Forwards Semiannual Effluent Releases Rept 25,Jan-June 1988 & Rev 2 to Offsite Dose Calculation Manual
ML20153G046
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 08/29/1988
From: Alden W
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
To: Russell W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
Shared Package
ML20153G049 List:
References
NUDOCS 8809080022
Download: ML20153G046 (1)


Text

-

~

10 CPR 50.36a(a)(2)

T.S. 6.9.2.h(2) 1 PHILADELPHIA ELECTRIC COMPANY 2301 M ARKET STREET P.O. DOX 8399 PHILADELPHI A. PA.19101 (2151541 4000 August 29, 1988 DocP.et No. 50-277 50-278 Mr. William T.

Russell, Administrator Region I U.S. Nuclear Regulatory Commission ATTN:

Document Control Desk Washington, D.C.

20555

SUBJECT:

Semi-Annual Effluent Releases Report No. 25 January 1, 1988 through June 30, 1988 Peach Bottom Atomic Power Station Unit Nos. 2 and 3 Dear Mr. Russell Enclosed are two copies of the Semi-Annual Effluent Releases Report No. 25, January 1 through June 30, 1988 for Peach Bottom Atomic Power Station Unit Nos. 2 and 3.

This report is being submitted in compliance with 10 CPR 50.36ata)(2) and the Technical Specifications of Operating Licenses DPR-44 and DPR-56, and to fulfill the requirements of Regulatory Guide 10.1.

During the report period, revisions were made to the Offsite Dose Calculation Manual (ODCM).

are enclosed with this report.

Two copies of the ODCM, Revision 2, Very truly yours, k

}l, l W. M. Alden Director Licensing Section Enclosures cc:

Addressee T.

P. Johnson, PBAPS Site Inspector

{

2 830829 R { 0 g@CK 050oo277 g i PEC 1