PNO-77-137:RPV Slated from Pebble Springs (Oregon) Site Dropped Approx 10 Feet Onto Barge When Being Loaded at Mt Vernon,In B&W Facility.Aprox 11 of Instrument Nozzles Bent, Some as Much as 51 Degrees
ML20151X799
Person / Time
Site: 05000514
Issue date: 08/04/1977
From: Dreher F, Moseley N, Reinmuth G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
To:
References
PNO-77-137, NUDOCS 9809170255
Download: ML20151X799 (1)


Text

fy,yuum 4

ri j

l-sf q w PRELIMII;ARY NOTIFICATION

[

August 4, 1977

~

m.

PRELIMINARY NOTIFICATION OF EVENT OR UNUSUAL OCCURRENCE--PNO-77-137

_This_ preliminary notification constitutes _ EARLY notice of an event of POSSIBLE safety or public interest significance.

The information presented is as initially received without verification or evaluation _

and is basically all that is known by IE staff on this date.

Facili ty Portland General Electric Company Pebble Springs Unit No. 1 Docket No. 50-514

Subject:

DAMAGE TO REACTOR PRESSURE VESSEL DURING LOADIMG ON BARGE The Reactor Pressure Vessel slated for Pebble Springs (Oregon) site dropped approximately 10 feet onto the barge it was being loaded on at the Mt. Vernon, Indiana B&W facility. The vessel came to rest on dunnage stacked on the barge deck. Approximately 11 of the instrument nozzles were bent, some as much as 51 degrees.

The vessel was being lifted on the barge by use of a 500 ton crane using two hooks. The brake on one of the hoists became overheated, allowing the bottom end of the vessel to slip at a rapid rate onto the dunnage.

Another 500 ton crar.e using one hook and a speader bar lifted the vessel and returned it to the shop area for any needed repairs.

Hartford Insurance and Bechtel representatives were at the site when the vessel was dropped.

Portland General Electric is sending an NDE specialist to the site to evaluata the extent of damage.

The gi j

Region V inspector assigned to the Pebble Springs Project will followup with the applicant (no CP or LWA has yet been issued for dl this project).

A O:

No media interest has been noted at the present time.

No press 2i release is planned.

Region V (San Francisco) received notification of this occurrence by telephone at 9.30 a.m. August 2,1977, from Portland General Electric Company.

Contact:

FADreher, IE x27451 GWReinmuth, IE x 27551 NCMoselcy x27344 Distribution: Transmitted H St m/37 ;

Commissioner Kennedy C. C. Kammerer, CA G. F. Murphy, JCAE Commissioner Gilinsky S. J. Chilk, SECY H. H. Whiteside, SCNR H. R. Myers, HCEE Transmitted:

MNBB N # d P Bldg /#ld SS Bldg /d : </V L. V. Gossick, EDO E. G. Case, NRR C. V. Smith, NMSS S. H. Hanauer, EDO J. A. Harris, PA

/

W. G. Mcdonald, MIPC Luge (MAIL)

E.Volgenau,i~N R. G. Ryan, OSP T. J. TElTernan, 01 A Region J2__~ ed:

11. K. Shapar, ELD PRELIf11 NARY NOTIFICATION 9809170255 770804 PDR I&E PNO-77-137 PDR

..