ML20151R052
| ML20151R052 | |
| Person / Time | |
|---|---|
| Site: | South Texas |
| Issue date: | 07/14/1988 |
| From: | Barnes I, Gilbert L NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| To: | |
| Shared Package | |
| ML20151R035 | List: |
| References | |
| 50-498-88-38, 50-499-88-38, NUDOCS 8808120035 | |
| Download: ML20151R052 (5) | |
See also: IR 05000498/1988038
Text
.
-
..
.
. - .
..
..
~* ' *
e
y
,
,-
1
APPENDIX B
U.S. NUCLEAR REGULATORY COMMISSION
REGION IV
NRC Inspection Report:
50-498/88-38
Operating License:
50-490/88-38
Construction Permit:
CPPR-129
Dockets:
50-498
50-499
Licensee:
Houston Lighting & Power Company (HL&P)
P.O. Box 1700-
Houston, Texas 77001
Facility.Name:
South Texas Project (STP), Units 1 and 2
Inspection At:
Inspection Conducted:
June 27 through July 1, 1988
Inspector:
/
7/N/' 6
L. D. G Hbert, Reactor Inspector, Materials
Uate
and Quality Programs Section, Division of
Reactor Safety
Approved:
b%
7//4/P7
I. Barnes, Chief, Materials and Quality
Date
Programs Section, Division of Reactor Safety
,
Inspection Summary
I_nspection Conducted June 27 through July 1, 1988 (Report 50-498/88-38)
Areas Inspected:
No inspection of Urit 1 was conducted.
Results:
Not applicable.
Inspection Conducte'd June 27 through July 1,1988 (Report 50-499/88-38)
Areas Inspected:
Routine, unannounced inspection of preservice inspection of
coniponents and component supports.
Results: Within the area inspected, one violation was identified (failure to
follow instructions, paragraph 2.b).
8808120035 880720 "
gDR
ADOCK 05000498
PNU
.
. _ _ _ .
_ _ .
. . .
- - _ . . - _
- , - ,
.
- ---. . - - - .
-
-
- _ - _ _ . - -
r
._,
,
.
2
DETAILS
1. .
Persons Contacted
HL&P
- J. T. Westermeier, Project Manager
- T._J. Jordan, Manager,ProjectQualityAssurance.(QA)
- L. Giles, Operations Manager . Unit 2
- D. C. King, Construction Manager
- A. R. Mikus, General Supervisor, Construction
- R. L. Beverly, Preservi-
Inspection (PSI)/ Inservice Inspection (ISI)
Supervising Engineer
- W. G. Wellborn, Supervising Project Engineer
_
- J. R. Mertink, Lead Engineer
- W. W. Trujillo, Supervisor, Project QA
- D. A. Murdock, ISI Coordinator, Piping
Bechtel Engineering Corporation (BEC)
- R. W. Miller, Project QA Manager
- R. H. Medina, QA Supervisor
- R. D. Bryan, Construction Manager
- R. Parekh, Project Engineer
Ebasco Services Incorporated (ESI)
- D. D. White, Construction Manager
.
- R. Apel, Quality Program Site Manager
- B. Higby, Piping Quality Control Supervisor
- W. M. Pardee, QA Site Supervisor
The NRC inspector also interviewed other contractor personnel during the
inspection.
- Indicates the personnel that attended the exit meeting.
The NRC resident
inspector also attended the exit meeting.
2.
Preservice Inspection (PSI)
a.
Review of Program (73051)
Initial NRC inspection of the Unit 2 PSI program is documented in NRC
Inspection Report 50-498/88-36; 50-499/88-36. During this
inspection, the NRC inspector selectively reviewed changes to the
licensee's PSI Examination Program Plan for Unit 2.
The review
included changes through Change No. 20.
No violations or deviations were identified.
- _ - _ _ _ _ _ _ _ _ _ _ _ _ _
'.
-
.
.
..
'
3
b.
Observa_t_i_on of Work Activities
(73053)
The NRC inspector reviewed the repairs required as a result of the
. PSI examinations.
Six items required to be repaired were selected
for this review.
Each item required to be repaired was identified in
a nonconformance report (NCR).
The repair was accomplished by Ebasco
under the construction program requirements and procedures. Two
items required repair welding in order to repair indications of lack
of fusion identified during the PSI ultrasonic examination.
The
repairs were nondestructively examined as required by the
construction program requirements and then reexamined under the PSI
examination program. The repairs reviewed are listed below:
Item Repaired
NCR Number
RPV Closure Stud 10B
AN-03557
Pipe 6-SI-2106-2
Pipe 6-SI-2106-1
Pipe 8-AF-2008(C)-15PL4&8
SS-05552
Pipe 8-AF-2012(C)-20PL5
SS-05553
In the areas inspected, the repairs and examinations were performed
in accordance with the requirements of the ASME Section III
construction code and the ASME Section XI preservice inspection code.
However, during the review of the repair of a surface indication on
auxiliary feedwater pipe spool AF-2012-H identified by PSI
examination of Item 8-AF-2012(C)-20PL5 the NRC inspector noted that
NCR SS-05553 required that the pipe minimum wall thickness after
repair be determined by mechanical or ultrasonic methods and
recorded. The NCR further stated that the wall thickness was not to
be reduced below 0.437 inch.
Since only the excavation depth was
recorded, the NRC inspector requested that the minimum wall thickness
be verified.
The actual wall thickness was ultrasonically measured
to be 0.418 inch at its thinnest area which is 0.019 inch below the
minimum wall thickness specified by the NCR. The nonconforming
condition was documented on NCR SP-05258. The NRC inspector
determined that QC personnel had measured the depth of excavation as
1/64 inch and then subtracted it from the 0.500 inch nominal wall
thickness specified for schedule 80S pipe. This method of
determining minimum wall thickness, although indicated as common
practice, is neither authorized by any procedure nor conservative, in
that it fails to recognize that pipe manufacturing tolerances would
permit an actual wall thickness of up to 121 percent below nominal to
be supplied.
The failure to follcw documented instructions for
measuring the minimum wall thickness is an apparent violation
(498/8838-01; 499/8838-01).
.
. -
- - -
-
- - _ _
.-
.-
.- _.
_
,
m
,
' *
.'
1;
,
,
'
0
4
c.
Review of Records
(73055)
The NRC inspector reviewed the following 25 PSI examination records
for completeness and retrievability.
The records included
visual (VT-1), liquid penetrant (PT), magnetic particle (MT), and
ultrasonic-(UT) examinations for components such as piping
longitudinal and circumferential welds, flange bolting, RCP flange
surface,-steam generator channel head cap to support ring, pipe lugs
for hangers, and pump body welds.
Exam Number
Method
Category
2(1.5)-CV-2126-BB1-2
B-J
2(1.5)-CV-2126-BB1-2FB
VT-1
B-G-2
4-RC-2422-BB1-1
B-J
6-RC-2015-NSS-1
B-F
SG-28-SR1
B-B
31-RC-2102-NSS-LOOP-1-2
B-J
16-RC-2412-NSS-3
B-J
2-CV-2121-BB1-1
B-J-
12-RH-2101-BB1-3A
B-J
6-S1-2327-B81'-7
B-J
RCP-2B-FS
VT-1
B-G-1
8-AF-2006-GA2(C)-20PL1
C-E
through -20PL8
8-CS-2102-PB2-2 & -2LU
C-F
B-RH-2103-KB2-3 & -3LU
C-F
RHARHS-2A-IWA1
C-C
SIAPHH-28-PCW2
C-G
No violations or deviations were identified.
. _ .
.-
, ,
< , 'f _ =
!
'
.
5-
.
3._
Exit Interview
The NRC inspector met with the licensee representatives denoted in
paragraph 1 on July 1, 1988, and summarized the inspection scope and
findings.--
!
The licensee comitted to a review of the Unit-1 records for potential
minimum wall violations resulting from QC inspectors using nominallwall
thickness tables and depth of excavation for detemining remaining wall
thickness. The licensee estimated the review would be completed by
July 10, 1988.
!
-
,