Supplemental Deficiency Rept CP-85-39 Re Equipment Conduit Interface.Initially Reported on 880111.Completion of Unit 1 Repair/Rework of Affected Cabinets & Correction of Equipment Qualification Documents Rescheduled to 881109
ML20154C283
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 05/13/1988
From: Counsil W, Woodlan D
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
CP-85-39, TXX-88447, NUDOCS 8805180105
Download: ML20154C283 (1)


Text

=.

h' mmwaw.mid E

Lo

  1. TXX-88447

.=

Fi e # 10110 2

903.10

~-

i 7UELECTRIC Ref. # 10CFR50.55(e)

May 13, 1988 William G. Counsil berwn kwr heuJens U. S. Nuclear Regulatory Commission Attn:

Document Control Desk Washington, D.C.

20555 l

2

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)

DOCKET N05. 50-445 AND 50-446 EQUIPMENT CONDUIT INTERFACE SDAR:

CP-85-39 (SUPPLEMENTAL REPORT)

Gentlemen:

On January 11, 1988, we notified you via our report logged TXX-88035 of a reportable deficiency involving conduit which was not installed in accordance with design documents. Our subsequent supplemental report logged TXX-88270, dated March 1,1988, provided estimated completion dates for the corrective l

actions remaining to be implemented.

The purpose of this supplemental report

'i is to revise the scheduled completion date for Unit I corrective actions previously reported in TXX-88270.

1 Completion of the Unit I repair / rework of the affected cabit:ets and correction of the equipment qualification documents has been rescheduled.

The new estimated completion date is November 9, 1988.

Very truly y<1urs,

(.d. Co h W. G. Counsil l

By:

D. R. Woodlan Docket Licensing Manager RSB/grr c-Mr. R. D. Martin, Region IV Resident inspectors, CPSES (3) i 8805180105 880513

~