,9 MAY 0 0 M38 MEMORANDUM FOR:
Thomas E. Murley, Dire-+rr, Office of Nucleer Reactor Regelation (NRP.)
James M. Taylor, Deputy Executive Director for Regional Operations Jarres Lieberman, Director, Office of Enforcement FROM:
J. Nelson Grace, Regional Administrator
SUBJECT:
ENFORCEMENT DISCRETION FOR HATCH NUCLEAR PLANT - UNIT 2 -
DOCKET N0. 50-366 This is to document that on April 15, 1988, Georgia Power Company (GPC) was verbally granted a one-time relief to Technical Specification 3.6.6.2.a which provides a limiting condition for operation (LC0) for the primary containment recombiner systems.
The relief allowed a one-time, 72-hour extension of the 30-day LC0 for operation with one recombiner system inoperable.
The relief was granted to permit operation of Unit 2 with one recombiner system inoperable for an additional 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> in order to complete the weld examination, pressure test, and system functional test after a repair to the system which involved cutting and welding of the suction pipe. The system was declared operable at 1:35 a.m. (EST) on April 17, 1988.
The licensee's letter dated April 18, 1988, was reviewed to ensure that the NRC and the licensee were in agreement regarding the extent of the enforcement discretion.
In addition to the justifications for operation in this condition presented in the licensee's letter, the remaining unit was operable; the initial functional testing indicated that the affected unit would indeed perform its function; and the welds in question had been dye penetrant tested.
Prior to relief being granted, the technical issues and extent of enforcement discretion were discussed with:
G. C. Lainas and L. P. Crocker of NRR; J. Nelson Grace, M. L. Ernst, L. A. Reyes, A. F. Gibson, Y. L. Brownlee, M. B. Shymlock, M. V. Sinkule D. C. Payne, C. A. Patterson, P. Holmes-Ray, and J. Menning of RII; and S. Tipps and J. Heidt of GPC.
W. Troskoski of E00 was also informed, i
i For information regarding this matter, please contact M. V. Sinkule of ry staff at extension 5506.
s Jf J.' Nelson Grace
Enclosures:
(See page 2)
M 8805170002 880002
\\
PDR ADOCK0500gg6 g
l Multiple Addressees 2
MAY 0 2 resa
Enclosures:
1.
NRC to GPC Letter dated April 26, 1988 2.
GPC to NRC Letter dated April 18, 1988 cc w/encis:
L. A. Reyes A. F. Gibson G. R. Jenkins M. V. Sinkule P. Holmes-Ray W. Troskoski, E00 D. Mathews, NRR L. P. Crocker, NRR S. A. Varga, NRR bec w/encis:
NRC Resident Inspector DRS Technical Assistant Hugh S. Jordan Executive Secretary Document Control Desk State of Georgia Ril Ril RII RII /
Pil {lI RI RII
/
QLk h
LRey( s'k IDi
'q W
LTrocine MSinkole VBrownlee AGibson GJen ins J frnst 4/,tt/88 4/ /88 t/g /88 4/M /88 4@8E 4/2 88' A f 1 BT
~
syyr r
ENCLOSURE 1 1
- [.. P et og#'o, UNif ED $f ATES j
NUCLEAR REGULATORY COMMISSION f.\\
'n REGION il I
5 y
101 M A2tETTA STREET, N W.
't ATLANTA. GEORGI A 303M
'S, APR 2 6 USB Docket No. 50-366 License No. NPF-5 Georgia Power Company ATTN: Mr. George F. Head Senior Vice President-Nuclear Operations P. O. Box 4545 Atlanta, GA 30302 Gentlemen:
SUBJECT:
CONFIRMATION OF ENFORCEMENT DISCRETION REGARDING TECHNICAL SPECIFICATION 3.6.6.2.a - HATCH - UNIT 2 This letter acknowledges receipt of your letter dated April 18, 1988, regarding your request for relief of Hatch Unit 2 Technical Specification 3.6.6.2.a on a one time basis.
This requirement provides a limiting condition for operation (LCO) for the primary containment recombiner systems, and the waiver requested
~
allowed for a one time 72-hour extension of the 30-day LCO for operation with one recombiner system inoperable.
This waiver was requested and subsequently granted via telecon on April 15, 1988.
The NRC has reviewed your April 18, 1988, letter documenting this issue and confirms that enforcement discretion i
was granted to permit operation of Unit 2 with one recombiner system inoperable for an additional 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> in order to complete the weld examination, pressure test, and system functional test after a repair to the system which involved cutting and welding of the suction pipe.
In addition to the justifications for operation i'n this condition presen'ted in your April 18, 1988, letter; the remaining unit was operable, the initial functional testing indicated that the affected unit would indeed perfortn its function, and the welds had been dye penetrant tested.
The system was declared operable at 1:35 a.m. (EST) on April 17, 1988.
Should you have any further questions regarding this letter, please contact this office.
Sincerely, l-
~
C' J. Nelson Grace Regional Administrator cc:
(See page 2)
&L!
,,,, -+,
Georgia Power Company 2
APR 20 %
cc:
J. T. Beckham, Vice President, Plant Hatch fl. C. Nix, Plant Manager
- 0. M. Fraser, Site Quality Assurance (QA) Supervisor L. Gucwa, Manager, Nuclear Safety and Licensing O
0 D
L
],,...,,,,,..,m-cm
- g_gepp ti4ctosuat 2
@?:Mie Y$$5%
Georgia Power t, t w vsg;egee se,v
,,w w a,v.-
SL-4563c 2014C X7GJ10-N000 April 18, 1988 U. S. Nuclear Regulatory Con;nission Regional Administrator - Region II Suite 2900 101 Harietta Street, N. W.
Atlanta. Georgia 30323 Attn: Dr. J. Nelson Grace PLANT HATCH - UNIT L NRC DOCKET 50-366 OPERATING LICENSE NPR-5 IECHNICAL $PECIFICATIONA Gentlemen:
Technical Speciftention (TS) requirements.This letter constitut Specifictil requirements (on a one time basis) was requested, y, relief from TS and subsequently granted via telecen between Georgia Power Company (GPC) personnel, esmbers,of your staff, and members of the NRR staff on April The waiver applied to Plant Hatch Unit 2 TS 3.6.6.2.a which provides a 15, 1988.
Limiting condition for Operation (1.C0) for the primary containment recombiner systems.
Specifically the waiver allowed for a one time extension of the 30 day LCO for, operation with one recombiner system inoperable.
The extension granted was for 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> (3 day:)
expiration of the 30 day LCO.
after the at about 2:00 COT.
The 30 day LCO expired on April 15 1988 cutting and welding of the suction piping.The repair to the recombine v
the understanding that Region II personnel vould be immediately notifie if problems were encountered during the weld examination and pressure testing or during the system functional test.
No problems were encountered, however, and the syste'n is functioning properly as of April 18, 1988.
The three day extension of the LC0 had am insignificant irtpact on plant safety.
Plant Hatch Unit 2 was origintily licensed eith a non-inerted containment which used primary hydrogen recombiners as primary reins the of LOCA ccmbustible gas control.
In 1982 the Unit 2 containment was inerted as required by 10 CFR 50.44 (C)(3(1).
The i
l(
') U
g, i,... tsitz eer oc wuc c'5 h"
^
' Enclosure 2 GeorglaPower d U. S. Nuc1Hr Regulatory Comission April 18, 1988 Page Two i
the hydrogen recombiner systems are notreference report pro i
plants with inerted containments.
necessary for safety in SHR for Unit 2 is justified. Based on reference 1, it is concluded that the 3 d If you have any questions in this regard, please contact this office at any time.
i Sincerely, p A. -
L. T. Gutwa GKN/lc
Reference:
1.
Nt00-22155, "Generation and Hitigation of. Combustible Gas Mixtures in Inerted BWR Hark I Containments", June 1982.
i t
c: caercia Power Conany Mr. 3. T. Beckham, Jr., Vice President - Plant Hatch GO-NORMS (L Nuelaar Ragy1Liery Comittion. Wathincton, D.
C._
Hr. L. P. Crocker, Licensing Project Manager - Hatch Document Control Desk U. S. Nuclear Regg1Ltory CoS91stion. Racion II Hr. P. Holmes-Ray Senior Resident Inspector - Hatch i
2014C
,. _ _