ML20153A759

From kanterella
Jump to navigation Jump to search
Notification of NRC Initial Operator Licensing Examination - Amended 05000298/2020301
ML20153A759
Person / Time
Site: Cooper Entergy icon.png
Issue date: 06/01/2020
From: Thomas Farina
Operations Branch IV
To: Dent J
Nebraska Public Power District (NPPD)
References
Download: ML20153A759 (4)


See also: IR 05000298/2020301

Text

June 1, 2020

Mr. John Dent, Jr.

Vice President-Nuclear and CNO

Nebraska Public Power District

Cooper Nuclear Station

72676 648A Avenue

P.O. Box 98

Brownville, NE 68321

SUBJECT:

COOPER NUCLEAR STATION - NOTIFICATION OF NRC INITIAL OPERATOR

LICENSING EXAMINATION - AMENDED 05000298/2020301

Dear Mr. Dent:

The purpose of this letter is to amend the dates for the upcoming operator licensing examination

validation and administration at Cooper Nuclear Station. Due to the COVID-19 pandemic, the

dates which were originally approved in a letter of September 6, 2019 (ML19249A968) could not

be met.

In conversations between myself and Mr. James Florence, Superintendent, Simulator and

Training Support, revised arrangements were made for the administration of operator licensing

examinations at Cooper Nuclear Station during the week of July 27, 2020. In addition, your

support for on-site validation of the examinations is required during the week of June 22, 2020.

Examination outlines, written examinations, operating tests, supporting reference materials, and

preliminary reactor operator and senior reactor operator license applications were previously

furnished by your staff. Final, signed applications certifying that all training has been completed

and requesting any waivers or excusals, as applicable, should be submitted at least 14 days

before the first examination date.

We request that any personal, proprietary, sensitive unclassified, or safeguards information in

your remaining submittals be contained in a separate enclosure and appropriately marked.

Delays in receiving the required materials, or the submittal of inadequate or incomplete

materials, may cause the examinations to be cancelled or rescheduled.

To conduct the requested written examinations and operating tests, it will be necessary for your

staff to provide adequate space and accommodations in accordance with ES-402, and to make

the simulation facility available on the dates noted above. In accordance with ES-302, your staff

should retain the original simulator performance data (e.g., system pressures, temperatures,

and levels) generated during the dynamic operating tests along with any video and audio

recordings of the dynamic operating tests until the NRC takes its licensing action on all of the

J. Dent, Jr.

2

applications and any adjudicatory actions on any hearing demands are complete. Appendix E

to NUREG-1021 contains NRC policies and guidelines that will be in effect while the written

examinations and operating tests are being administered.

The minimum guideline for receiving final waiver or excusal requests is 14 days before the first

examination date. Resolutions resulting from verbal inquiries by the licensee to the NRC are

not binding. Submittals addressing waivers and/or excusals should be in writing (i.e., on

NRC Form 398, or as directed when I am contacted to determine the method for submission).

The NRCs final decision on whether to grant a waiver or excusal will be documented on the

final (not preliminary) NRC Form 398 submitted for the applicant and will not be provided until

the final application is submitted to the NRC.

Paperwork Reduction Act Statement

This letter contains mandatory information collections that are subject to the Paperwork

Reduction Act of 1995 (44 U.S.C. 3501 et seq.). The Office of Management and Budget (OMB)

approved these information collections (approval number 3150-0011). Send comments

regarding this information collection to the Information Services Branch, Office of the Chief

Information Officer, Mail Stop: T6 A10M, U.S. Nuclear Regulatory Commission, Washington,

DC 20555-0001, or by e-mail to Infocollects.Resource@nrc.gov, and to the Desk Officer, Office

of Information and Regulatory Affairs, NEOB-10202, (3150-0011) Office of Management and

Budget, Washington, DC 20503.

The burden to the public for these mandatory information collections is estimated to average

400 hours0.00463 days <br />0.111 hours <br />6.613757e-4 weeks <br />1.522e-4 months <br /> per examination including the time for reviewing instructions, searching existing data

sources, gathering and maintaining the data needed, and completing and reviewing the

information collection. You may submit comments on any aspect of the information collection,

including suggestions for reducing the burden, to the FOIA, Privacy and Information Collections

Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by

electronic mail to INFOCOLLECTS.RESOURCE@NRC.GOV; and to the Desk Officer, Office of

Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and

Budget, Washington, DC 20503.

Public Protection Notification

The NRC may not conduct nor sponsor, and a person is not required to respond to, a request

for information or an information collection requirement unless the requesting document

displays a currently valid OMB control number.

This letter will be made available for public inspection and copying at

http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in

accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections,

Exemptions, Requests for Withholding.

J. Dent, Jr.

3

Thank you for your cooperation in this matter. Mr. Florence has been advised of the policies

and guidelines referenced in this letter. If you have any questions regarding the NRCs

examination procedures and guidelines, please contact me at 817-200-1117, or Greg Werner,

Chief, Operations Branch, at 817-200-1159.

Sincerely,

6/1/2020

X

Signed by: Thomas J. Farina

Thomas J. Farina, Chief Examiner

Operations Branch

Division of Reactor Safety

Docket No. 05000298

License No. DPR-46

ML20153A759

SUNSI Review:

ADAMS:

Non-Publicly Available

Non-Sensitive

Keyword:

By: TJF

Yes No

Publicly Available

Sensitive

NRC-002

OFFICE

SOE:OB

NAME

TFarina

SIGNATURE

TJF

DATE

5/29/2020