UNIVERSITY OF MISSOURI RESEARCH REACTOR OPERATIO.NS MONTHLY
SUMMARY
/
~
' (Q,J s
tJ h
MAY 1998 Prepared by:
f)
Operations Staff 1rmiro J.L J ~
9810200250 980531 DR ADOCK 05000186 PDR' Jun i21 Nil l
e May 1998
. The reactor operated continuously in May with the following exceptions: four shutdowns for scheduled maintenance and/or refueling.
Two NRC inspectors visited the facility to review our exempt release license. No violations and no areas of concern were noted.
Major maintenance items for the month included: conducting the annual containment building leak rate test; shipping 16 spent fuel elements to the Department of Energy's Savannah River Site in South Carolina.
OPERATIONS
SUMMARY
HOURS OPERATED THIS PERIOD 692 TOTAL HOURS. OPERATED 212,000 HOURS AT FULL POWER THIS PERIOD 689 TOTAL HOURS AT FULL POWER 208,901 INTEGRATED POWER THIS PERIOD 287 MWD TOTAL INTEGRATED POWER S1,194 MWD MAINTENANCE ACTIVITIES
~
05/04/98 Refueled - removed core 98-23, loaded core 98-24.
05/11/98 Refueled - removed core 98-24, loaded core 98-25. Performed annual containment building leak rate test.
05/18/98 Refueled - removed core 98-25, loaded core 98-26.
05/25/98 Refueled removed core 98 26, loaded core 98-27.