Responds to Generic Ltr 88-03 Re Generic Issue 93, Steam Binding of Auxiliary Feedwater Pumps. Verified That Procedures Remain in Place to Monitor Fluid Conditions within Auxiliary Feedwater Sys Each Shift
ML20154M468
Person / Time
Site: Rancho Seco
Issue date: 05/25/1988
From: Andognini G
SACRAMENTO MUNICIPAL UTILITY DISTRICT
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
TASK-093, TASK-93, TASK-OR GCA-88-348, GL-88-03, GL-88-3, IEB-85-001, IEB-85-1, NUDOCS 8806010292
Download: ML20154M468 (2)


Text

_ _ _ _ _ _ _ _ _ - _ _ _ _ _ _

' S'M U =

f

~

SACRAMENTO MUNICIPAL UTILITY DISTRICT O 62o1 S Street. P.o. Box 15830, Sacramento CA 95852 1830,(918) 452 3211 AN ELECTRIC SYSTEM SERVING THE HEART OF CALIFORNIA

'8 Av 2 51988 GCA 88-348 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 Docket No. 50-312 Rancho Seco Nuclear Generating Station License No. DPR-54 RESPONSE TO GENERIC LETTER 88-03

Reference:

R. J. Rodriguez to J. B. Martin letter dated February 27, 1986, Response to IE Bulletin 85-01

Dear Sirs:

Generic Letter 88-03 resolves Generic Safety Issue 93, "Steam Binding of Auxiliary Feedwater Pumps," by perpetuating the recommendations of IE Bulletin 85-01. The referenced correspondence provides the Rancho Seco response to IE l Bulletin 85-01.

Pursuant to the requirements of Generic Letter 88-03, Rancho Seco has verified that procedures remain in place to:

1) monitor fluid conditions within the AFW system each shift during times when the system is required to be operable. (This nonitoring ensures that fluid temperature at the AFW pump discharge is maintained at ambient conditions), and
2) recognize steam binding and restore the AFW system to operable status should steam binding occur.

Rancho Seco will continue to maintain these procedures.

Pursuant to the request contained in Generic Letter 88-03, the following estimates are provided for your information: staff time to perform required confirmation (1 hot!r); staff time to prepare required documentation (12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />).

I l

8806010292 880525 PDR ADOCK 05000312 gk P DCD RANCHO SECO NUCLEAA GENERATING STATION O 1444o Twin Cities Road. Herald, CA 95638 9799; GO9) 333 2935

MAY 2 51998

. Document Control Desk GCA 88-348 3

Members of your staff with questions requiring additional information or clarification may contact Mr. Steve L. Crunk at (209) 333-2935, extension 4913.

State of California SS County of Sacramento G. Carl Andognini, being first duly sworn, deposes and says: that he is CEO, Nuclear of Sacramento Municipal Utility District (SMUD), the licensee herein; that he has executed the foregoing document; that the statements made in this document are true and correct to the best of his knowledge, information, and belief, and that he is authorized to execute the document on behalf of said licensee.

ww GT Cp(1 An4egninf f ~

~

Chief Executive Officer, Nuclear Subscribed and affirmed to before me this 46 day of NS/ ,1917r.