Georg a Power Company 333 P,edmont Avtoue Ararta. Georgta 30308 Teechone 494 5266526 Ual>ng M3ress rest cit <e son 4sas A tanta, Georg a 30302 Ed((cNEh$rt

't"**'"" e* c'"c '>=

tww cwatons YL-52 0015e X7(k117-Y750 August 29, 1988 U. S. Nuclear Regulatory Commission ATTN: Document Control Oesk Washington, D. C.

20555 PLANT V0GTLE - UNIT 1 NRC DOCKET 50-424 OPERATING LICENSE NPF-68 FOURTH SUPPLEMENT TO

SUMMARY

REPORT OF STARTUP TEST PROGRAM Gentlemen:

Section 6.8.1.1 of the Yogtle Electric Generating Plant Unit 1 Technical Specifications requires Georgia Power Company (GPC) to submit a supplement to the stenary report of plant startup and power escalation testing every three months until completion of the test program.

The initial summary report was submitted on August 31, 1987 with supplemental reports submitted on November 30, 1987, February 29, 1988, and May 23,1988.

Enclosed is the fourth supplement to the sumary report.

This supplement addresses the remaining Startup tests that were incomplete as of our last submittal.

Should you have any questions in this regard, please contact this office at any time.

Sincerely.

MV '

ra W. G. Hairston !!!

JAE:llh Enclosure c: (see next page) f,$[hD0 P

I

a r

Georgia Power d U. S. Nuclear Regulatory Comission August 29, 1988 Page Two i

i c: Georgia Power Comparty Mr. P. D. Rice l

Mr. G. Bockhold, Jr.

GO-NORMS U. -S. Nuclear Regulatory Comission i

Dr. J. N. Grace, Regional Administrator Mr. J. B. Hopkins, Licensing Project Manager, NRR (2 copies) l Mr. J. F. Rogge, Senior Resident Inspector - Operations, Yogtle l

i l

l i

i i

0015e L

j ENCLOSURE PLANT YOGTLE - UNIT 1 NRC DOCKET 50-424 OPERATING LICENSE NPF-68 FOURTH SUPPLEMENT TO

SUMMARY

REPORT OF STARTUP TEST PROGRAM This fourth supplement to the initial startup report addresses the remaining startup tests that were incomplete at the time of submittal of the original startup report and three supplements.

These tests are identified according to the section numbering scheme used in the original report. The test number is provided in parentheses.

Please note that test 1-5RJ-01 has been erroneously omitted from prior reports.

7.6.6 Process and Effluent Radiation Monitoring System Test (1-650-01)

The Process.nd Effluent Radiation Monitoring System (PEW 4S) Test, FSAR Section 14.2.8.2.28, remains to be compl eted.

Testing of the four radiation monitors outstanding as of the last supplement to the startup report will be completed via a special test procedure.

Three of the monitors, ARE-2533A, ARE-25333, and ARE-2565A, will be tested following repair.

The fourth,1RE-0014, is functional but awaits a gaseous airborne release at full power in order for it to be tested.

The results from these tests will be discussed in a future supplemental report.

5.9 Proteus Computer Operational Test (1-5RJ-01) 1 Software problems with the graphics package prevented the successful completion of the graphics software test section of the Proteus Computer Oparational Test (FSAR Section 14.2.8.1.109) during the startup program.

The graphics software test will be performed during the first refueling outage under the provisions of a special test procedure.

0015e E-1 08/29/88 YL-52