Informs of Util Plans to Resolve Generic Ltr 87-02 & Unresolved Safety Issue A-46, Seismic Qualification of Electrical Equipment. Intends to Join Seismic Qualification Util Group as Alternative for Addressing Ltr
ML20153B929
Person / Time
Site: Farley 
Issue date: 08/19/1988
From: Hairston W
ALABAMA POWER CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
REF-GTECI-A-46, REF-GTECI-SC, TASK-A-46, TASK-OR GL-87-02, GL-87-2, NUDOCS 8808310154
Download: ML20153B929 (1)


Text

,, g. - AlabarnaPowerComp!ny

' 600 North 18th Street Post Office Box 2641 Birrningham, Alabama 352914400 Telephone 2052501837 W. G. Hairston. ill Senior Vice President Nuclear Operations g

the southern electrcsystem August 19, 1988 Docket Nos. 50-348 t

U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Vashington, D.C.

20555 Gentlemen Joseph H. Farley Nuclear Plant - Unit 1 Seismic Qualification of Electrical Equipment (Generic Letter 87-02)

By letter dated June 23, 1988, Alabama Power Company discussed its plan to address Generic Letter 87-02.

At that time Alabama Power Company was strongly considering resolving Generic Letter 87-02 issues by performing a comparison between Units 1 and 2 of Farley Nuclear Plant.

Since Unit 2 had been reviewed by the NRC during initial Unit 2 licensing and determined to be adequate, this comparison vould demonstrate that Unit 1 is likewise seismically qtialified.

In addition, Alabama Power Company continued to monitor the activities of the Seismic Qualification Utility Group (SOUG) j and maintained this effort as alternative for addressing Generic Letter E'7 -02. Alabama Power Company has nov determined 'that joining S00G and implementing the applicable provisions of the generic resolution under development by:SQUG vould be the most expeditious approach to resolving Generic Letter:87-02 and thus Unresolved Safety Issue A-46, "Seismic j

Qualification of Equipment in Operating Plants."

j l

Alabama Power Company vill respond to the NRC's SER on the SOUG Generic Implementation Procedure on a schedule which is commensurate with the schedule for SQUG member utilities.

If you have any questions, please advise.

Respectfully submitted, 8808310154 880919 J

V PDR ADOCK 05000348 dA, k m _g._

P PDC V. G. Hairston, III VGH,III/BHV: dst-V8.18 d ON cc Mr. L. B. Long Tl Dr. J. N. Grace 8 0 Mr. E. A. Reeves Mr. V. H. Bradford

[

/