Forwards Revised Commitments Re safety-related Sys Design Criteria.Delays in Restart of Unit 2 & Continued Use of Resources on Restart Effort Impeded Progress on Design Criteria Project
ML20153D559
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 05/04/1988
From: Gridley R
TENNESSEE VALLEY AUTHORITY
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
NUDOCS 8805090196
Download: ML20153D559 (3)


Text

,'

TENNESSEE VALLEY AUTHORITY CH ATTANOOG A, TENNESSEE 37401 5N 157B Lookout Place MAY 0 41988 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Hashington, D.C.

20555 Gentlemen:

In the Matter of

)

Docket Nos. 50-327 Tennessee Valley Authority

)

50-328 SEQUOYAH NUCLEAR PLANT (SQN) - REVISION TO POSTRESTART SCOPE AND SCHEDULE FOR DESIGN CONTROL SYSTEM

Reference:

TVA letter to NRC dated December 15, 1987 In the referenced letter, TVA revised the completion schedule for the safety-related system design criteria.

TVA had anticipated completing this work by March 31, 1988. All of the safety-related design criteria, except the radiation monitoring system, have been revised and are currently under final review by the engineering branches.

The bulk of the effort is complete.

The remaining work involves completion of the reviews, resolution of comments, and formal issuance.

This work will be completed by May 31, 1988.

The radiation monitoring system design criteria have not been issued yet; however, they will be completed by June 30, 1988.

The revised commitments are listed in the enclosure to this letter.

The previous schedule was established on the basis of an earlier restart of unit 2.

Delays in the restart of unit 2 and the continued use of resources on the restart effort have impeded progress on the design criteria project.

In addition, work on the radiation monitoring system design criteria has been constrained because of the limited availability of personnel with the specialized expertise required for the work and the budget constraints that have precluded contracting the work.

If you have any further questions, please telephone M. J. Burzynski at (615) 870-6172.

Very truly yours, TENNESSEE VALLEY AUTHORITY M-R. Gridley, Di ector Nuclear Licensing and Regulatory Affairs Enclosure 9

cc:

See page 2

\\ \\

(

8805090196 880504 PDR ADOCK 05000327 An Equal Opportumty Employer f3 DCD

_ s U.S. Nuclear Regulatory Commission gg 0 4 $88 l

cc (Enclosure):

Mr. K. P. Barr, Acting Assistant Olrector for Inspection Programs TVA Projects Division U.S. Nuclear Regulatory Commission Region II 101 Marletta Street, NH, Suite 2900 Atlanta, Georgia 30323 Mr. G. G. Zech, Assistant Ofrector for Projects TVA Projects Olvision U.S. Nuclear Regulatory Commission One White Fitnt, North 11555 Rockville Pike Rockville, Maryland 20852 Sequoyah Resident Inspector Sequoyah Nuclear Plant 2600 Igou Ferry Road Soddy Daisy, Tennessee 37379 l

P i

{

t

3 ENCLOSURE SEQUOYAH NUCLEAR PIANT REVISED COMMITMENTS - SAFETY-RELATED SYSTEM DESIGN CRITERIA 1.

All safety-related system design criteria except the radiation monitoring system will be issued by May 31, 1988.

2.

The radiation monitoring system design criteria will be issued by June 30, 1988.