USEC A Global Energy Company September 15,1998 GDP 98-0195 Mr. Robert C. Pierson Chief, Special Projects Branch Division of Fuel Cycle Safety and Safeguards, NMSS U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Paducah Gaseous Diffusion Plant (PGDP)
Docket No. 70-7001 Monthly Update on Progress of Seismic Upgrades to Buildings C-331 and C-335
Dear Mr. Pierson:
By letter dated April 15,1998 (see the refsrence), USEC committed to provide a monthly update on the progress of the installation of the seismic upgrade modifications to Buildings C-331 and C-335 beginning May 15,1998.
The enclosure to this letter provides the progress ofinstallation of these modifications through August 31,1998. The enclosed summary schedule shows that cell floor utility relocations are slightly behind schedule due to an additional scope ofwork that has been identified. However, it is expected that this slippage can be made up and completion of the cell floor utility relocations will be in accordance with the schedule. Cell floor steel installation is currently behind schedule in both buildings with the greatest variance in Building C-331 (approximately two months behind). USEC is evaluating the schedule slippage to determine the impact on the June 30,1999 completion date.
/
. USEC will discuss this issue with the NRC after the effect on the completion date is determined.
j Relocation ofutilities and preparation for steel installation on the ground floor of both buildings did beginin August.
m ya Should you have any questions related to this subject, please contact Steve Routh at (301) 564-3251.
j There are no new commitments contained in this submittal.
l~
e85 N m.
-Sincerely, 8
o
- 5. A. Id t
m
~^
Steven A. Toelle h
Nuclear Regulatory Assurance and Policy Manager g5"*
6903 Rockledge Drive, Bethesda, MD 20817-1818 Telephone 301-564 3200 Fax 301-564-3201 http://www.usec.com Offices in L.ivermore, CA Paducah, KY Portsmouth, OH Washington, DC
t Mr. Robert C. Pierson
. September 15,1998 GDP 98-0195, Page 2 '
Reference:
Letter from Steven A. Toelle (USEC) to Robert C. Pierson (NRC), " Schedule for Seismic Upgrades to Buildings C-331 and C-335,". Letter GDP 98-0082, April 15, 1998.
Enclosure:
Schedule for Seismic Upgrades to Buildings C-331 and C-335 cc: NRC Region III Oflice NRC Resident Inspector - PGDP NRC Resident Inspector - PORTS Mr. Randall M. DeVault (DOE) j I
j i
i i
l i
1 I
Enclosure to GDP 98-0195 Milestone Schedule for Seismic Upgrades to Buildings C-331 and C-335 Progress Through August 31,1998
ACMVRy AcEvRy
- Eany + Eady rRem
.. _ 2_i _ _ _ _
8#
TKTG1J IJ iSWTL 1. U J ] F ' l ETT-~A 1J1J I AT SEISMIC UPGRADES C-331/C-335 IINTERMEDikTEIMi[ESTONE l K2RD021'Bidg Ci331 Start Cell Floof SteelInstallation..]10JUN98A 0'
+
i 0
+
l K2RD025 ~ Bldg CL335 Start Cell Floor Steelinstallation 30JUN98A K2RD02T Bldg C-331 Start Ground Floor SteelInstallation 17AUG98A
~
0
+
K2RD029^ Bldg C-335 Start Ground Floor Steel Installation - 17AUG9BA
' ~~ 0
+
l ~ PROJECT MANAGEMENT i K2RD001' Team assemble-(Mgmt 8 Support Personnel) 01APR98Ai20APR98A"O umm K2RD013 ~ PORC presentations ~(CAAS;SteeIInstallation)- 12JUN98A 18JUN98A~0 m
! ENGINEERING
~
~~
~~
f n2RD012 ] Complete brealfroom engineering design 03APR98Ar30SEP98 -
10
! 'K2RDOC2 ~ ~ Review'JS Alberici Qa Plan & Procedures--' 13APR98A,12JUN98A ~- O K2RD015' Establish QA & QC self assessment plan-~- ' 14MAY9 19JUN98A~0 mumme
[
- K2PD9929 Complete Design /CFC
- -'~-~ ---
~-~ 30SEP98 0
+
i PROC / FAB / DELIVERY j K2RD009 Procurement to contract ground floor relocations'04MAY9BA 19JUN98A 0
K2RD017 ~ Cell floor steel delivery (JS Alberici)
~ ~ ~ ~ ~
05MAY98A 31AUG98
~ ~4 i
! K2RD045 Ground Floor Fabrication (JS Alberici) ~~
~ ' '
25MAY98A29JAN99 108 l
l j K2RD047' Ground Floor Steel Delivery (JS'Alberici)-~
23DEC98 12FEB99-~~35 K2PP9939 Complete Procurement
- - - ~ - - '
12FEB99 ~ '
0
+
, CONSTRUCTION ~
K2RDC05-Contractor re~-mobilization (office, tools;mp~ r)-'20APRS8A 15MAY98A'-~0 ummum w
K2RD008-Training (Contractor) Initial Crew-04MAY98A 08MAY98A O
a i
i m
1W2 y.
hm Project Start 27 MAR 96
- sm Earty Bar Project FWah 30JUL99 Progrees Bar LOCKHEED MARTIN UTILITY SERVICES g
D*
SEISMIC UPGRADE PROJECT
-es ='W 7
SUMMARY
SCHEDULE (AUGUST-98)
4 AcWMy
-i s Eeny --
- Eeny.
Regn AspMy
~o-1
_d esenetygen
~
7aameti, Fledeli Der
- f g' = riWEe "y g " =]4 g g g, g g
(,
g M2RD010~ CsN floor utility iol6Esti6Hs-(Elet Mech'l&CJ 14REAY98A 28FEB99-117
';, g~.,
ZA
~~
' r-K2RD00T' JSA~and LRAUS~ work ~pekg's~~preo~(first 11) 22RRAY98A19JUN98A' ~O r
j K2RD024' Steelinstallathm C-331, Cell Floor 08JUH98A 30JUN99 ~
205
-- -=- --- -
- +
---+'-4 K2RDC28 ~5teelInstallation C-335, Cell Floor 30JUN98A 30JUN99 -
203
"~-~~ -
'-e,w
-+ +--- " <-,- ~~" - a i
! K2RD028-Steelinstallation C-331; Ground Floor 17AUG98A30JUN99 ~214 a ', u - - e o - - 4 v. - 4 " o -4 ' ~ - ~
" ' a -- " ' < -" ; 1
' K2RD030~5teelInstallation C-335, Ground Floor 17AUG98A 30JUN99'~~214 K2RD020 - Grd f;oof utilltfrelocations'(Elect l Mech, I&C)'- 11SEP98~~ 31REAY99 ~~181 F~ '-
- ~------~--"i-K2PC9989 Complete Constructionlinstallation 30JUN99-' -- D
+.
K2PK9989 Complete Project 30JUL99 ~