ML20153C729

From kanterella
Jump to navigation Jump to search
Forwards Braidwood Unit 1 Cycle 1 Startup Rept Final Suppl
ML20153C729
Person / Time
Site: Braidwood Constellation icon.png
Issue date: 08/25/1988
From: Hunsader S
COMMONWEALTH EDISON CO.
To: Davis A
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML20153C732 List:
References
NUDOCS 8809010272
Download: ML20153C729 (1)


Text

V t

Commonwealth Edison one Fd N Sonal Plaza. Chicago, Ilknois (v 7 Address Reply tz Pos Office Box 767 August 25, 1988

% / chicago, nhnois so690 0767 Mr. A. Bert Davis Regional Administrator Region III U. S. Nuclear Regulatory Commission 799 Roosevelt Road -

Glen Ellyn, IL 60137

SUBJECT:

Braidwood Nuclear Power Station Unit 1 Cycle 1 Startup Report HEC Docket No. 50-456

REFERENCES:

(a) February 29, 1988 S.C. Hunsader letter to A.B. Davis (b) May 31, 1988 S.C. Hunsader letter to A.B. Davis

Dear Mr. Davis:

In accordance with Technical Specification 6.9.1.3, reference (a) provided the Startup Report for Braidwood Unit 1 Cycle 1. That report covered initial criticality. Reference (b) provided the Startup Report Supplement, dated May, 1988, covering the time from initial criticality through the 90% power testing plateau. Enclosed with this letter is the Unit 1, Cycle 1 Start Up Report Final Supplement, dated August, 1988, covering the balance of Startup Testing including the completion of testing at the 100%

power testing plateau.

Please address any questions concerning this submittal to this office.

Very truly yours, hS. C. Hunsader f MW Nuclear Licensing Administrator

~

Attachment cc: S. Sands - NRR NRC Document Control Desh / ,

enc 1: Braidwood Unit 1, Cycle 1 Startup Report, Final Supplement 4296K 8809010272 000025 Y ,

DR ADOCK 0500 6 1 (

f

, - - . . - - - . . , _ . , , . - _ . . . ,