ML20154P924

From kanterella
Jump to navigation Jump to search
Supplemental Deficiency Rept CP-85-27 Re Seismic Gap Between Structures.Initially Reported on 851217.Completion of Corrective Actions Rescheduled Until 890223.Schedule for Unit 2 Unchanged
ML20154P924
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 09/30/1988
From: Beck J
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
CP-85-27, TXX-88710, NUDOCS 8810030229
Download: ML20154P924 (1)


Text

M

==

Log iTXX-88710

-- 4 File # 10110 C C # 903.8 TUELECTRIC Ref. # 10CFR50.55(e)

September 30, 1988 wuum c. co.mu EnrMvr Vke Pte,idret U, S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C. 20555 l

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION (CPSES) i' DOCKET N05. 50-445 AND 50-446 SEISMIC GAP SDAR: CP-85-27 (SUPPLEMENTAL REPORT)  ;

Gentlemen:

On December 17, 1985, TV Electric letter logged TXX-4650 provided notification that the deficiency involving the seismic gap between structures was '

reportable under the provisions of 10CFR50.55(e). The latest report on this -

issue, logged TXX-88434, was submitted June 28, 1988. This report is -

submitted to update the corrective action completion schedule.

TXX-88434 indicated that the Unit 1 corrective actions for this issue would be completed by October 1, 1988. This activity has been rescheduled for completion by February 23, 1989. The schedule for Unit 2 remains unchanged.

I Very truly yours, W. G. Counsil By. M.

J6hn W. Beck Vice President, Nuclear Engineering CBC/gj c - Mr. R. D. Martin, Region IV {

Resident inspectors, CPSES (3) '

l

)

8810030229 880930 PDR S ADOCK 05000445 PDC 55&)