Telephone (508) 568-2233 Facsimile (508)5684703 YANKEEATOMICELECTRIC COMPANY ~ ~~~

$ 580 Main M. set, Bolton. Massachusetts G1740-1398 YAFEEE m.

DON K. DAVIS September 23,1998 BYR 98-037 United States Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Attention: Mr. Morton B. Fairtile Senio Project Manager Non-Power Reactors and Decommissioning Project Directorate Division of Reactor Program Management Office of Nuclear Reactor Regulation

Reference:

(a) License No. DPR-3 (Docket No. 50-29)

Subject:

Yankee Nuclear Power Station Change of Personnel

Dear Mr. Fairtile:

As you are aware, most of the dismantlement and decontamination activities at YNPS have been completed in the areas that are not associated with fuel storage. The entire decommissioning task is estimated to be more than 80% complete. Final status surveys to ensure that YNPS meets the NRC's radiological release criteria are underway. The removal of the remaining systems and components and the decontamination of buildings not associated with fuel storage is currently scheduled to be finished in early 1999. In light of the progress made by Yankee, and as originally planned by Yankee as part ofits decommissioning cost estimate, the responsibilities of Site Manager / Manager of Operations and Decommissioning Manager have been consolidated.

Therefore, Mr. Donald A. Reid will replace Mr. Kenneth J. Heider (Site Manager / Manager of Operations) and Ms. Jane M . Grant (Decommissioning Manager). While the responsibilities have been consolidated, Mr. Reid will assume the titles of both positions.

Mr. Reid is a highly qualified nuclear executive whose experience includes being Vice President of Operations and Engineering at Vermont Yankee; most recently, Mr. Reid has been a management consultant for both YNPS and CYAPCO decommissioning efforts. As required by Section 6.3.1 of Appendix A of the YNPS Possession Only License (Reference (a)), Mr. Reid satisfies the qualifications specified in ANSI 18.1-1971 for the position which he is assuming. Mr. Reid's lo assignment is effective immediately.

b 30 9809250159 980923 PDR ADOCK 05000029 -

H PDR

. - , - ~. .. . . _ .

United States Nuclear Regulatory Commission September 23,1998 Attention: . Mr. Morton B. Fairtile Page 2 I am fully confident that Mr. Reid will provide the leadership necessary to assure that the decommissioning of YNPS will continue to be prformed safely and efficiently. Also, I will keep you informed of other changes in key personnel and the YNPS management structure as the decommissioning of YNPS progresses.

Very truly yours, YANKEE ATOMIC ELECTRIC COMPANY

\

N .)*  % w.wsh+

Don K. Davis, Chairman 4, pg,g,7p% , g

_ President and CEO l

cc: USNRC, Region I