Text

V t

Commonwealth Edison one Fd N Sonal Plaza. Chicago, Ilknois (v 7 Address Reply tz Pos Office Box 767

/ chicago, nhnois so690 0767 August 25, 1988 Mr. A. Bert Davis Regional Administrator Region III U. S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, IL 60137

SUBJECT:

Braidwood Nuclear Power Station Unit 1 Cycle 1 Startup Report HEC Docket No. 50-456

REFERENCES:

(a)

February 29, 1988 S.C. Hunsader letter to A.B. Davis (b)

May 31, 1988 S.C. Hunsader letter to A.B. Davis

Dear Mr. Davis:

In accordance with Technical Specification 6.9.1.3, reference (a) provided the Startup Report for Braidwood Unit 1 Cycle 1.

That report covered initial criticality.

Reference (b) provided the Startup Report Supplement, dated May, 1988, covering the time from initial criticality through the 90% power testing plateau.

Enclosed with this letter is the Unit 1, Cycle 1 Start Up Report Final Supplement, dated August, 1988, covering the balance of Startup Testing including the completion of testing at the 100%

power testing plateau.

Please address any questions concerning this submittal to this office.

Very truly yours, h

f MW S. C. Hunsader Nuclear Licensing Administrator

~

Attachment cc:

S. Sands - NRR

/

NRC Document Control Desh enc 1: Braidwood Unit 1, Cycle 1 Startup Report, Final Supplement 4296K Y

8809010272 000025 DR ADOCK 0500 6

1

(