cooce***********************************************************************
UNIT 1 OPERATING DATA REPORT coco ************************************************************************
Docket No. 50-317 May 17, 1988 Prepared by C.Behnke Telephone:(301)260-4871 OPERATING STATUS
~~~~. -~~~~~~~~~
l l
- 1. UNIT NAME Calvert Cliffs Unit 1
- 2. REPORTING PERIOD APRIL 1988
- 3. LICENSED THERMAL POWER (MWT) 2700 1
- 4. NAMEPLATE RATING (GROSS MWe) 918 l
S.
DESIGN ELECTRICAL RATING (NET MWe) 845
- 6. MAXIMUM DEPENDABLE CAP'Y (GROSS MWe) 860
- 7. MAXIMUM DEPENDABLE CAP'Y (NET MWe) 825
- 8. CHANGE IN CAPACITY RATINGS none 9.
POWER LEVEL TO WHICH RESTRICTED n/a
- 10. REASONS FOR RESTRICTIONS n/a Cumulative This month Year-to-Dato to Dato
- 11. HOURS IN REPORTING PERIOD 719 2,903 113,796
- 12. NUMBER OF HOURS REACTOR WAS CRITICAL 194.3 2,378.3 88,765.5
- 13. REACTOR RESERVE SHUTDOWN HOURS 0.0 0.0 3,019.4
- 14. HOURS GENERATOR ON LINE 192.9 2,351.3 86,804.2
- 15. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 0.0
- 16. GROSS THERRAL ENERGY GENERATED (MWH) 470,945 6,099,545 218,174,263 l
- 17. GROSS ELECTRICAL ENERGY GEN'TED(MWH) 158,913 2,051,480 72,267,192 l
- 18. NET ELECTRICAL ENERGY GENERATED (MWH) 151,894 1,967,731 69,003,692
- 19. UNIT SERVICE FACTOR 26.8 81.0 76.3 l
- 20. UNIT AVAILABILITY FACTOR 26.8 81.0 76.3
- 21. UNIT CAPACITY FACTOR (USING MDC NET) 25.6 82.2 73.5
- 22. UNIT CAPACITY FACTOR (USING DE3 NET) 25.0 80.2 71.8
- 23. UNIT FORCED OUTAGE RATE 0.0 1.1 9.9
- 24. SHUTDOWNS SCHEDULED OVER THE NEXT SIX MONTHS (TYPE, DATE AND DURATION):
l None
- 25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF START-UP:
May 29, 1988 Note: Line 21 "Cumulative" factor no longer uses a weighted average.
8805180137 880430 PDR ADOCK 05000317 4,,v R
DCD y
.... -. _. -. -. ~..
_....-..-... -. -._--~ -
~_-.- _=_
o l
~
IHelf S.ItrI11tWlES AMI I1MIR R!111ETI(Mei IIIKXIT Mt.
50-317 IMIT IIADE Calvert Cliffs-U1 BRATE May 11. 1988 03rIE nn ny C. Behnke Rf'filRT M19FI13 __Alr11. 1988 W3EI1erieE (301)260-4871 m
s O
a C~
ta C tt a C
I. i e rs tav
(
g'Q Caeise? & Coraret.ive
,o [
C 33y No.
D.it e S
p t l'.ves it u o
,% t. i. w e t o i
v" e
v, n6 m
.= a ec
<y 6
\\
O I*t v tetil Recairt vtW'e j
hh
]g Re1M D8't M gy H
d
.>>g u
I 6
i 88-02 880409 S
526.1 C
1 N/A N/A N/A Shutdown for Refueling operations.
j 1
l i
l l
l l
l l
l l
l 1
I 17 :
l'osteil -
Rease ni:
Ph41mul:
I:xliiliit. C-Inst nert.insis S: Selw sholed A-lipilgunctit l'ailisse (I:xistain)
I -M.ismial for. I'nliaratisws of Dat.a i
ll-Hiint enance os Test.
241.irnial Screwn.
Int ry Sw ets for I,icesisc C-RefieeI i tin 3-hit <=natic Scraat.
Event Regwirt. (lIR) l'ile l
D-Regislatory Restrictiews 1-Otlp r (Exgilain)
(NtRIE-0161)
E-Ogn rat or Training & I.icense Evwninal inwi F-kiniinist rat.ive 5
E'I'I I'I l I -
8'"'"' 8'""'C" G-Og= rat iewial Errur (I:xgilaise)
II-Ot tw-r (l'.xgilain)
.._..,,._,4
r i
AVERAGE DAILY UNIT POWER LEVEL t
Docket No. 50-317 l
Calvert Cliffs Unit No. 1 May 12, 1988 i
Completed by C. Behnke Telephone: (301) 260-4871 MAY 1988 l
2 l
i Average Daily Power Level Average Daily Power Level Day (MWe-Net)
Day (MWe-Net) 1 841 17 0
i 2
841 18 0
3 804 19 0
l i
4 841 20 0
r 5
837 21 0
6 831 22 0
I 7
676 23 0
e 8
658 24 0
9 0
25 0
i 10 0
26 0
i r
a r
11 0
27 0
(
1 12 0
28 0
i i
13 0
29 0
14 0
30 0
t 15 0
f 16 0
1
(
t t
I I
t
?
1
Summary of U-l operating Experience April 1988 Date Time Event Description 4/1 0000 Began at 97% derated power (2nd Stage MSR, out of service due to leakage) 840 MWe (net).
4/6 1500 Reduced power for phase isolation testing (93%) to 820 MWe (net).
4/7 1110 Reduced power for Alterex testing.
At 2100, increasing power to 70%.
4/8 1115 SGFP testing.
4/8 2115 Ramp-down commenced for shutdown.
4/9 0152 Unit removed from grid, i
Summary of U-l operating Experience April 1988 The Unit began the month at the 97% derated maximum for out of service 2nd Stage MSR's (leakage).
Reduced power (1500) for phase isolation testing.
Remained at 93%
until 4/7/88 at 1300 when power was reduced to 50% for SGFP test-ing.
Unit returned to 97% (SAM) on 4/8/88.
Began ramp-down for shutdown at 1300.
Unit removed from the grid at 0152, 4/9/88 for Refuel-ing/ILRT Scheduled Outage.
Unit remained off-line through the end of this reporting period (scheduled to return on or about May 29th).
t
'+
l t
3 a
May 5, 1988 REWELING_1NMRMATION.. REQUEST a
1.
Name of facility: Calvert Cliffs Nuclear Power Plant, Unit No. 1.
4 2.
Scheduled date for next refueling shutdown: April 8, 1988 3.
Scheduled date for restart following refueling: May 26, 1988 i
4.
Will refueling or resumption of operation thereafter require a Technical i
I Specification change or other license amendment?
i 2
Resumption of operation arter refueling will require changes to Technical l
Specifications. The changes will be such as to allow operation of the plant with a fresh reload batch and reshuffled core for unit l's first 24 month 2
- cycle, j
)
5.
Scheduled date(s) for submitting proposed licensing action and supporting l
l information.
e February 17, 1988 (actual submittal date was February 12, 1988)
I i
i
(,
Important licensing considerations associated with the refueling.
Reload fuel will be similar to that reload fuel inserted into Calvert
]
Cliffs Unit 2 Eighth Cycle except for four lead demonstration assemblies manufactured by Advanced Nuclear Fuels i
7.
The number of fuel assemblies (a) in the core and (b) in the spent fuel f
storage pool.
(a) 217 (b) 1235 l
Spent fuel pools are common to Units 1 and 2.
8.
(a) The present licensed spent fuel pool storage capacity, and (b) the size j
j of any increase in licensed storage capacity that has been requested or is planned, in number of fuel assemblies, j
(a) 1830 (b) 0 f
}
1 9.
The proj ected date of the last refueling that can be discharged to the Spent Fuel Pool assuming the present licensed capacity and maintaining l
space for one full core offload.
i t
i April, 1991
}
l l
i I
i
coco ************************************************************************
UNIT 2 OPERATING DATA REPORT 0000c***********************************************************************
Docket No. 50-318
[
May 12, 1988 Prepared by C.Behnku l
Telephone:(301)260-4871 OPERATING STATUS
~~~~~ -~~~
- 1. UNIT NAME Calvert Cliffs Unit 2 2.
REPORTING PERIOD APRIL 1988 l
- 3. LICENSED THERMAL POWER (MWT) 2700 l
- 4. NAMEPLATE RATING (GROSS MWe) 918
- 5. DESIGN ELECTRICAL RATING (NET MWe) 845
- 6. MAXIMUM DEPENDABLE CAP'Y (GROSS MWe) 860
- 7. MAXIMUM DEPENDABLE CAP'Y (NET MWe) 825
- 8. CHANGE IN CAPACITY RATINGS none 9.
POWER LEVEL TO WHICH RESTRICTED n/a
- 10. REASONS FOR RESTRICTIONS n/a i
l Cumulativo i
This month Year-to-Date to Date l
__o....._____............__________.
- 11. HOURS IN REPORTING PERIOD 719 2,903 97,151
- 12. NUMBER OF HOURS REACTOR WAS CRITICAL 618.0 1,975.7 79,819.5
- 13. REACTOR RESERVE SHUTDOWN HOURS 0.0 0.0 1,296.6 i
- 14. HOURS GENERATOR ON LINE 613.4 1,966.3 78,647.9
- 15. UNIT RESERVE SHUTDOWN HOURS 0.0 0.0 0.0
- 16. GROSS THERMAL ENERGY GENERATED (MWH) 1,638,533 5,194,779 198,535,443
- 17. GROSS ELECTRICAL ENERGY GEN'TED(MWH) 551,496 1,762,169 65,650,270
- 18. NET ELECTRICAL ENERGY GENERATED (MWH) 5;v,227 1,691,405 62,632,463
- 19. UNIT SERVICE FACTOR 85.3 67.7 81.0
- 20. UNIT AVAILABILITY FACTOR 85.3 67.7 81.0
- 21. UNIT CAPACITY FACTOR (USING MDC NET) 89.4 70.6 78.2
- 22. UNIT CAPACITY FACTOR (USING DER NET) 87.3 69.0 76.4
- 23. UNIT FORCED OUTAGE RATE 12.4 5.0 5.6
- 24. SHUTDOWNS SCHEDULED OVER THE NEXT SIX MONTHS (TYPE, DATE AND DURATION):
None
- 25. IF UNIT IS SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF START-UP:
May 2, 1988 Note: Line 21 "Cumulative" factor no longer uses a weighted average.
i l
IMIT 9ETI11tRfMS A!Eit 11RGR RilitILTitWIS fuKET III). 50-318 IJIIIT IIAPE Calvert Cliffs - U2
~
IIATE. May 11, 1983 OWW1F.TU) In C. Behnke RfJ4 INT PEMfDI April 1988 TEff.81EJIE (301)260-4871 m
ts.5 o
w
=
c-es:
,3g 1.iren ev-g y
C;ui.e
& Can tw:f,ive o{
g ul Act i,wi t o o
5us I:u nt.
11.ie c 5.,.
es es
.c a cr:
hy
]
Ne 'I N *t ~t. M U
l*f 4 Ve sit ReTtit 11*f wM*
6
- a. m s u
0 88-06 880401 S
18.4 B
N/A N/A N/A N/A Continued shutdown for pre-suruner general maintenance mini-outage.
88-07 880427 F
87.2 A
2 88-04 HB PUMPXX Trip on low Steam Generator water level because 21 SCFP trioped for no apparent reason. There were no prior (or subsequent) rymptoms.
- 1. Monitor trip circuitry to find l
root cause.
- 2. Evaluate possible replacement of installed Thrust Bearing wear monitor.
L I
M-tlwaal:
I:sliilait Criamt riertiewis l':
how evj Reaw ns:
A-14rsi wiu nt tailanv- (Ihplaist) 1 -Kuntal fan-Pav lura *.iews of Dat a 8: Selwshale 1 l
ll-Hiint e nauw c an 1 cst, 2-Munnal Ser.in.
I' sit ry Flp et.S fut-I,ieratse C-Re fow l isin 3-Asit
- wa it ic Sce=-
1* nt Reiirt,(IJx) rite U-Regislatin y Re si rict.iews 4-(M ice (thplain)
(NtWI G-0161 )
I',-tgn r at os 1 raining & l.is ete INaminat 14wn l',%Iminist rat.ive 5 INiillait l' ~ S.w Sennre G-tgw rat s.,wial l'.rtue ( thpla. int II-(Mlw r- (I:splain)
AVERAGE DAILY UNIT POWER LEVEL Docket No. 50-318 Calvert Cliffs Unit No. 2 May 12, 1988 Completed by C.
Behnke Telephone: (301) 260-4871 MAY 1988 Trage Daily Power Level Average Daily Power Level (MWe-Net)
Day (MWe-Net) 67 17 874 a
791 18 877 3
820 19 880 4
871 20 879 5
874 21 879 6
872 22 878 7
870 23 878 8
868 24 879 9
866 25 877 10 868 26 876 11 870 27 321 12 868 28 0
13 871 29 0
14 872 30 0
15 873 16 874
Summary of U-2 Operating Experience April 1988 Date Time Event Descriotion 4/1 0000 Unit began shutdown in th'a Pre-Summer General Maintenance Outage (day #35 of 35).
The original 23 day schedule was extenced (primari-ly) due to 2-FW-130/133 replacements and FWH 25A/B associated repairs / velds /RTs (radio-graphs).
4/1 1821 Paralleled unit to grid, began power ramp-up.
4/2 0200 Held at 85% for STP-M-213; at 0845 held power to investigage #4 bearing on the Main Turbine.
By 1020, began ramp up to 100%.
4/3 1455 Reduced power to clean waterboxes, returned to full power at 2020.
4/27 0850 Unit manually tripped when S/G levels decreased
- lost #21 SGFP.
4/30 2400 Unit renained shutdown for repairs to #22 S/G Main Steam hanger.
Summary of U-2 Operating Experience April 1988 The Unit began this reporting period shut down.
On April 1 at 1821, paralleled Unit to grid; began power ramp-up.
Held at 85% power (0200, 4/2/88) for STP testing, STP-M-213; at 0845, while investigating #4 Main Turbine bearing temperature; @
1020 began ramp-up.
At 1455, (4-3-88) reduced power to clean waterboxes (returned at 2020).
At 0850 on April 27th, Unit was manually tripped when S/G levels decreased too low (due to loss of #21 SGFP).
Stayed shutdown until May 2.
i i
, _ ~,, _ _ _ _ _ _ _ _ _
4 l
May 5, 1988 REFUELING INFORMATION REOUEST 1.
Name of facility: Calvert Cliffs Nuclear Power Plant, Unit No. 2.
2.
Scheduled date for next refueling shutdown: April 1, 1989 3.
Scheduled date for restart following refueling: May 15, 1989 4.
Will refueling or resumption of operation thereaf ter require a Technical Specification change or other license amendment?
Resumption of operation after refueling will require changes to Technical Specifications. The changes will be such as to allow operation of the plant with a fresh reload batch and reshuffled core.
5.
Scheduled date(s) for submitting proposed licensing action and supporting information.
February 9, 1989 6.
Important licensing considerations associated with the refueling.
Reload fuel will be similar to that reload fuel inserted into the previous cycle.
7.
The number of fuel assemblies (a) in the core and (b) in the spent fuel storage pool.
(a) 217 (b) 1235 Spent fuel pools are common to Units 1 and 2.
8.
(a) The present licensed spent fuel pool storage capacity, and (b) the size of any increase in licensed storage capacity that has been requested or is planned, in number of fuel assemblies.
(a) 1830 (b) 0 9.
The proj ected date of the last refueling that can be discharged to the Spent Fuel Pool assuming the. present licensed capacity and maintaining space for one full core offload.
April, 1991
BALTIM O RE GAS AND ELECTRIC CHARLES CENTER.R O. BOX 1475 BALTIMORE, MARYLAND 21203 JAMES R. LEMONS MANAGER NUCLE AR OPERATK)P4s OEPARTMENi Document Control Desk U.S.
Nuclear Regulatory Commission 1 White Flint North Floor P1-Room 37 11555 Rockville Pike Rockville, MD 20850 ATTENTION:
Document Control Desk SUIkTECT:
April Operating Data Reports for Calvert Cliffs Units 1 and 2 (Dockets 50-317 and 50-318)
Gentlemen:
The subject reports are being sent to you as required by Technical Specification 6.9.1.6.
If there are any questions, please contact Carl Behnke, (301) 260-4871.
Sincerely, f.
R.
'twsv J
Lemons Manager-Nuclear Operations Department JRL/CB/j af Enclosures cc:
W. T. Russell (NRC)
S. A. McNeil (NRC)
D. Trimble (NRC)
P. Ross (NRC)
T. Magette (DNR)
D. Reilly (INPO)
K. Gibbard (DOE)
K. Gromack (CE)
Y' qi l
l s