pn Moug$'g UNITED STATES NUCLEAR REGULATORY COMMisslON e
o REGION 111 7
GLEN ELLYN, ILLINOIS 60137 gr
~f WAY I8E MEMORANDUM FOR:
Thomas E. Murley, Director, Office of Nuclear Reactor Regulation j
FROM:
A. Bert Davis, Regional Administrator
SUBJECT:
REGION III RECOMMENDATION FOR THE ISSUANCE OF A FULL POWER LICENSE FOR BRAIDWOOD STATION UNIT 2 I
We have completed our review of all matters that were required to be completed prior to exceeding 5 percent power. We have found that those matters have been satisfactorily completed.
With the exception of those deferrals and exemptiens identified in the full power license, we believe Braidwood Station Unit 2 has been properly constructed and tested and can be operated safely at 100 percent power.
Therefore, we recomend that a full power license be issued for Braidwood Station Unit 2.
d&J6M A. Bert Davis Regional Administrator cc: