Log # TXX-88608 i
~
File 8 10110
=
=
908.3 R ' 'OC'" U'b ('I i
illEl CCTRIC August 9, 1988 f
Wmse G. rowinu om,,
m n,,a,,,
i U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C.
20555 SUBJECI: COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)
DOCKET N05. 50-445 AND 50-446 CLASS 1E CABLE ARRANGEMENT SDAR: CP-87-101 (SUPPLEMENTAL REPORT)
Gentlemen:
On January 11, 1988, we informed you t,j our report logged Txx-88063 of a deficiency involving Class 1E cable arrangement which we deemed reportable under the provisions of 10CFR50.55(e).
This supplemental report is submitted to provide the status of corrective actions.
The documentation on Nonconformance Reports (NCRs) of any multiple single conductors per phase circuits not in agreement with the revised requirements of Electrical Specification 2323-ES-100 (as discussed in TXX-88063) is presently scheduled for completion by December 30, 1988, for Unit 1 and i
prior to fuel load for Unit 2.
[
r Very truly yours, W. G. Counsil t
By:
4).
Jp)hW. Beck Vrce President, Nuclear Engineering WJH/grr c - Mr. R. D. Martin, Region IV Resident Inspectors, CPSES (3) fg>1 5" E 8 %,P _