ML20153H036

From kanterella
Jump to navigation Jump to search
Forwards Emergency Plan Evaluation Rept,Reed Reactor Facility, Accepting Emergency Plan.Full Implementation Should Be Accomplished within 120 Days of Ltr Date.Date When Full Implementation Achieved Requested
ML20153H036
Person / Time
Site: Reed College
Issue date: 02/20/1986
From: Berkow H
Office of Nuclear Reactor Regulation
To: Kay M
REED COLLEGE, PORTLAND, OR
Shared Package
ML20153H040 List:
References
NUDOCS 8602280581
Download: ML20153H036 (3)


Text

'

. February 20, 1986 Docket No. 50-288 Dr. M. A. Kay. Director Reactor Facility Reed College 3203 S. E. Woodstock Boulevard Portland, Oregon 97202 ,

Dear Dr. Kay:

SUBJECT:

EMERGENCY PLAN ACCEPTANCE The staff of the U. S. Nuclear Regulatory Commission (NRC) has completed its review and evaluation of the revised emergency plan for the Reed Reactor Facility dated September 15, 1985 with revisions submitted on December 18, 1985 and January 14, 1986, in compliance with 10 CFR 50.54(q) and (r). The plan was reviewed against the requirements of Appendix E to 10 CFR Part 50, the guidance criteria set forth in Revision 1 to Regulatory Guide 2.6 and ANSI /ANS-15.16-1982, " Emergency Planning for Research Reactors."

Based on its review, and as discussed in the enclosed evaluation, the staff concludes that the emergency plan for the Reed Reactor Facility meets both the requirements of the regulations and the guidelines provided to you and is, therefore, acceptable. We request that you begin to implement your approved emergency plan immediately, with full implementation to be accomplished within 120 days of the date of this letter. Furthermore, you are requested to inform us by letter of the date on which complete implementatic is achieved.

If you have any questions, please contact John Dosa, our Project Manager for your facility, at (301) 492-8207.

Sincerely, Original signed by Herbert N. Berkow, Director Standardization and Special Projects Directorate Division of PWR Licensing-8, NRR

Enclosure:

DISTRIBUTION:

As stated -Docket File "NSIC

, DMatthews SSPD~Readinf JDosa FKantor NRC PDR PNoonan RHogan cc w/ enclosure: Local PDR DTondi See next page DCS HBerkow DPW [SSPD D ^ ',l B_:SSPD DPWRL-B:SSPD DPW %.JSPD

ac PMo an DTondi W HBe w 0/y/86 02/1 /86 02/q/86 02/ 86 8602280581 860220 hDR ADOCK 05000288 PDR

/' o,, UNITED STATES E g NUCLEAR REGULATORY COMMISSION l

[ :y WASHINGTON, D. C. 20555

% ,, # February 20, 1986

.l Docket No. 50-288 Dr. M. A. Kay, Director Reactor Facility Reed College 3203 S. E. Woodstock Boulevard f ortland, Oregon 9720f.

Dear Dr. Kay:

SUBJECT:

EMERGENCY PLAN ACCEPTANCE The staff of the U. S. Nuclear Regulatory Commission (NRC) has completed its review and evaluation of the revised emergency plan for the Reed Reactor Facility dated September 15, 1985 with revisions submitted on December 18, 1985 and January 14, 1986, in compliance with 10 CFR 50.54(q) and (r). The plan was reviewed against the requirements of Appendix E to 10 CFR Part 50, the guidance criteria set forth in Revision I to Regulatory Guide 2.6 and ANSI /ANS-15.16-1982, " Emergency Planning for Research Reactors."

Based on its review, and as discussed in the enclosed evaluation, the staff concludes that the emergency plan for the Reed Reactor Facility

~

meets both the requirements of the regulations and the guidelines provided to you and is, therefore, acceptable. We request that you begin to implement your approved emergency plan innediately, with full implementation to be accomplished within 120 days of the date of this letter. Furthermore, you are requested to inform us by letter of the date on which complete implementation is achieved.

4 -

If you have any questions, please contact John Dosa, our Project Manager  ;

for your facility, at (301) 492-8207. '

i Sincarely, by .(

Herbert N. Berkow, Director Standardization and Special Projects Directorate Division of PWR Licensing-8, NRR

Enclosure:

As stated

cc w/ enclosure:

See next page

O Reed College Docket No. 50-288 cc: Director, Oregon Department Of Energy 528 Cottage Street, N. E.

Salem, Oregon 97310 Mayor of City of Portland 1220 Southwest 5th Avenue 4 Portland, Oregon 97204 l Administrator Siting and Regulation 1 Oregon Department of Energy  !

Labor and Industries Building Room 111 Salem, Oregon 97310 l

Attorney General '

Department of Justice State Office Building Salem, Oregon 97130 l

l

_ - _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - . _ _ _ _ _ _ _ _ _ .-. _ _ _ _ - _ - _ _ - _ _ _ _ _ _ _ _ _ _ _ _ . _ - - - - _