Responds to Re Schedule for Implementation of Hardware Mods,Per Insp Rept 50-271/85-19.Schedule Cannot Be Expedited Since Engineering Evaluation in Progress. Temporary Mod to Physical Security Plan Will Be Submitted
ML20151U643
Person / Time
Site: Vermont Yankee File:NorthStar Vermont Yankee icon.png
Issue date: 01/23/1986
From: Murphy W
VERMONT YANKEE NUCLEAR POWER CORP.
To: Murley T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
FVY-86-7, NUDOCS 8602110073
Download: ML20151U643 (2)


Text

?

4 Q

VERMONT YANKEE NUCLEAR POWER CORPORATION

~

RD 5. Boa 169. Ferry Road. Brattleboro. VT 05301 ENGINEERING OFFICE

/

1671 WORCESTER AOAD F AAMINGHAM. MASSACHUSETTS 01701 tatt%=t sit era otoo January 23, 1986 U.S. Nuclear Regulatory Commission Office of Inspection and Enforcement Region I 631 Park Avenue King of Prussia, PA 19406 Attention:

Dr. Thomas E. Murley Regional Administrator

References:

a)

License No. OPR-28 (Docket No. 50-271) b)

Letter, USNRC to VYNPC, NVY 85-275, dated 12/31/85 c)

Letter, VYNPC to USNRC, FVY 85-92, dated 10/04/85 Dear Sir

Subject:

Supplemental Information Pertaining to Inspection No. 50-271/85-19 In response to your letter of December 31, 1985 (Reference (b)], we have reviewed the schedule identified in our October 4, 1985 letter (Reference (c)]

regarding the implementation of certain hardware modifications. We have concluded that we are unable to expedite the schedule for the following reasons:

1)

The engineering evaluation to determine the exact scope of the necessary hardware modification is in progress and is presently being done on an expedited schedule.

2)

We cannot finalize the schedule for completing the hardware modifica-tion until the engineering evaluation is completed.

In addition, a detailed. design change package has to be developed and approved prior to the actual modification taking place.

As stated in our October 4 letter, we believe the current schedule is justified since interim measures have been implemented which assure CAS-SAS monitoring effectiveness until the permanent modification is made.

In addition, we will submit a temporary change to our Physical Security Plan within ten (10) days which formally incorporates the interim compensatory measures described in our October 4 letter.

060D110073 060lZi N

PDH ADUCK OSOOOP/ l f

a P Dit I h

o VERMONT YANKEE NUCLEAR POWER COMPOHATION 4'

U.S. Nuclear Regulatory Commission January 23, 1986 Page 2 Based on the above, we believe that the current schedule for completing the necessary hardware nedifications is justified. However, should you have any questions or desire additional information, please contact Mr. James B.

Sinclair, Security Supervisor, at our plant site.

Very truly yours, "f'Yj Warren P. Murphy Vice President and Manager of Operations WPM /RP/dessp4.1 y___..._,,~