ML20151Y268

From kanterella
Jump to navigation Jump to search
Monthly Operating Repts for Aug 1998 for Browns Ferry Nuclear Plant,Units 1,2 & 3.With
ML20151Y268
Person / Time
Site: Browns Ferry  Tennessee Valley Authority icon.png
Issue date: 08/31/1998
From: Abney T, Jay Wallace
TENNESSEE VALLEY AUTHORITY
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9809180175
Download: ML20151Y268 (13)


Text

.

. . ,~ j IUA 1 Tennessee Valley Authonty. Post Office Box 2000 Decatur, Alabama 35609 j September 11, 1998 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 Gentlemen:

In the Matter of ) Docket Nos. 50-259 Tennessee Valley Authority ) 50-260 50-296 BROWNS FERRY NUCLEAR PLANT (BFN) - AUGUST 1998 MONTHLY OPERATING REPORT The enclosure provides the August 1998 Monthly Operating Report as required by BFN Technical Specifications Section 5.6.4.

If you have any questions concerning this matter, please call me at (256) 729-2636.

S ncer T. E. Abney Manager of uicens ng and Indub ry Af airs Enclosure g cc: See page 2 ,-Lk j i

9809180175 980831 PDR

~

ADOCK 05000259 R pyg

(

r 4 v t. o' n 11op,am l

. J l

l 1

U.S. Nuclear' Regulatory Commission l Page 2 September 11, 1998 {

l Enclosure cc (Enclosure):

Mr. Harold O. Christensen, Branch Chief U.S. Nuclear Regulatory Commission l Region II  !

'61 Forsyth Street, S.W.

Suite 23T85 Atlanta, Georgia 30303 l

Mr. Frederick J. Hebdon, Director Project Directorate II-4 Division of Reactor Projects I-II office of Nuclear Reactor Regulation, Mail 13 H3  ;

Washington, D.C. 20555 INPO Records Center Institute of Nuclear Power Operations 700 Galleria Parkway Atlanta, Georgia 30339-5957 Mr. James Lang, Manager Advanced Reactor Department Electric Power Research Institute 3340 Hillview Avenue Palo Alto, California 94304 NRC Resicent Inspector Browns Ferry Nuclear Plant 10833 Shaw Road Athens, Alabama 35611 Regional Administrator U.S. Nuclear Regulatory Commission Region II 61 Forsyth Street, S.W.

Suite 23T85 Atlanta, Georgia 30303 Ms. Barbara Lewis McGraw-Hill Companies 1200 G Street, N.W.

Suite 1100 Washington, D.C. 20005-3802 l

[

ENCLOSURE TENNESSEE VALLEY AUTHORITY BROWNS FERRY NUCLEAR' PLANT (BFN)

MONTHLY OPERATING REPORT AUGUST 1998 UNIT 1 DOCKET NUMBER 50-259 LICENSE NUMBER DPR-33 UNIT 2 DOCKET NUMBER 50-260 LICENSE NUMBER DPR-52 UNIT 3 DOCKET NUMBER 50-296 LICENSE NUMBER DPR-68

e OPERATIONAL

SUMMARY

AUGUST 1998 BROWNS FERRY NUCLEAR PLANT UNIT 1 Unit 1 remains shutdown on administrative hold to resolve various TVA and NRC concerns. Unit 1 has been on administrative hold since June 1, 1985. As a result, TVA' considers that accrual of reporting hours is suspended since the unit has a maximum dependable capacity of zero MWe. Accordingly, TVA does not consider reporting cumulative hours for the period beginning June 1, 1985, when calculating the operating status variables.

I t

BROWNS FERRY NUCLEAR PLANT UNIT 2 For the month of August, Unit 2 generated 794,960 megawatt hours gross electrical power and operated at a net capacity factor of 97.9 percent. As of August 31, 1998, Unit 2 has operated continuously for 305 days.

BROWNS FERRY NUCLEAR PLANT UNIT 3 For the month of August, Unit 3 generated 673,680 megawatt hours gross electrical power with a net capacity factor of 82.5 percent. On July 21, 1998, at 23:59 hours, the unit began coastdown for the Cycle 8 refueling outage. As of August 31, 1998, Unit 3 has operated continuously for 134 days.

E-1

v AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50-259 UNIT NO. ONE DATE: Sept. 3, 1998 COMPLETED BY: J. E. Wallace TELEPHONE (256)729-7874 MONTH AUGUST'1998 AVERAGE DAILY POWER LEVEL AVERAGE DAILY POWER LEVEL DAY (MWe-Net). DAY (MWe-Net)

1. .0 17. 0
2. 0 18. 0

, 3. 0 19. 0

4. O' -20. 0
5. 0 21. 0
6. 0 22. 0
7. 0 23. 0
8. 0 24. 0
9. 0 25. 0
10. 0 26. 0
11. 0 27. 0 12 0 28. 0
13. 0 29. O l
14. 0 30. 0
15. . 0 31. 0

-16.

0 l .. E-2 5

L:

AVERAGE DAILY UNIT POWER LEVEL r

DOCKET NO. 260 UNIT NO. TWO DATE: Sept. 3, 1998 COMPLETED BY: J. E. Wallace TELEPHONE (256)729-7874 MONTH August.1998

' AVERAGE DAILY POWER LEVEL AVERAGE DAILY POWER LEVEL DAY (MWe-Net) DAY (MWe-Net) 1.- 1081 17. 1056

2. 1058 18. 1098
3. 994 19. 1047
4. 1060 20. 1073
5. 1022 21. 987
6. ,1079 22. 1051

-7.

1028 23. -

1043

8. 1071 24, 1050
9. 1077 25. 1059
10. 1056 26. 1047 l
11. 1079 27. 1036  !

l 12 1034 28. 1044 l

.13. 1037 29. 889 l

14. 1031 30. 1054 l l
15. 1020 31, 1022 l
16. 1045 i E-3 l

[

s AVERAGE DAILY' UNIT POWER LEVEL DOCKET NO. .50-296 UNI { NO. THREE' DATE: Sept. 3, 1998 COMPLETED BY: J. E. Wallace TELEPHONE (256)729-7874 i MONTH August 1998 AVERAGE DAILY' POWER LEVEL AVERAGE DAILY POWER LEVEL DAY- (MWe-Net) DAY (MWe-Net)

1. 946 17, 873 2 .- 992 18. 928
3. 842 19. 862 l
4. 960 20. 826 l

.5. 911 21. 801 )

6. 962 22. 857
7. 954 23. 789
8. 933- 24. 841 j
9. 919 ~25. 844
10. 923 26. 845
11. 917 27. 829 12 912 28. 836
13. 894 29. 825 14; 892 30. 818
15. 901 31. 772
16. 835 l

I i

l OPERATING DATA REPORT Docket No 50-259 Date: Sept. 3.1998 Completed By: J. E. Wallace Telephone: (256)-729-7874  ;

1 l '. Unit Name: BFN Unit 1 l

2. . Reporting Period: August 1998
3. Licensed Thermal Power (MWt): 3293
4. Nameplate Rating (Gross Mwe): 1152

' 5. Design Electrical Rating (Net Mwe): 1065

6. Maximum Denendable Capacity (Gross MWe): 0
7. Maximum Dependable Capacity (Net MWe): 0
8. If changes Occur in Capacity Rating (Item Numbers 3 Through 7) Since Last Report, Give Reasons: N/A
9. Power Level To Which Restricted, If any (net MWe): 0
10. Reasons for Restrictions, If any: Administrative Hold This Month Yr-To-Date Cumulative *
11. Hours in Reporting Period 0 0 95743
12. Number of Hours Reactor was Critical 0 0 59521
13. Reactor Reserve Shutdown Hours 0 0 6997
14. Hours Generator On-Line 0 0 58267
15. Unit Reserve Shutdown Hours 0 0 0
16. Gross Thermal Energy Generated (MWh) 0 0 168066787
17. Gross Electric Energy Generated (MWh) 0 0 55398130
18. Net Electrical Energy Generated (MWh) 0 0 53796427
19. Unit Service Factor 0 0 60.9
20. Unit Availability Factor 0 ,

0 60.9

21. Unit Capacity Factor (Using MDC Net) 0 0 52.8
22. Unit Capacity Factor (Using DER Net) 0 0 52.8
23. Unit Forced Outage Rate 0 0 25.6
24. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each): N/A
25. If Shutdown at End of Report Period, Estimate Date j ofStartup: To Be Determined
  • Excludes hours under Administrative Hold (June 1,1985 to present) i E-5 i

l

]

.j OPERATING DATA REPORT i

i Docket No. 50-260 Date: Sept. 3.1998 i

. Completed By: J. E. Wallace Telephone: (256)-729-7874 i

1. Unit Name: BFN Unit 2 )

-2. ' Reporting Period: Aueust 1998

' 3. Licensed Thermal Power (MWt): 3293

4. Nameplate Rating (Gross Mwe): 1152'
5. Design Electrical Rating (Net Mwe): 1065
6. Maximum Dependable Capacity (Gross MWe): 1998.4
7. Maximum Dependable Capacity (Net MWe): 1065 l
8. If changes Occur in Capacity Rating (Item Numbers 3 Through 7) Since Last Report, Give Reasons: N/A
9. ' Power Level To Which Restricted, If any (net MWe): N/A
10. Reasons fcr Restrictions, If any: N/A This Month Yr-To-Date Cumulative *
11. ' Hours in Reporting Period 744.0 5831.0 154206
12. Number of Hours Reactor was Critical 744.0 5831.0 112637
13. Reactor Reserve Shutdown Hours 0.0 0.0 - 14200

-- 14. Hours Generator On-Line 744,0 5831.0 110244

15. Unit Reserve Shutdown Hours 0.0 0.0 0
16. Gross Thermal Energy Generated (MWh) 2438357.0 19111536 329147020

- 17. Gross Electric Energy Generated (MWh) 794960.0 6371900 109374378

- 18. Net Electrical Energy Generated (MWh) 775857.0 6227166 106433258

19. Unit Service Factor 100.0 100.0 71.5
20. Unit Availability Factor 100.0 100.0 71.5
21. Unit Capacity Factor (Using MDC Net) 97.9 100.3 64.8
22. Unit Capacity Factor (Using DER Net) 97.9 100.3 64.8

- 23. Unit Forced Outage Rate 0.0 0.0 13.5

24.  : Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each): N/A
25. If Shutdown at End of Report Period, Estimate Date of.Startup: N/A .

4

  • Excludes hours under Administrative Hold (June 1,1985 to May 24,1991)

E-6

OPERATING DATA REPORT Docket No. 50-296 Date: Sept. 3.1998 Completed By: J. E. Wallace Telephone: (256)-729-7874 i

1. Unit Name: BFN Unit 3 i Reporting Period: Aunust 1998
9. Licensed Thermal Power (MWt): 3293
4. Nameplate Rating (Gross Mwe): -1152
5. Design Electrical Rating (Net Mwe): 1065
6. Maximum Dependable Capacity (Gross MWe): 1098.4
7. Maximum Dependable Capacity (Net MWe): 1065
8. If changes Occur in Capacity Rating (Item Numbers 3 Through 7) Since Last Report, Give Reasons: N/A
9. Power Level To Which Restricted, If any (net MWe): N/A
10. Reasons for Restrictions, If any: N/A This Month Yr-To-Date Cumulative *
11. Hours in Reporting Period 744.0 5831.0 97428
12. Number of Hours Reactor was Critical 744.0 5563.0 68637
13. Reactor Reserve Shutdown Hours 0.0 0.0 5150
14. Hours Generator On-Line 744.0 5536.6 67258
15. Unit Reserve Shutdown Hours 0.0 0.0 0.0
16. Gross Thermal Energy Generated (MWh) 2140920.0 17145055 204579968
17. Gross Electric Energy Generated (MWh) 673680.0 5648960 68412370
18. Net Electrical Energy Generated (MWh) 653694.0 5503351 65708849
19. Unit Service Factor 100.0 95.0 69.0
20. Unit Availability Factor 100.0 95.0 69.0
21. Unit Capacity Factor (Using MDC Net) 82.5 88.6 63.3
22. Unit Capacity Factor (Using DER Net) 82.5 88.6 63.3
23. Unit Forced Outage Rate 0.0 0.1 15.5
24. Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration of Each): Unit 3 Cycle 8 Refueling Outage, Scheduled to Begin September 20,1998,22 Days Duration
25. If Shutdown at End of Report Period, Estimate Date of Startup: N/A
  • Excludes hours under Administrative Hold (June 1,1985 to November 19,1995)

E-7

UNIT SHUTDOWNS AND POWER REDUCTIONS REPORT MONTH: AUGUST 1998 DOCKET NO: 50-259 UNIT NAME: BFN-1 DATE: September 3,1998 COMPLETED BY: J. E. Wallace TELEPHONE: (256) 729-7874 Ng 9 Date} iType' : Duration! ; Reason 2 : Method. 00! LLicenscej .

Systeni] Component! ;Cause and Corrective Action to.Preventj

-~(Hours)( Shuttingjj Event; Report? ~

Code *r Code *# iRecurrence?

.:r .

^

No!

^

DownL~ _

Rea$ tor'd 1 06/01/85 S 744 F 4- N/A N/A N/A Administrative hold to resolve various TVA and NRC concerns.

2

' F: Forced Reason: ' Method

  • Instructions for Preparation of S: Scheduled A-Equipment Failure (Explain) 1-Manual Data Entry sheets for Licensee B-Maintenance or Test 2-Manual Scram Event Report (LER)

C-Refueling 3-Automatic Scram (NUREG - 1922)

D-Regulatory Restriction 4-Continuation of Existing E-Operator Training and License Outage Examination 5-Reduction F-Administrative 9-Other G-Operational Error (Explain)

H-Other (Explain)

E-8

_ _ _ _ . - - . _ _ _ _ _ _ _ . _ _ _ _ _ _ _ - m___-_._m .____A._-m-___ _-____-_________-_-_m - -m_ ..-__r_. __m -

~~

UNIT SHUTDOWNS AND POWER REDUCTIONS REPORT MONTH: AUGUST 1998 DOCKET NO: 50-260

- UNIT NAME: BFN-2 DATE: September 3,1998 COMPLETED BY: J. E. Wallace TELEPHONE: (256) 729-7874 NS !jDatej Type'c Duration;. Reason *L Alethod ofJ ;Licenseef (Systeni! Coinpo_nenti Cause;and Corrective Action;to; Prevent?

l(Hours)f

~

Shuttingl]  : Event Reportl .CSdeY [ Code"

! Recurrence 3

!Downl  : No' -

~ReactSYE * >

N/A 2

8 F: Forced Reason: ' Method ' Instructions for Preparation of S: Scheduled A-Equipment Failure (Explain) 1-Manual Data Entry sheets for Licensee B-Maintenance or Test 2-Manual Scram Event Report (LER)

C-Refueling 3-Automatic Scram (NUREG - 1022)

D-Regulatory Restriction 4-Continuation of Existing E-Operator Training and License Outage Examination 5-Reduction F-Administrative 9-Other G-Operational Error (Explain)

H-Other (Explain)

E-9

UNIT SHUTDOWNS AND POWER REDUCTIONS REPORT MONTH: AUGUST 1998 DOCKET NO: 50-296 UNIT NAME: BFN-3 DATE: September 3,1998 COMPLETED BY: J. E. Wallace TELEPHONE: (256) 729-7874 JN;ug #Datej Type'~ ! Duration; (Reason

  • Method oQ ! Licensee;! Systeni: Component ;.Cause and;Correc.t.ive Action to Pm: cat)

~

(Hours [ FSlistting? [EyeRRepodl l Cod 4I [ Code? lR$currence? ~
Downi . 'No m ,

a  ; Reactor'd ^ '

NA 2 3

' F: Forced Reason: Method

  • Instmetions for Preparation of S: Scheduled A-Equipment Failure (Explain) 1-Manual Data Entry sheets for Licensee B-Maintenance or Test 2-Manual Scram Event Report (LER)

C-Refueling 3-Automatic Scram (NUREG - 1022)

D-Regulatory Restdction 4-Continuation of Existing E-Operator Training and License Outage Examination 5-Reduction F-Administrative 9-Other G-Operational Error (Explain)

H-Other (Explain)

E-10