Commission1997-04-18018 April 1997 Forwards Partially Withheld Background Briefing Package in Preparation for 970425 Meeting Between Comed & Commission ML20147J2391997-04-0909 April 1997 Notification of Meeting on 970416 W/Util in Rockville,Md to Discuss Overall Response & Present Addl Details Re Performance Indicators Used to Monitor Performance Stations ML20236N0071997-04-0707 April 1997 Responds to Request for TS Interpretation on Containment Vent & Drain Valves at Braidwood ML20138J7671997-02-0505 February 1997 Informs That NRC Plans to Administer Generic Fundamentals Exam Section of Written Operator Licenseing Exam on 970409. Ltr W/Copy to Chief,Operator Licensing Branch Must Be Submitted to Listed Address in Order to Register Personnel ML20149M6901997-01-19019 January 1997 Notification of 970128 Meeting W/Commonwealth Edison Co to Discuss Licensee Proposed Program for Use of Mixed Oxide Fuel ML20133J4821997-01-15015 January 1997 Notification of 970123 Meeting W/Licensees in Rockville,Md to Discuss Contents of Plants TS Conversion Submittal, Provide Staff Comments Based on Initial Screening Review & Discuss Review Schedule ML20133J5811997-01-15015 January 1997 Notification of 970122 Meeting W/Util in Rockville,Md to Discuss Licensee Status of Program for Replacement & Operation of New SG at Byron 1 & Braidwood 1 ML20196D8671997-01-0202 January 1997 Submits Review of Ad Hoc NRR Dpv Review Panel Re 961017 Memo Dpv on Dynamic Testing of Instrumentation Channels at Braidwood ML20196D8011997-01-0202 January 1997 Forwards NRR Ad Hoc Dpv Review of Recipient Differing Professional View Re Dynamic Testing of Instrumentation Channels at Braidwood,Per 961017 Memo ML20196D8881997-01-0202 January 1997 Provides Results of Review of Dpv That Was Expressed in 961017 Memo Re Dynamic Testing of Instrumentation Channels at Braidwood 1999-09-01
[Table view] |
Text
. - _ _
[ ,
/7v;h
=.
AMR 2 51964 MEMORANDUM FOR: Region III Files (Braidwood 1 and 2)
FROM: P. R. Pelke, Project Inspector, Braidwood
SUBJECT:
WELDING AND VALVES AT BRAIDWOOD (50-456; 50-457)
(AMS NO. RIII-85-A-0204)
On March 24, 1986, the Allegation Review Board met to discuss the subject allegation. The outline of the meeting is enclosed.
P. R. Pelke Project Inspector
Enclosure:
Outline for Allegation Review Board cc w/ enclosure:
A. Davis C. Norelius C. Paperiello E. Greenman W. Little J. Harrison R. Gardner D. Danielson J. Jacobson C. Weil W. Kropp J. Stevens, NRR M. Farber I
f'gI >1-p>wa mm !
~ .h
&Ecl
OUTLINE FOR ALLEGATION REVIEW BOARD (AMS NO. RIII-85-A-0204)
References:
(1) Memorandum from Charles H. Weil to Charles E. Norelius dated December 16, 1985 (2) Letter from Charles H. Weil to alleger dated December 16, 1985 ,
(3) Letter from alleger to Charles H. Weil dated December 17, 1985 (4) Letter from alleger to Charles H. Weil dated December 19, 1985 l (5) Letter from alleger to Charles H. Weil dated December 21, 1985 ,
I (6) Memorandum from T.N. Tambling to Charles E. Morelius dated December 26, 1985 (7) Memorandum from P.R. Pelke to RIII Files dated February 25, l l
1986 Recommended Inspector: John Jacobson
- Reference (2) numbered the individual concerns as documented in Reference (1). Additionally, the alleger expands on those concerns in References (3),
(4), and (5). Reference (6) documented the first Allegation Review Board on this allegation.
Attached are the interview results and revised action plan developed in response to the initial Allegation Review Board meeting.
Scheduled Completion Date: 07/01/86, however, the inspector should accomplish interim inspections if possible.
4
)
INTERVIEW RESULTS - ALLEGATION RIII-85-A-0204 The alleger was interviewed on 2/26/86 from approximately 6:30 p.m. to 9:00 p.m. at a location near his home by J. Jacobson and W. Kropp. The alleger was told that the purpose of the interview was to attempt to clarify his concerns .
as outlined in C. Weil's letter to the alleger, dated 12/16/B5 and to afford the opportunity to voice any additional concerns he may have. The points discussed and the NRC inspector's recommended actions are as follows:
Item 1:
The alleger made a general statement that productivity was stressed above quality. When asked for specifics he could offer none. He stated that his only "real" concerns were Items 5 and 7.
Recommended NRC Action:
None.
l l
l Item 2:
The alleger Feferred to the " tack in place / weld in place" program at Braidwood. The alleger stated that this program was developed because
" engineering was so screwed up," however, he had'no hardware related d
concerns. The alleger was told that the NRC had reviewed this program and accepted it. He said that he had no real problem with it.
Recomended NRC Action:
None.
I 1
Item 3:
The alleger stated that often secondary hangers are attached to primary hangers and that many clearance problems existed. He stated that he had seen situations where the pipe was not even touching the hanger, i.e.
bearing no load. When asked for specifics he could give none and added
]
that most of his experience was with class "D" nonsafety related piping.
I
)
Recommended NRC Action:
The Region III staff is currently aware of the clearance issue and will continue to monitor licensee progress.
Item 4:
See Item 3.
Item 5:
The alleger stated that he had seen large porosity holes in the completed and flat topped RC piping welds. He stated that he had brought this to the attention of a Q.C. inspector in late 1984 or early 1985. The alleger could not remember the name of the inspector and added that he has since gone back to look for these " holes" and could not find them.
, The alleger agreed that possibly the " holes" had since been repaired.
l l
Recommended NRC Action:
i Review RC piping repair packages to ascertain if repairs have in fact been made. The inspector will also visually examine a sample of the RC piping, including welds 1RC01-8 and IRC03-8 which the alleger stated contains some small minor porosity.
Iten 6:
I The alleger stated that he was part of a work crew assigned to torque the body to bonnet bolts on pressurizer valves 1A0V-RY455-A and 1A0V-RY456.
The alleger described the modification of the torque wrench as an 8" extension fit-onto the head of the wrench. He stated that an engineer made torque correction calculations as the wrench was positioned on the difficult to reach bolt heads. The alleger doubts the validity of ths calculations.
/
Recommended NRC Action:
Review the bolt up records and associated calculations for these valves.
In addition, verify a sample of actual bolt torque.
Item 7:
The alleger stated that the welding electrode weave width as stated in the welding procedure (4 X electrode diameter) was violated in that some welders used only 3 weld passes for a joint approximately 3" wide. His concern is that excessive heat was applied to the pipe joint, and that he knew about the pipe cracking problem at Dresden. The NRC inspector explained that the problem at Dresden was associated with the BWR system only and did not apply to Braidwood. The alleger also stated that root repairs were made from the inside on the RC piping due to " suck back."
The NRC inspector explained that the method of repair was technically acceptable and that the final radiography would detect any unacceptable repair. The alleger stated that he had no problem with that.
Recommended NRC Action:
Review the welding precedure and joint design to ascertain welding requirements.
Review delta ferrite records for a sample of RC welds and verify some actual ferrite readings. If ferrite is present in sufficient quantity in J
the welds, this will indicate that " excessive" heat was not used during weldings.
Review a sample of radiographs of RC welds or reference a previous NRC review of radiographs to establish soundness of RC joints.
Itsn 8:
The alleger stated that he had no personal knowledge, but had heard that CEAs were being improperly installed. He also stated that " failed" CEAs were being dispositioned use-as-is via the Getschow 9006 Form.
Recommended NRC Action:
The Region III staff is currently aware of the CEA installation issue and will continue to monitor licensee progress on the 50.55(e). The inspector will review a sample of the completed 9006 Forms for proper disposition.
Item 9:
The alleger stated that many structural welds contained undercut. When asked for specifics he replied "just look anywhere in the plant." The NRC inspector explained the recently adopted VWAC provisions for undercut
,..o and the reasons behind this provision. He replied that he had no problem with it then.
Recomended NRC Action:
Perfonn a visual weld inspection of a sample of structural welds.
Additional Items of Concern:
- a. Inspect hanger ICV 15014S for proper installation. The alleger stated that this hanger was installed misaligned and that the supervision said to " wait and see if Q.C. catches it."
Recommended NRC Action:
Inspect hanger.
- b. Hanger 1FP12005R had to be drilled out for load pin to fit. His concern is that this may not be the proper hanger.
Recommended NRC Action:
Inspect hanger.
The alleger was told the extent of the proposed action for each item and indicated satisfaction with our response.