Informs That Quad Cities Nuclear Power Station Is Proceeding to Implement Performance Centered Maint Program & Expects That Action Step 10 Will Be Completed by End of May 1999
ML20154F138
Person / Time
Site: Quad Cities  Constellation icon.png
Issue date: 10/02/1998
From: Krich R
COMMONWEALTH EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9810090088
Download: ML20154F138 (1)


Text

.-

Commonweahh Edtson Comguny c

1400 Opus Place Downen Grm e, IL 60515-5701 l

\\

October 2,1998 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 Quad Cities Nuclear Power Station, Units 1 and 2 Facility Operating License Nos. DPR-29 and DPR-30 NRC Dock.el Nos. 50-254 and 50-265 i

Subject:

Delay in Implementation of a Strategic Rerform Initiative Action Step

Reference:

Comed letter, " Integration of Section 50.54(f) Commitments Into the Nuclear Generation Group Strategic Reform Initiatives," dated February 17,1998 The Commonwealth Edison (Comed) Company Nuclear Generation Group (NGG)

Strategic Reform Initiatives (SRIs) and associated work plans are described in the referenced letter. Action Step 10 of the work plan fot Strategic Reform Initiative

)

NGG-3, " Ensure Excellence in Plant Material Condition," stated that the Perfonnance Centered Maintenance (PCM) program would be implemented at all sites by August 30,1998.

During the Commonwealth Performance Oversight Panel (CPOP) meeting held with the Nuclear Regulatory Commission (NRC) on June 30,1998, representatives of Comed stated that any missed milestones in the SRI work plans would be identified to the h%C.

At the next CPOP meeting held on September 14.1998, representatives of Comed informed the NRC that NGG-3, Action Step 10 was not completed on schedule at the L

Quad Cities Nuclear Power Station. Quad Cities Nuclear Power Station is proceeding to implement the PCM program and expects that Action Step 10 will be completed by the end of May,1999.

If there are any questions or comments concerning this letter, please refer them to Mr. B. Rybak at (630) 663-7286.

Respectfull,

R. M. Kri h Vice President - Regulatory Services cc:

Regional Administrator-NRC Region III NRC Senior Resident Inspector - Quad Cities Nuclear Power Station

^^~

9810090088 981002 PDR ADOCK 05000254l P