Submits Implementation Schedule for Proposed Fire Protection Mod of Auxiliary Bldg HVAC Sys.Advises of Manpower Adjustments to Accomodate 881020 Unit 2 Outage
ML20151L239
Person / Time
Site: Zion  File:ZionSolutions icon.png
Issue date: 07/28/1988
From: Trzyna G
COMMONWEALTH EDISON CO.
To:
Office of Nuclear Reactor Regulation
References
4996K, NUDOCS 8808030414
Download: ML20151L239 (2)


Text

_ -

' ' N Commonwealth Edison One Fir:: Naional Plan Chicago, Illinois

. , -  % i)]

V' Address Reply to: Post Offc3 Box 767 (s/ Chicago, Illinois 60690 0767 July 28, 1988 Director of Nuclear Reactor Regu)ation U.S. Nuclear Regulatory Commission Mail Station F1-137 Washington, DC. 20555

Subject:

Zion Nuclear Powee Station, Units 1 and 2 NRC Docket Nos. 50-295 and 50-304 Fire Protection-HVAC Modif3 cations Reforences July 15, 1988 letter from G.E. Trzyna to NRR Gentlemen:

Commonwealth Edison has evaluated the proposed fire protection modification of the Auxiliary Building HVAC syttoin and provides the following implementation schedule:

ACTIVITY COMPLETIQti DATE

1) Begin initial design activities June 29, 1988 (ie., conduit routing, emergency lighting location, conceptual design and procedure revisions)
2) Issue design drawings for comment August 5, 1988
3) Issue drawings foe construction September 1, 198S
4) Install new conduit for HVAC power Octobe.r 20, 1988 feeds for exhaust fans OA and OB
5) Disconnect exist.'.ng OA and OB power February 15, 1989 feeds: pull back cable into cable spreading room; reroute cable through new conduit and terminate
6) Fire wrap new conduit with 1-hour March 31, 1989 fira wrap A0 l

1 0 808030414 880728 p DR ADOCK 05000295 PDC

/ ., ,

6

+ '

(cont'd.)

ACTIVITY CCMPLETION DATE

7) Incorporate new installation into FOPS March 31, 1989
8) Install additional emergency lights March 31, 1989 The'above schedule represents a realistic aggressive attempt to complete the modification in a timely fashion. This modification was processed in an accelerated manner and in a more compressed time frame than a typical modification while still adhering to the requirements of the CECO modification program. Please bei advised that we have adjusted our manpower to accommodate the Unit 2 outage which begins on October 20, 1988.

Please direct any questions that you may have to this office.

Very truly yours, m(

G. E. Trzyna Nuclear Licensing Administrator

/klj cc J. Norris-NRR Resident Inspector-Zion 4966K