ML20154A282

From kanterella
Jump to navigation Jump to search
Forwards Insp Repts 50-373/98-19 & 50-374/98-19 on 980716-0831.Notice of Violations Not Being Issued for Listed Violations,Due to Minor Safety Significance or Either Staff Took Appropriate Corrective Actions of Identified Issues
ML20154A282
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 09/24/1998
From: Grant G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Kingsley O
COMMONWEALTH EDISON CO.
Shared Package
ML20154A284 List:
References
50-373-98-19, 50-374-98-19, NUDOCS 9810020257
Download: ML20154A282 (3)


See also: IR 05000373/1998019

Text

. - _ . - ~ . .-.-

-. .... - - - .--.

.. - . - . - - .

- - -.

l

-

.

.

!/

UNITED STATES

j

ptpah

NUCLEAR REGULATORY COMMISSION

og

i

g

REGION lli

.-

{

g

801 WARRENVILLE ROAD

i

e

LISLE. ILLINOIS 60532-4351

k.,,g /

i

September 24, 1998

.

i

Mr. Oiiver D. Kingsley

l

President, Nuclear Generation Group

i

Commonwealth Edison Company

ATTN: Regulatory Services

Executive Towers West ill

1400 Opus Place, Suite 500

.

Downers Grove,IL 60515

SUBJECT:

LASALLE INSPECTION REPORT 50-373/98019(DRP); 50-374/98019(DRP)

<

i

Dear Mr. Kingsley:

,

'

j

This refers to the inspection conducted July 17 through August 31,1998, at the

j

. LaSalle Nuclear Power Station. The purpose of the inspection was to determine whether

j

activities authorized by the license were conducted safely and in accordance with NRC

i

requirements. In addition to routine resident inspection during this period, regional inspection

!

staff also assisted in conducting extensive observations of startup activities fotbwing the Unit 1

extended outage. At the conclusion of the inspection, the findings were discussed with those

,

7

members of your staff identified in the enclosed report.

'

. Overall, performance of plant personnel was acceptable during the Unit i startup. In

3

particular, operators performed well while effectively controlling plant activities, conducting

j

briefings, communicating with other personnel and each other, maintaining a questioning

attitude, and responding to equipment problems. Some violations of NRC requirements and

]

other instances of human p erformance deficiencies were identified which indicates a need to

continue your current focus in this area at LaSalle. For example, a failure of operators to

!

follow procedure resulted in inadvertent start of an emergency diesel generator, and an

!

engineer prov!ded an incorrect core flow value resulting in establishment of non-conservative

j

flow-biased power range scram and rod block setpoints. A Notice of Violation is not being

[

issued for these violations because they were either of minor safety significance or your staff

identified these issues and took appropriate corrective actions.

.

i

i

During the Unit 1 startup, several equipment pratalems challunged plant personnel. In each

/

!

instance, your staff took appropriate, conservative actions, inc!uding shutting down the plant

'

,

on two occasions, to resolve the problems. One of these shutdowns involved operators

]

manually scramming the plant in response to a feedwater transient caused by a flow controller

~

card failure. The other shutdown was a pre-planned evolution to address intermediate range

,

monitor failures, failures during testing of the reactor core isolation cooling pump mechanical

'

overspeed trip function, and flow control valve control circuitry noise problems in the reactor

i

recirculation system. None of these equipment problems directly impacted safe operation of

the facility. We also continue to recognize the extensive actions taken during the extended

4

i

outage to address the more significant equipment problems at LaSalle. However, these

!

equipment failures during startup do re emphasize the need to maintain a focus on resolving

Unit i equipment problems.

'

v

9810020257 990924

PDR

ADOCK 05000373

/

G

PDR

i

- _ _

-

,_

._

__

., _

_

.

.

.

.

O. Kingsley

-2-

,

In accordance with 10 CFR 2.790 of the NRC's " Rules of Practice," a copy of this letter and its

enclosure will be placed in the NRC Public Document Room.

Sincerely,

Original signed by

Geoffrey E. Grant, Director

Division of Reactor Projects

Docket Nos.: 50-373;50-374

License Nos.: NPF-11; NPF-18

Enclosure:

Inspection Report 50-373/98019(DRP);

50-374/98019(DRP)

cc w/ encl:

M. Wallace, Senior Vice President

D. Helwig, Senior Vice President

G. Stanley, PWR Vice President

J. Perry, BWR Vice President

D. Farrar, Regulatory Services Manager

1. Johnson, Licensing Director

DCD - Licensing

F. Dacimo, Site Vice President

T. O'Connor, Station Manager

P. Bames, Regulatory Assurance Supervisor

R. Hubbard

N. Schloss, Economist

Office of the Attomey General

State Liaison Officer

Chairman, Illinois Commerce Commission

DOCUMENT NAME: G:\\LASA\\LAS98019.DRP

To reimive e copy of this document. Indicate in the box "C" = Cnow without attachm int / enclosure "E" = Copy with attachment / enclosure "N" = No copy

OFFICE

Rlll

- lF Rill

C

Rill

Rlli

l

_

NAME

Hills:mi pe-d

Shear 666

LanksburyGD%

Grant 4EQ/

DATE

09At/98

09/12/98

09p.5/98

09/bf9()[]

OFFICIAL RECORD COPY

..- -

,-

-

-

--

,,

. ..______

-

_ _ . - . _ _ _ _ _ _ _ _ . . . <

_ _.. ..__._ - . - _ . _

_

- . . _ . _

__

-

,

.

A.

O. Kingsley

-3-

l

l

Distribution:

,

'

SAR (E-Mail)

Project Mgr., NRR w/enci

~J. Caldwell, Rlll w/enci

C. Pederson, Rill w/ encl

B. Clayton, Rlli w/enct

SRI LaSalle w/end

DRP w/end

TSS w/enci

DRS (2) w/end

Rlli PRR w/end

j

PUBLIC IE-01 w/end

Docket File w/enci

~ GREENS

LEO (E-Mail)

DOCDESK (E-Mail)

!

l

,

1

1

3C0035

l