MEMORANDUM TO:
Samuel J. Collins, Director Offica of Nuclear Reactor Regulation Originalsignedby FROM:
Thomas T. Martin, Chairman ThomasT. Martin Committee To Review Generic Requirements
SUBJECT:
CRGR REVIEW OF THE YEAR-2000 AUDIT PLANS As you are aware, CRGR review of the Year-2000 (Y2K) Audit Plans was scheduled in early September before the Y2K audits were to begin on September 14,1998. However, this review was cancelled at the request of NRR managers and with their assurance that: (1) these are audits and not inspections, (2) thece is no associated enforcement provision, and (3) no new requirements are being imposed; hence, there is no backfitting. The Committee, however, expects that should there be future staff proposals to impose new requirements, revise existing position (s), or establish new Y2K compliance criteria, they, and the associated inspection guidance, will be submitted for CRGR consideration, cc:
F. J. Miraglia, NRR M. R. Knapp, NMSS J. A. Murphy, RES D. C. Dambly, OGC J. E. Dyer, R-IV CONTACT:
Raji Tripathi, xEOD 415-7584 l
Distribution:
PDR bJRClCP6R)
'g CRGR SF CRGR CF JMitchell b t. hk] {3 E
T avers i
RLSpessard JWermiel MChiramal DISK / DOCUMENT NAME: S:\\CRGR\\Y2KADTS.WPD
- see previous concurrence To receive a copy of this document, indicate in the box: 'C' = Copy w/o attachment, 'E' = Copy w/ attachment, "N" = No copy OFC CRGR C
C:CRV NAME RTripath!
TT rfin DATE 09/28/9 7
, [ / 29 /98 OFFICIAL RECORD COPY
" ' [: 3
[/h 9810020413 980929 C[6/'2 PDR REVQP NROCROR CORRESPONDENCE PDR
/ C fr N-2. 'f YFv /12 VD C
MEMORANDUM TO:
Samuel J. Collins, Director Office of Nuclear Reactor Regulation FROM:
Thomas T. Martin, Chairman Committee To Review Generic Requirem ts
SUBJECT:
CRGR REVIEW OF THE YEAR-2000 A D P NSf" As you are aware, CRGR review of the Year-2000 (Y2 Audit Plans was scheduled in early September before the Y2K audits were to begin on S tember 14,1998. However, this review was deferred at the request of NRR managers d with their assurance that: (1) these are audits and not inspections, (2) there is no asso, lated enforcement provision, and (3) no new requirements are being imposed; hence, ere is no be.ck!itting. The Committee, however, l
expects that shou'd there be future staff p posals to impose new requirements, revise existing position (s), or establish new Y2K com sance criteria, they, and the associated inspection guioance, will be submitted for C R consideration.
cc:
F. J. Miraglia, NRR M. R. Knapp, NMS J. A. Murphy, RE i
D. C. Dambly, GC J. E. Dyer, R-CONTACT:
R iTripithi, AEOD 5-7584 i
Distribution:
CRGR SF CRGR CF JMitchell RTripathi WTravers RLSpessard JWermiel MChiramal DISK / DOCUMENT NAMJ: S:\\CRGR\\Y2KADTS.WPD To receive a copy of this document, indicate in the box: "C" = Cepy w/o attachment, "E' = Copy w/ attachment, "N' = No copy OFC CRGR C:CRGR NAME RTripathi TTMartin f.TE 7 /Af /98
/
/98 OFFICIAL RECORD COPY
e
- 4 ""%
f 4
UNITED STATES g
j NUCLEAR REGULATORY COMMISSION o
WASHINGTON, D.C. 20656-0001 s
September 29, 1998 MEMORANDUM TO:
Samuel J. Collins, Director Office of Nuclear Reactor Regulation FROM:
Thomas T. Martin, Chairman M
Committee To Review Generic Requirements
SUBJECT:
CRGR REVIEW OF THE YEAR-2000 AUDIT PLANS As you are aware, CRGR review of the Year-2000 (Y2K) Audit Plans was scheduled in early September before the Y2K audits were to begin on September 14,1998. However, this review was cancelled at the request of NRR managers and with their assurance that: (1) these are audits and not inspections, (2) there is no associated enforcement provision, and (3) no new requirements are being imposed; hence, there is no backfitting. The Committee, however, expects that shodd there be future staff proposals to impose new requirements, revise existing position (s), or establish new Y2K compliance criteria, they, and the associated inspection guidance, will be submitted for CRGR consideration.
cc:
F. J. Miraglia, NRR M. R. Knapp, NMSS J. A. Murphy, RES D. C. Dambly, OGC J. E. Dyer, R-IV CONTACT:
RajiTripathi, AEOD 415-7584