Final Deficiency Rept CP-85-35 Re Cable Tray Hanger Design. Initially Reported on 861021.Design Vaildation Program for Cable Tray Hangers Based on as-built Conditions & Testing Program Confirming Design Validation Completed
ML20153D686
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 05/04/1988
From: Counsil W, Woodlan D
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
CP-85-35, TXX-88437, NUDOCS 8805090251
Download: ML20153D686 (2)


Text

'

.- 4

.E E~"

log # TXX-88437 C- - File # 10110 C

903.9 7UELECTRIC Ref. # 10CFR50.55(e)

D,$Sd%,$,,, May 4, 1988 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C. 20555

SUBJECT:

COMANCHE PEAV STEAM ELECTRIC STATION (CPSES)

DOCKET NOS. 50-445 AND 50-446 CABLE TRAY HANGER DESIGN SDAR: CP-85-35 (FINAL REPORT)

REF: SDAR: CP-83-15, "CABLE TRAY CLAMPS" Gentlemen:

On October 21, 1986, we notified you by our letter logged TXX-6048 of a deficiency involving cable tray hanger design which we deemed reportable under thn provisions of 10CFR50.55(e). Our latest report on this issue, logged TXX-88410, was submitted April 27, 1988. This report is submitted to update the corrective action completion schedule for this issue.

As indicated in TXX-6048, our corrective actions for this issue include a design validatior. program (which include the issue regarding inadequate bolting material and fastener tension for cable tray clamps - SDAR: CP-83-15) for cable tray hangers based on as-built conditions and a testing program to provide additional confirmation of the design validation methods.

The testing program has been completed.

With respect to the design validation program for Unit 1 and Common Area, -

as-dasigned drawings have been developed for each cable tray hanger. Field walkdowns have been performed (per FVM-CS-001/FVM-CS-003) to establish and indicate on the drawings, the hanger as-built conditions. Final as-built drawings were produced from information gathered from the walkdown effort.

Quality Control Verifications of the as-built drawings were performed in accordance with Ql-QP-11.10-9, which has been revised to N01-3.09-M-001, "Modification, Rework and As-Built Inspection / Verification of Cable Tray Hangers in Unit 1" and QI-QP-11.10-2A, "Inspection of Unit 2 Cable Tray Supports for Spread Room Attachments." Span layout sketches were developed, based on field walkdown data.

The total number of hangers identified as requiring modification as a result of the design validation is eight hundred seventy-four (874) out of a total of seven thousand five hundred sixty six (7566) hangers in Unit I and Common.

Design Change Authorizations (DCAs) have been issued for these modifications.

G805090251 880504 PDR S

ADOCK 05000445 o hnh ol,ve stree LB 81 Dallas. Texas M01 /y, 6' DCD l 6

l TXX-88437 May 4, 1988 Page 2 of 2 The Unit 1 corrective actions is currently scheduled for completion by August 1, 1988. Corrective actions for Unit 2 are currently scheduled for completion prior to Unit 2 fuel load.

Very truly yours, U.b W. G. Counsil By:-

D. R. Woodlan Docket Licensing Manager DAR/grr c-Mr. R. D. Martin, Region IV Resident Inspectors, CPSES (3)

.