Text
M==
Log iTXX-88710 4
File # 10110 C
C
- 903.8 Ref. # 10CFR50.55(e)
TUELECTRIC September 30, 1988 wuum c. co.mu EnrMvr Vke Pte,idret U, S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C.
20555 l
SUBJECT:
COMANCHE PEAK STEAM ELECTRIC STATION (CPSES) i DOCKET N05. 50-445 AND 50-446 SEISMIC GAP SDAR: CP-85-27 (SUPPLEMENTAL REPORT)
Gentlemen:
On December 17, 1985, TV Electric letter logged TXX-4650 provided notification that the deficiency involving the seismic gap between structures was reportable under the provisions of 10CFR50.55(e).
The latest report on this issue, logged TXX-88434, was submitted June 28, 1988.
This report is submitted to update the corrective action completion schedule.
TXX-88434 indicated that the Unit 1 corrective actions for this issue would be completed by October 1, 1988.
This activity has been rescheduled for completion by February 23, 1989.
The schedule for Unit 2 remains unchanged.
I Very truly yours, W. G. Counsil By.
M.
J6hn W. Beck Vice President, Nuclear Engineering CBC/gj c - Mr. R. D. Martin, Region IV
{
Resident inspectors, CPSES (3)
)