MONTHYEARML24029A2752024-01-29029 January 2024 Request to Reschedule Evaluated Force-on-Force Drill IR 05000498/20230042024-01-29029 January 2024 Integrated Inspection Report 05000498/2023004 and 05000499/2023004 ML24024A1162024-01-24024 January 2024 STP Unit 2 Request for Information IR 05000498/20244042024-01-18018 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000498/2024404; 05000499/2024404 IR 05000498/20230032023-12-28028 December 2023 Acknowledgment of Reply to a Notice of Violation (NRC Inspection Report 05000498/2023003 and 05000499/2023003) ML23360A1692023-12-26026 December 2023 FEMA, Submittal of Radiological Emergency Preparedness Final Report for the South Texas Project Medical Services Drill Evaluated on August 31, 2023 NOC-AE-230040, Supplement to Proposed Alternate Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (Relief Request RR-ENG-4-06)2023-12-14014 December 2023 Supplement to Proposed Alternate Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (Relief Request RR-ENG-4-06) NOC-AE-230039, Docket Nos. Stn 50-498, Stn 50-499 - Reply to a Notice of Violation, NRC Inspection Report 05000498/2023003 and 05000499/20230032023-12-12012 December 2023 Docket Nos. Stn 50-498, Stn 50-499 - Reply to a Notice of Violation, NRC Inspection Report 05000498/2023003 and 05000499/2023003 ML23326A2592023-12-0505 December 2023 Review of the Fall 2022 Steam Generator Tube Inspection Report ML23339A1902023-12-0505 December 2023 Update Foreign Ownership, Control, or Influence (FOCI) IR 05000498/20234012023-12-0404 December 2023 Security Baseline Inspection Report 05000498/2023401 and 05000499/2023401 ML23324A0102023-11-16016 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23310A2282023-11-13013 November 2023 Integrated Inspection Report 05000498/2023003 and 05000499/2023003, and Notice of Violation ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML23298A0002023-11-0101 November 2023 the Associated Independent Spent Fuel Storage Installation - Issuance of Amendment Nos. 226 and 211 Related to Order Approving Indirect Transfer of Licenses and Conforming License Amendments ML23303A0782023-10-30030 October 2023 Submittal of Supplemental Information in Response to Order Consenting to License Transfers and Approval of Draft Conforming License Amendments ML23279A0342023-10-30030 October 2023 Associated Independent Spent Fuel Storage Installation - Order Approving Indirect Transfer of Licenses and Draft Conforming License Amendments (EPID L-2023-LLM-0004) (Letter) IR 05000498/20234032023-10-26026 October 2023 Material Control and Accounting Program Inspection Report 05000498/2023403 and 05000499/2023403 (Cover Letter) ML23317A1262023-10-12012 October 2023 South. Texas Project Physical Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program Revision 26 ML23279A1382023-10-0505 October 2023 Responses to Requests for Additional Information Related to Application for Order Approving Indirect Transfer of Control of Licenses ML23271A1942023-10-0303 October 2023 Notification of Commercial Grade Dedication Inspection (05000498/2024013 and 05000499/2024013) and Request for Information ML23270B2592023-09-27027 September 2023 Update Foreign Ownership, Control, or Influence ML23263B1132023-09-20020 September 2023 Operator Licensing Examination Schedule Revision 1 IR 05000498/20243012023-09-0707 September 2023 Notification of NRC Initial Operator Licensing Examination 05000498/2024301; 05000499/2024301 IR 05000498/20233012023-09-0101 September 2023 NRC Examination Report 05000498/2023301 and 05000499/2023301 ML23243B0562023-08-31031 August 2023 Supplemental Information to Application for Order Approving Indirect Transfer of Control of Licenses ML23236A6042023-08-24024 August 2023 Annual Dose Report for 2022 IR 05000498/20230052023-08-22022 August 2023 Updated Inspection Plan for South Texas Project Electric Generating Station, Units 1 and 2 (Report 05000498/2023005 and 05000499/2023005) - Mid Cycle Letter ML23229A5262023-08-17017 August 2023 Inservice Inspection Summary Report - 1 RE24, ML23229A5892023-08-17017 August 2023 Voluntary Response to Regulatory Issue Summary (RIS) 2023-02, Scheduling Information for the Licensing of Accident Tolerant, Increased Enrichment, and Higher Burnup Fuels ML23229A4992023-08-17017 August 2023 Supplement to Proposed Alternate Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (Relief Request RR-ENG-4-06) ML23228A2102023-08-15015 August 2023 Closure of Investigation (OI 4-22-19) ML23222A0322023-08-10010 August 2023 Report of Changes Made to Quality Assurance Program for Radioactive Material Packages ML23221A3002023-08-0909 August 2023 RE22 Inspection Summary Report for Steam Generator Tubinq, Rev. 1 (Epld L-2023-LRO-0029) ML23222A2792023-08-0909 August 2023 Submittal of Update Foreign Ownership, Control, or Influence (FOCI) IR 05000498/20230022023-07-28028 July 2023 Integrated Inspection Report 05000498/2023002 and 05000499/2023002 ML23198A0532023-07-24024 July 2023 Request for Withholding Information from Public Disclosure ML23188A1612023-07-14014 July 2023 the Associated ISFSI - Notice of Consideration of Approval of Indirect Transfer of Licenses and Conforming Amendments and Opportunity to Request a Hearing (EPID L-2023-LLM-0004) - Letter ML23193A9932023-07-11011 July 2023 Submittal of Update Foreign Ownership, Control or Influence (FOCI) ML23192A0482023-07-11011 July 2023 NRC Initial Operator Licensing Examination Approval 05000498/2023301; 05000499/2023301 NOC-AE-230039, Submittal of Update Foreign Ownership, Control or Influence (FOCI)2023-07-11011 July 2023 Submittal of Update Foreign Ownership, Control or Influence (FOCI) ML23180A2822023-06-29029 June 2023 Operator Licensing Examination Schedule ML23177A2522023-06-26026 June 2023 Units 1, 2 & Independent Spent Fuel Storage Installation - Biennial Submittal of Technical Specification Bases Changes, Commitment Changes, 10 CFR 50.59 Evaluation Summary, and 10 CFR 72.48 Evaluation Summary ML23166B0802023-06-14014 June 2023 Update Foreign Ownership, Control, or Influence (FOCI) ML23163A1762023-06-12012 June 2023 Application for Order Approving Indirect Transfer of Control of Licenses 2024-01-29
[Table view] Category:Response to Request for Additional Information (RAI)
MONTHYEARML22326A2962022-11-22022 November 2022 Clarification on STPNOC Response to Request for Additional Information Regarding Request for Approval of Alternate Disposal Procedures for Very Low-Level Radioactive Material ML22244A1152022-09-0101 September 2022 Response to NRC Comments on Relief Request RR-ENG-3-25 ML22231A4692022-08-19019 August 2022 STPNOC Response to Request for Additional Information Regarding Request for Approval of Alternate Disposal Procedures for Very Low-Level Radioactive Material ML22091A3082022-04-0101 April 2022 Supplement to Request for Exemption from Certificate of Compliance (CoC) Inspection Requirement for One Multipurpose Canister ML21308A6032021-11-0404 November 2021 Response to End of Enforcement Discretion and Request for Approval of Alternate Disposal Procedures for Very Low-Level Radioactive Material NOC-AE-21003846, Response to End of Enforcement Discretion and Request for Approval of Alternate Disposal Procedures for Very Low-Level Radioactive Material2021-11-0404 November 2021 Response to End of Enforcement Discretion and Request for Approval of Alternate Disposal Procedures for Very Low-Level Radioactive Material ML21067A7722021-03-0808 March 2021 Response to Request for Additional Information Regarding 1RE22 Inspection Summary Report for Steam Generator Tubing NOC-AE-21003784, Response to Request for Additional Information Regarding 1RE22 Inspection Summary Report for Steam Generator Tubing2021-03-0808 March 2021 Response to Request for Additional Information Regarding 1RE22 Inspection Summary Report for Steam Generator Tubing ML20154K7652020-06-0202 June 2020 Supplemental Response Regarding Bulletin 2012-01 NOC-AE-20003735, Supplemental Response Regarding Bulletin 2012-012020-06-0202 June 2020 Supplemental Response Regarding Bulletin 2012-01 NOC-AE-20003733, Response to Request for Additional Information for Proposed Alternatives to ASME OM Code 2012 Edition for the Fourth Inservice Test Interval (Relief Request PRR-01)2020-05-18018 May 2020 Response to Request for Additional Information for Proposed Alternatives to ASME OM Code 2012 Edition for the Fourth Inservice Test Interval (Relief Request PRR-01) ML20139A2162020-05-18018 May 2020 Response to Request for Additional Information for Proposed Alternatives to ASME OM Code 2012 Edition for the Fourth Inservice Test Interval (Relief Request PRR-01) NOC-AE-20003716, Request for Additional Information for Proposed Alternative to ASME Section XI Requirements for the Repair/Replacement of Essential Cooling Water System Class 3 Buried Piping2020-03-0909 March 2020 Request for Additional Information for Proposed Alternative to ASME Section XI Requirements for the Repair/Replacement of Essential Cooling Water System Class 3 Buried Piping ML20069L4992020-03-0909 March 2020 Request for Additional Information for Proposed Alternative to ASME Section XI Requirements for the Repair/Replacement of Essential Cooling Water System Class 3 Buried Piping NOC-AE-19003673, Response to Request for Additional Information for South Texas Project (STP) Units 1 & 2 License Amendment Request to Revise Technical Specification 3.8.1.1 (A.C. Sources, Operating) (L-2018-LLA-00782019-06-25025 June 2019 Response to Request for Additional Information for South Texas Project (STP) Units 1 & 2 License Amendment Request to Revise Technical Specification 3.8.1.1 (A.C. Sources, Operating) (L-2018-LLA-0078 NOC-AE-19003637, Supplement to South Texas Project (STP) Units 1 & 2 License Amendment Request to Revise Technical Specification 3.8.1.1 (A.C. Sources, Operating) (L-2018-LLA-0078)2019-05-16016 May 2019 Supplement to South Texas Project (STP) Units 1 & 2 License Amendment Request to Revise Technical Specification 3.8.1.1 (A.C. Sources, Operating) (L-2018-LLA-0078) NOC-AE-18003602, Response to Request for Additional Information for License Amendment Request to Revise Technical Specification 3.8.1.1 (A.C. Sources, Operating)2018-12-0606 December 2018 Response to Request for Additional Information for License Amendment Request to Revise Technical Specification 3.8.1.1 (A.C. Sources, Operating) NOC-AE-18003598, Response to Request for Additional Information Request for Relief from the Third 10-Year Interval ISI Program ASME Section Xl Code Requirements for Category B-N-2 and B-N-3 Welds (Relief Request RR-ENG-3-16)2018-09-26026 September 2018 Response to Request for Additional Information Request for Relief from the Third 10-Year Interval ISI Program ASME Section Xl Code Requirements for Category B-N-2 and B-N-3 Welds (Relief Request RR-ENG-3-16) NOC-AE-18003574, Response to Request for Additional Information Regarding Request for Exemption from 10 CFR 55.472018-05-21021 May 2018 Response to Request for Additional Information Regarding Request for Exemption from 10 CFR 55.47 NOC-AE-17003441, Revised Response Request for Additional Information for the Review of the South Texas Project License Renewal Application2017-02-0909 February 2017 Revised Response Request for Additional Information for the Review of the South Texas Project License Renewal Application NOC-AE-17003434, Response to Request for Additional Information on Revised Applicability Matrix for Questions Regarding Risk-Informed GSI-191 Licensing Application2017-01-19019 January 2017 Response to Request for Additional Information on Revised Applicability Matrix for Questions Regarding Risk-Informed GSI-191 Licensing Application NOC-AE-17003435, Response to NRC Security Reactive Inspection Report 05000498/2016407, 05000499/2016407, EA-16-2502017-01-19019 January 2017 Response to NRC Security Reactive Inspection Report 05000498/2016407, 05000499/2016407, EA-16-250 IR 05000498/20164072017-01-19019 January 2017 South Texas Project, Units 1 and 2 - Response to NRC Security Reactive Inspection Report 05000498/2016407, 05000499/2016407, EA-16-250 NOC-AE-16003428, Response to Request for Additional Information for the Review of License Renewal Application2017-01-12012 January 2017 Response to Request for Additional Information for the Review of License Renewal Application NOC-AE-16003429, Response to Requests for Additional Information for Review License Renewal Application - RAI 82.1.8-32017-01-0505 January 2017 Response to Requests for Additional Information for Review License Renewal Application - RAI 82.1.8-3 NOC-AE-16003427, Revised Applicability Matrix for Response to Request for Additional Information Questions APLA-1a and APLA-1b Regarding STP Risk-Informed GSl-191 Licensing Application2016-12-0707 December 2016 Revised Applicability Matrix for Response to Request for Additional Information Questions APLA-1a and APLA-1b Regarding STP Risk-Informed GSl-191 Licensing Application ML16321A4072016-11-0909 November 2016 Response to Request for Additional Information Regarding Sensitivity Studies for STPNOC Risk-Informed Pilot GSl-191 Application NOC-AE-16003356, Flooding Mitigating Strategies Assessment (MSA) Report Submittal2016-09-29029 September 2016 Flooding Mitigating Strategies Assessment (MSA) Report Submittal NOC-AE-16003404, Response to Request for Additional Information for the Review of License Renewal Severe Accident Mitigation Alternatives2016-09-27027 September 2016 Response to Request for Additional Information for the Review of License Renewal Severe Accident Mitigation Alternatives NOC-AE-16003412, Revised Response to Request for Additional Information APLA-4-4 STP Risk-Informed GSI-191 Licensing Application2016-09-12012 September 2016 Revised Response to Request for Additional Information APLA-4-4 STP Risk-Informed GSI-191 Licensing Application NOC-AE-16003394, Additional Information for the Review of the South Texas Project, Units 1 and 2, License Renewal Application - Aluminum Bronze AMP (TAC Nos. ME4936 and ME4937)2016-07-28028 July 2016 Additional Information for the Review of the South Texas Project, Units 1 and 2, License Renewal Application - Aluminum Bronze AMP (TAC Nos. ME4936 and ME4937) ML16230A2322016-07-21021 July 2016 Responses to Apla Round 4 Requests for Additional Information Regarding STP Risk-Informed GSl-191 Licensing Application NOC-AE-16003395, Third Set of Responses to Requests for Additional Information STP Risk-Informed GSI-191 Licensing Application2016-07-21021 July 2016 Third Set of Responses to Requests for Additional Information STP Risk-Informed GSI-191 Licensing Application NOC-AE-16003368, Third Sets of Responses to April 11, 2016 Requests for Additional Information Regarding STP Risk-Informed GSI-191 Licensing Application2016-07-18018 July 2016 Third Sets of Responses to April 11, 2016 Requests for Additional Information Regarding STP Risk-Informed GSI-191 Licensing Application NOC-AE-16003328, Second Supplement to Response to RAI for Information Pursuant to 10 CFR 50.54(f) Recommendation 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident: Phase 2 Staffing Assessment2016-06-30030 June 2016 Second Supplement to Response to RAI for Information Pursuant to 10 CFR 50.54(f) Recommendation 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident: Phase 2 Staffing Assessment NOC-AE-16003367, Second Set of Responses to April 11, 2016 Requests for Additional Information Regarding Risk-Informed GSI-191 Licensing Application2016-06-16016 June 2016 Second Set of Responses to April 11, 2016 Requests for Additional Information Regarding Risk-Informed GSI-191 Licensing Application NOC-AE-16003380, Request for Additional Information Set 35 for the Review of the South Texas Project, Units 1 and 2, License Renewal Application (TAC Nos. ME4936 and ME4937)2016-05-19019 May 2016 Request for Additional Information Set 35 for the Review of the South Texas Project, Units 1 and 2, License Renewal Application (TAC Nos. ME4936 and ME4937) NOC-AE-16003366, First Set of Responses to April 11, 2016 Requests for Additional Information Regarding STP Risk-Informed GSl-191 Licensing Application2016-05-11011 May 2016 First Set of Responses to April 11, 2016 Requests for Additional Information Regarding STP Risk-Informed GSl-191 Licensing Application NOC-AE-16003357, Revision to Proposed Exemption to 10CFR50.46 Described in Pilot Submittal and Requests for Exemptions and License Amendment for a Risk-Informed Approach to Address Generic Safety Issue (GSl)-191 and Respond To..2016-04-13013 April 2016 Revision to Proposed Exemption to 10CFR50.46 Described in Pilot Submittal and Requests for Exemptions and License Amendment for a Risk-Informed Approach to Address Generic Safety Issue (GSl)-191 and Respond To.. NOC-AE-16003347, Response to Request for Additional Information Regarding the License Amendment Request for Extension of Containment Leakage Rate Testing Program2016-03-17017 March 2016 Response to Request for Additional Information Regarding the License Amendment Request for Extension of Containment Leakage Rate Testing Program NOC-AE-16003348, Response to Request for Additional Information for License Renewal Application 2014 Annual Update (Tac. Nos. ME4936 and ME4937)2016-03-10010 March 2016 Response to Request for Additional Information for License Renewal Application 2014 Annual Update (Tac. Nos. ME4936 and ME4937) NOC-AE-15003320, Response to Request for Additional Information Set 34 for the Review of the License Renewal Application2015-12-17017 December 2015 Response to Request for Additional Information Set 34 for the Review of the License Renewal Application NOC-AE-15003318, Response to Request for Additional Information and Supplement to Emergency License Amendment Request to Revise Technical Specification 5.3.2 to Allow Operation with 56 Full-Length Control Rod Assemblies for Cycle 202015-12-0909 December 2015 Response to Request for Additional Information and Supplement to Emergency License Amendment Request to Revise Technical Specification 5.3.2 to Allow Operation with 56 Full-Length Control Rod Assemblies for Cycle 20 NOC-AE-15003303, Response to Request for Additional Information for the Review of the License Renewal Application - Set 322015-11-12012 November 2015 Response to Request for Additional Information for the Review of the License Renewal Application - Set 32 NOC-AE-15003296, Request for Additional Information Regarding the License Amendment Request for Extension of Containment Leakage Rate Testing Program2015-10-0808 October 2015 Request for Additional Information Regarding the License Amendment Request for Extension of Containment Leakage Rate Testing Program ML15251A2492015-10-0505 October 2015 Summary of Telephone Conference Call Held on August 6, 2015, Between the U.S. Nuclear Regulatory Commission and STP Nuclear Operating Company, Concerning Request for Additional Information, Set 32, Pertaining to the South Texas Project, Lic ML15246A1282015-08-20020 August 2015 Attachment 1-5 Response to 2009 RAIs Through 1-6 Responses to Round 2 RAIs NOC-AE-15003278, Response to Request for Additional Information for the Review of License Renewal Application - Set 312015-07-29029 July 2015 Response to Request for Additional Information for the Review of License Renewal Application - Set 31 NOC-AE-15003276, Response to Request for Additional Information Regarding Relief Request RR-ENG-3-17 Regarding Deferral of Inservice Inspection of Reactor Pressure Vessel Cold Leg Nozzle Dissimilar Metal Butt Welds2015-07-22022 July 2015 Response to Request for Additional Information Regarding Relief Request RR-ENG-3-17 Regarding Deferral of Inservice Inspection of Reactor Pressure Vessel Cold Leg Nozzle Dissimilar Metal Butt Welds NOC-AE-15003255, Supplement to Response to Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident - Phase 2 Staffing Assessment2015-07-0202 July 2015 Supplement to Response to Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 9.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident - Phase 2 Staffing Assessment 2022-09-01
[Table view] |
Text
June 2, 2020 NOC-AE-20003735 10 CFR 50.4 STI: 35018831 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 South Texas Project Units 1 and 2 Docket Nos. STN 50-498 and STN 50-499 Supplemental Response Regarding Bulletin 2012-01
References:
- 1. Letter from NRC to All Power Reactor Licensees; Request for Additional Information Regarding Response to Bulletin 2012-01, Design Vulnerability in Electrical Power System"; December 20, 2013; ML13351A314.
- 2. Letter from G.T. Powell to NRC Document Control Desk, STPNOC Response to Request for Additional Information regarding Response to Bulletin 2012-01, Design Vulnerability in Electrical Power System; January 30, 2014; NOC-AE-14003077; ML14043A117.
By Reference 2, STP Nuclear Operating Company (STPNOC) provided a response to the NRC request in Reference 1. STPNOC completed the analysis initiated in Reference 2 regarding the Class 1E loss of voltage and degraded voltage relaying systems. STPNOC determined that the relaying systems can detect and protect against a consequential Open Phase Condition and no modifications to the plant are required. Further technical explanation is provided in the attached Enclosure.
There are no commitments in this letter.
If there are any questions regarding this letter, please contact Zachary Dibbern at (361) 972-4336 or me at (361) 972-7743.
Roland Dunn Jr.
General Manager, Engineering ZD
Enclosure:
STPNOC Response to Follow-Up NRC Information Request
NOC-AE-20003735 Page 2 of 2 cc:
Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 1600 E. Lamar Boulevard Arlington, TX 76011-4511
NOC-AE-20003735 Enclosure Page 1 of 2 STPNOC Response to Follow-Up NRC Information Request Please note that Open Phase Condition (OPC) responses previously provided for STP Units 3 and 4 are no longer applicable because the Construction and Operating Licenses for those units have been cancelled, and therefore this response only pertains to STP Units 1 and 2.
The information in this correspondence provides additional technical information to accurately reflect the STP Nuclear Operating Company (STPNOC) OPC resolution strategy.
STP has three independent offsite power sources which are the unit auxiliary transformers via backfeed from the main transformers and the two standby transformers. For a single open phase without a ground fault on the high-voltage side of the main transformers, the main transformers recreate the lost phase on the secondary side of the transformer due to the wye-delta configuration and their large Megavolt Amp (MVA) rating. For a single open phase on the high-voltage side of the standby transformer or a single open phase with a ground fault on the high-voltage side of the main transformers or standby transformers, the Class 1E loss of voltage or degraded voltage bus relaying will trip the Class 1E 4.16 kV buses, which then automatically realign to be powered by the Emergency Diesel Generators. NRC Bulletin 2012-01 (ML12074A115) discusses the possibility that an open phase condition, with or without accompanying ground faults, located on the high-voltage side of a transformer connecting a General Design Criteria (GDC) 17 offsite power circuit to the plant electrical system could result in a degraded condition in the onsite power system. The requests and industry schedules provided in NRC Bulletin 2012-01 and Nuclear Energy Institute (NEI) OPC Industry Guidance Document (NEI 13-12, December 2013) have been met as documented in STPNOCs January 30, 2014, response (ML14043A117) to the NRCs December 20, 2013, Request for Additional Information (RAI) (ML13351A314). STPNOCs RAI response stated that a vulnerability study and calculations were to be completed in accordance with the NEI 13-12 (December 2013) schedule as part of STPNOCs strategy for resolving this issue. STPNOC performed calculation 14PK007 and determined that no modifications to the plant were required to address the industry OPC issue.
STPNOC calculation 14PK007 demonstrates that the existing Class 1E 4.16 kV bus loss of voltage and degraded voltage relaying will detect and protect Class 1E loads from a consequential single open phase condition. In addition, this calculation demonstrates that if there is a single open phase on the high-voltage side of the generator step-up transformers (also known as the Main Transformers), then the lost phase will be recreated on the secondary side of the transformers without adversely impacting Class 1E loads. Therefore, based on the calculation 14PK007 results, STPNOC concluded that no modifications to the plant were required to address the open phase condition industry issue.
There is no vulnerability on the high-voltage side of the Main Transformers. Specifically, STPNOC calculation 14PK007 demonstrates that if there is a single open phase on the high-voltage side of the Main Transformers, then the lost phase will be recreated on the secondary side of the transformers without adversely impacting Class 1E loads. ANSI/IEEE C50.41 recommends maintaining a voltage imbalance of less than 5%; therefore, the acceptance criteria in STPNOC calculation 14PK007 for negative sequence bus voltage is less than 4%
voltage imbalance. Given these calculation results, STPNOC concluded that no modifications to the plant were required to address an open phase condition on the high-voltage side of the Main Transformers and the existing relays were adequate in detecting and protecting against an OPC.
NOC-AE-20003735 Enclosure Page 2 of 2 There is a vulnerability on the high-voltage side of the Standby Transformers. Specifically, STPNOC calculation 14PK007 demonstrates that if there is a single open phase on the high-voltage side of the Standby Transformers, the Class 1E loss of voltage or degraded voltage bus relaying will automatically trip and protect the Class 1E 4.16 kV buses from a consequential OPC. With respect to applicable testing and monitoring programs, the existing Class 1E 4.16 kV bus loss of voltage and degraded voltage relaying already have previously established periodic testing, calibrations, setpoint verifications, and inspections. In addition, the surveillance requirements for the existing Class 1E 4.16 kV bus loss of voltage and degraded voltage relaying are already in the STP Units 1 and 2 Technical Specifications.
Based on the results of calculation 14PK007 and the existing Class 1E 4.16 kV bus loss of voltage and degraded voltage relaying detection and protection capabilities, STPNOC concluded that no modifications to the plant were required to address an open phase condition on the high-voltage side of the Standby Transformers.