ML20151P118

From kanterella
Jump to navigation Jump to search
Supplemental Deficiency Rept CP-87-40 Re Electrical Isolation Between Class 1E & non-Class 1E Equipment. Initially Reported on 880111.Unit 1 Completion Date Revised to 890215.Unit 2 Activities on Schedule
ML20151P118
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 08/03/1988
From: Counsil W
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
CP-87-40, TXX-88600, NUDOCS 8808090200
Download: ML20151P118 (1)


Text

.

M

=M Log # TXX-88600 2

File # 10110 C

C 907.5

" # '*C'R *'b'('}

NELECTRIC August 3, 1988 Williaan G. Counsil Enocwin Vke President U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C.

20555

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)

DOCKET NOS. 50-445 AND 50-446 ELECTRICAL ISOLATION BETWEEN CLASS 1E AND j

NON-CLASS 1E EQUIPMENT SDAR: CP-87-40 (SUPPLEMENTAL REPORT)

Gentlemen:

l On January 11, 1988, we notified you by our report logged TXX-88060 of a reportable deficiency involving electrical isolation between Class 1E and non-Class 1E ecuipment.

In our last report logged TXX-88287, dated March 7, 1988, we pro /idec a Unit I completion date of August 8,1988, for the implementation of the corrective actions associated with this issue.

The implementation schedule for Unit 1 corrective actions has been revised.

The new scheduled date for the completion of the corrective actions specified in TXX-88060 is February 15, 1989.

Unit 2 activities are still scheduled to be completed by Unit 2 fuel load.

Very truly yours,

$kfdu W. G. Counsil VPC/grr c - Mr. R. D. Martin, Region IV Resident Inspectors, CPSES (3) 8G08090200 880803