ML20154A346

From kanterella
Jump to navigation Jump to search
Forwards Insp Repts 50-352/98-07 & 50-353/98-07 on 980707-0831.No Violations Noted.Weaknesses Noted with Reactor Engineering Support to Rod Pattern Adjustment
ML20154A346
Person / Time
Site: Limerick  Constellation icon.png
Issue date: 09/25/1998
From: Anderson C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Rainey G
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
Shared Package
ML20154A350 List:
References
50-352-98-07, 50-352-98-7, 50-353-98-07, 50-353-98-7, NUDOCS 9810020281
Download: ML20154A346 (3)


See also: IR 05000352/1998007

Text

-. . . . . . - . - - - - - - . , _ _ . - - . - - .---- - -- ~- -

.. - +

'

September 25, 1998

Mr. G. Rainey, President

PECO Nuclear

Nuclear Group Headquarters i

Correspondence Control Desk

P. O. Box 195

Wayne, PA 19087-0195

SUBJECT: NRC INTEGRATED INSPECTION REPORT 50-352/98-07,50-353/98-07

Dear Mr. Rainey:

This refers to the inspection conducted on July 7,1998, through August 31,1998, at

your Limerick Units 1 and 2 reactor facilities. The enclosed report presents the results of

this inspection.

During the 8-week inspection period covered by this report, the conduct of activities at

Limerick Units 1 and 2 was generally characterized by safe and conservative operations

and decision making. Your operators responded very well to unexpected plant conditions

on three separate occasions. However, weaknesses were noted with reactor engineering

support to a rod pattern adjustment.

In accordance with 10 CFR 2.790 of the NRC's " Rules of Practice," a copy of this letter,

'its enclosure (s), and your response will be placed in the NRC Public Document Room

. (PDR).

.

Sincerely, j

Original Signed by: )

f

Clifford J. Anderson, Chief

Project Branch 4

Division of. Reactor Projects

Docket Nos.: 50-352,50 353

License Nos: NPF-39, NPF-85

,

'

Enclosure: NRC Inspection Report 50 352/98-07,50-353/98-07

.

9810020281 980925

PDR ADOCK 05000352

G PM ,

0FFICIAL RECORD COPY IE:01

. -

. _

_

_ _. . _ _ . . _ . _ . _ _ _ . _ _ . _ - _ _ . _ . .

.

_ - . .m_ _ _

.

G. Rainey 2

cc w/ encl:

J. J. Hagan, Vice President, Nuclear Stat;on Support

G. Edwards, Chairman, Nuclear Review Board and Director - Licensing

J. von Suskil, Vice President - Limerick Generating Station

M. P. Gallagher, Plant Manager, Limerick Generating Station

T. Moore, Manager, Experience Assessment

Secretary, Nuclear Committee of the Board

~ Commonwealth of Pennsylvania

,

b

4

4

+

'

l

-

. . . . . . . - . ~ .- .

.- - _ _ -- - - . - - .. .

. ,

.

4

l

G. Rainey

-

3

Distribution w/ encl:

Region i Docket Room (with concurrencer.) )

H. Miller, RA/W. Axelson, DRA (1)

C. Anderson, DRP

i

D. ':lorek, DRP

i

R.Junod,DRP

NRC Resident inspector

Nuclear Safety Information Center (NSIC)

PUBLIC

{

l

! . Distribution w/ encl: (Via E-Mail) I

B. McCabe, OEDO l

R. Capra, PDI-2, NRR

4 Inspection Program Branch, NRR (IPAS)

B. Buckley, PD 1-2, NRR

M. Thadani, PD 1-2, NRR l

R. Correia, NRR I

F. Talbot, NRR I

M. Campion, ORA

DOCDESK

l

'

!

,

I

.i '

DOCUMENT NAME: G:\ BRANCH 4\ LIM \ LIM 9807A.lNS

/ To receive a copy of this document, indicate in the box: "C" = Copy without

attachment /encips f "E" = Copy wPh attachment / enclosure "N" = No copy

OFFICE Rl/D@ff ' Rl/DRP ,

NAME DFigffk j CAnderson (jd

'

DATE 09[$298 09/ggf/98

OFFICIAL RECORD CO')Y