l j7 pg]4 April 25,1983 Docket Nos. 50-277 and 50-278 FACILITY: Peach Bottom Atomic Power Station, Units 2 and 3 LICENSEE: Philadelphia Electric Company (PECo)
SUBJECT:
SUMMARY
OF THE APRIL 5,1983 MEETING WITH PHILADELPHIA ELECTRIC COMPANY PERTAIriING TO STATUS OF REVIEW 0F APPENDIX R MODIFICATIONS Members of the NRC staff met with representatives of Philadelphia Electric Company (the licensee) on April 5,1983. A list of the meeting attendees is provided as Enclosure 1.
The purpose of the meeting was to discuss the status of Appendix R. Fire Protection Program, modifications at the licensee's Peach Bottom facility. The licensee confirmed three areas of Appendix R (10 CFR Part 50, Appendix R) where additional work, design and modifications still were required; namely,Section III G. Safe Shutdown capability Section M. Cable Penetration Seal Qualification, and Section III F Automatic Fire Detection. Presentations on these three areas by the licensee included a general description of modifications to be performed and target dates for submittal of design descriptions and completion of modifications. The licensee was asked to submit to the NRC within a short time period (approximately two weeks) a summary of its Peach Bottom's Appendix R status highlighting the three areas discussed at this meeting.
4:183?
Gerald E. Gears, Project Manager Operating Reactors Branch No. 4 Division of Licensing
Enclosure:
As stated 8305040716 830425 PDR ADOCK 05000277 F
PDR omce>
B # 4..:.D.. L...
45.1...
.- n.
NAC FORM 318 00-80)NRCM ON3 OFFICIAL RECORD COPY usceo:mi moco
?
MEETING
SUMMARY
DISTRIBUTION Licensee: Philadelphia Electric Company
- Copies also sent to those people on service (cc') 1,1,st. for subject plant (s).,
Docket File NRC PDR L PDR ORBi4 Rdg I
Project Manager-GGears JStolz Glainas Licensing Assistant-RIngram OELD JHeltames, AE0D ELJordan, IE JHTaylor, IE ACRS- (10)
NSIC NRC Meeting
Participants:
WJohns ton TWamEach RFerguson BShields-KCyr JStang RVollmer ABlough LWhitney t
e w
~
MEETING WITH PHILADELPHIA ELECTRIC COMPANY APRIL 5, 1983
SUBJECT:
APPENDIX R NAME ORGANIZATION
- Gerald E. Gears Project Manager, DL, NRR Victor Benaroya CMEB, DE, NRR William V. Johnston DE NRR T. V. Wambach ORB #S, DL, NRR R. L. Ferguson CMEB, DL, NRR Bill Shields ELD, NRC I
Karen Cyr -
ELD, NRC A. R. Blough Resident Inspector, Region I, NRC Leon E. Whitney IE, DQASIP, ORPB,Section I W. T. Ullrich PECo, Supt. Nuc. Services S. A. Spitis.,
PECo, PBAPS Staff G. Morley PECo, Supv. Eng. Mech. Engineering
~
Gary J. Reid PECo, Mechanical Engineering Douglas M. Groves PECo, Mechanical Engineering Troy B. Conner, Jr.
Conner & Wetterhahn, P.C.
Eugene J. Bradley PECo R. J. Lees PECo, Electrical Engineering V. S. Boyer PEco, Senior VP Nuclear Power W. J. Mindick PECo, Electrical Engineering W. C. Birely PECo, Nuclear Section John Stang CHEB, DE, NRR R. Vollmer Director, DE, NRR O
F v