ML20151K996

From kanterella
Jump to navigation Jump to search
Notifies NRC of Change to Util Previous Commitment to Provide Bvps,Unit 2 Ipeee,Submittal by Jul 1997.IPEEE Submittal Date Has Been Rescheduled to 970930
ML20151K996
Person / Time
Site: Beaver Valley
Issue date: 07/29/1997
From: Jain S
DUQUESNE LIGHT CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9708060204
Download: ML20151K996 (1)


Text

. ~_ . _ . _ . _ _ _ . . _ _ _ . . _ _ ._ _. _. _ ._ ~ ._ -. _.

t-ver Valley Powet .itation SNppingport, PA 15077-0004 f

S

  • ENdE ioom r.x ElE E l %l*20*$vwon July 29,1997 4

l s

! U. S. Nuclear Regulatory Commission 2-

/ Attention: Document Control Desk Washington, DC 20555-0001 l

i

Subject:

Beave'r Valley Power Station, Unit No. 2

! Docket No. 50-412, License No. NPF-73 4 IPEEE Submittal Date Extension -

The purpose of this letter is to notify the Nuclear Regulatory Commission (NRC) of a change to our previous commitment to provide the Beaver Valley Power Station Unit No. 2 IPEEE submittal by July 1997. By letter dated October 1,1992, Duquesne Light Company made this commitment and the NRC acknowledged this with their letter dated July 19,1994.

The progress being made to meet this conunitment was interrupted when the NRC conducted their maintenance rule inspection the week of July 11, 1997. The key individuals working on the IPEEE were diverted to inspection preparation and support activities which resulted in the scheduled completion date being delayed. Therefore, the Beaver Valley Unit No. 2 IPEEE submittal date has been rescheduled to September 30, 1997.  ;

If you have any questions regarding this submittal, contact Mr. J. Arias, Director, Safety and Licensing at (412) 393-5203.

Sincerely, Sushil C. Jain c: Mr. D. M. Kern, Sr. Resident inspector Mr. H. J. Miller, NRC Region I Administrator Mr. D. S. Brinkman, Sr. Project Manager DELIVERING b!b,b,5f!$f $ bll I 9700060204 970729 I PDR ADOCK 05000412 P PDR

!