Forwards Revised Attachment I to GL Koester Re Temporary Exemption to Section III.D.3 of 10CFR50,App J. Rev Incorporates Info Re Five Addl Valves
ML20151W101
Person / Time
Site: Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 02/05/1986
From: Koester G
KANSAS GAS & ELECTRIC CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
KMLNRC-86-025, KMLNRC-86-25, NUDOCS 8602110489
Download: ML20151W101 (4)


Text

_ _ - - _ _, - - _ _ - - - _ - - - _ _

KANSAS GAS AND ELECTRIC COMPANY THE ELECTM COMPANY I

{

ota==t norstra u m.. " "* "*

i February 5, 1986 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C.

20555 KMLNRC 86-025 Re:

Docket No. STN 50-482 Ref:

1)KMLNRC 86-008 from G.L. Koester, KG&E to H.R. Denton, NRC, dated 1/20/86 Subj :

Supplemental Information Regarding Temporary Exemption to 10CFR50, Appendix Je Section III.D.3

Dear Mr. Denton:

The purpose of this letter is to provide information inadvertently omitted from Attachment I to the Reference.

This information consists of five additional valves and associated information that did not appear in the table in Attachment I.

However, the information was accurately provided in

~

Attachment II to the Reference.

A revision to Attachment I is provided.as an enclosure to this letter.

Please replace the affected pages of the Reference with the enclosure.

If you have any questions concerning this matter, please contact me or Mr.

O. L. Mayaard of my staff.

Very truly yours, Glenn L. Koester Vice President - Nuclear GLK:see Enclosure cc: P0'Connor (2) p

""* "8 AD - J. KNIGHT (1tr Only)

EJohnson EB (BALLARD)

EICSB (ROSA)

B 8602110409 860200

, Ji RSB (BERLINGER)

PDR ADOCK O$000402 P

PDR I

FOB (CENAROYA) 201 N. Market - Wictuta, Kansas - man Address: PO. Box 208 I #ctuta, Kansas 67201 - Telephone: Area Code (316) 261-6451

ENCLOSURE

(

J 2

ATTACHMENT 1 Rev. I l

l

Mr. H. R. Denten KMLNRC 86-025 February 5, 1985 Attachment I Rev. I to KMLNRC 86-008 Page 1 of 2 SAFETY EVALUATION This application requests a revision to the Wolf Creek Generating Station, Unit No.

1 Technical Specifications Section 4.6.1.2.d to allow a one-time only deferment of the specified 24 month mar.imum surveillance interval on the below listed containment penetrations for the first operating cycle only (Cycle 1);

provided these surveillances are performed prior to startup following the first refueling outage (Refuel 1).

These surveillances cannot be safely performed at POWER OPERATION.

The proposed changes to the Technical Specifications are provided as Attachment IV.

Refuel 1 is the next scheduled shutdown and is currently scheduled to begin in October, 1986.

In the event of any unanticipated delays in the refueling schedule a unit shutdown to perform these surveillances will be initiated by October 31, 1986. Therefore this request entails an approximate seven month extension in the most limiting case.

If an. unscheduled shutdown of sufficient duration and resulting in appropriate plant conditions occurs prior to Refuel 1, Kansas Gas and Electric Company intends to perform any surveillances that can reasonably be completed.

Since refueling outages normally occur approximately every twelve to eighteen. months, extensions beyond the twenty four month maximum interval allowed by the Technical Specifications are not usually necessary.

However, due to the extended plant startup program and plant performance during Cycle 1, Kansas Gas and Electric Company is requesting the aforementioned Technical Specification Revisions.

Without the requested revisions Wolf Creek Generating Station would be forced into an outage for the purpose of surveillance testing.

Penetration Valve Surveillance Due Date P-41............. BB-V118 12/12/86 BB-HV8351A 07/12/86 P-22............. BB-V148 07/06/86 BB-HV8351B 07/07/86 P-39............. BB-V178 07/09/86 BB-HV8351C 07/11/86 P-40............. BB-V208 07/09/66 BB-HV8351D 07/09/86 P-24............. BG-V135 03/01/86 BG-HV8100 03/01/86 BG-HV8112 08/25/86 P-74............. EG-V204 07/19/86 EG-HV58 12/04/86 I

EG-HV127 12/04/86 P-80............. BG-8381 04/13/86 BG-HV8105 07/18/86 P-23............. BG-HV8160 04/19/86 BG-HV8152 04/22/86 P-71............. EF-HV31 07/12/86 EF-HV33 07/12/86 l

  • Note these valves included only for completeness

4 e

Mr. H. R.;Denton ENLNRC 86-025

" Rev.-l to KMLNRC 86-008 Page 2 of 2 P-73............. EF-HV45 06/09/86 j-EF-HV47 06/09/86

[

EF-HV49 06/09/86 l

--P-28............. EF-HV32 09/25/86 EF-HV34 09/25/86 l

P-29.....-.........'EF-HV46 09/25/86 EF-HV48 09/25/86

+

EF-HV50 09/25/86

-For each of the penetrations considered in the request-for extension of the-surveillance interval, it can be shown that one or both of the following

- design parameters apply:

1.

A closed-ASME piping system (inside and/or outside containment) precludes the release of containment atmosphere to the environs.

i 2.

Should an isolation valve leak slightly when

closed, the pressurized fluid seal within the pipe precludes. release of containment atmosphere to the environs.

4 Specific details for each containment penetration are included as Attachment i

II and III.

In each case, possible degradation of a containment leakage barrier does not result in a release of radioactive materials from the i

containment atmosphere.

-~

Therefore, the proposed amendment does not increase the probability or consequences of an accident previously evaluated.

The proposed change does not. involve hardware changes nor a change in the l

. manner in which the isolation systems at each penetration functions.

Therefore, the possibility of creating a new-or different kind of accident from any. accident previously evaluated does not ar.iat.

The proposed change does not alter the leakage rate limitations' established i

- in the Technical Specifications.

Therefore, the margin for possible deterioration ~ of the containment integrity during the service intervals between tests has not been reduced.

Additionally, the integrity of-the closed systems has been verified by the Containment Integrated Leak Rate i -

Test (ILRT).

The impact of extending the testing interval of penetrations

[

bounded by these closed systems is reduced by satisfactory ILRT results.

The requested revisions would not have a significant impact on safe operation of the plant when compared to the transient associated with a shutdown for the purpose of performing these surveillances.

Based on the above and the considerations presented in Attachment III, the aforementioned proposed revisions to the Wolf Creek Generating Station, Unit No.

1, Technical Specifications do not adversely affect or endanger the health or safety of the general public or involve a significant safety hazard.