ML20151C154
ML20151C154 | |
Person / Time | |
---|---|
Site: | South Texas |
Issue date: | 02/10/1988 |
From: | Day B AUSTIN, TX |
To: | Grimsley D NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM) |
References | |
FOIA-88-107 NUDOCS 8804120189 | |
Download: ML20151C154 (2) | |
Similar Documents at South Texas | |
---|---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARNOC-AE-000675, Forwards Clarification on Items Included in 990531 Response to RAI Re Proposed License Amend Associated with Operator Action for Sbloca,As Requested1999-10-21021 October 1999
[Table view]Forwards Clarification on Items Included in 990531 Response to RAI Re Proposed License Amend Associated with Operator Action for Sbloca,As Requested NOC-AE-000680, Forwards Rev 5 to 0PGP03-ZV-0001, Severe Weather Plan1999-10-20020 October 1999 Forwards Rev 5 to 0PGP03-ZV-0001, Severe Weather Plan NOC-AE-000683, Forwards 30-day Rept Concerning Significant Changes to Accepted Large Break Loss of Coolant Accident ECCS Evaluation Model for South Tx Project,Units 1 & 2,IAW 10CFR50.46(a)(3)(ii)1999-10-19019 October 1999 Forwards 30-day Rept Concerning Significant Changes to Accepted Large Break Loss of Coolant Accident ECCS Evaluation Model for South Tx Project,Units 1 & 2,IAW 10CFR50.46(a)(3)(ii) ML20217K9341999-10-15015 October 1999 Forwards SER Accepting Util 990609 Relief Request RR-ENG-2-4 for Relief from ASME Code,Section XI, Nondestructive Exam Requirements Applicable to Stp,Units 1 & 2,reactor Vessel Closure Head Nuts ML20217K9091999-10-15015 October 1999 Forwards SER Accepting Util 990609 Relief Request RR-ENG-2-3 from ASME Code,Section Xi,Nondestructive Exam Requirements Applicable to South Texas Project,Units 1 & 2, Pressurizer Support Attachment Welds 05000498/LER-1999-008, Forwards LER 99-008-00 Re Turbine Trip That Occurred While Performing Main Turbine Emergency Trip Test.Commitments Made by Licensee Are Listed in Corrective Actions Section of LER1999-10-12012 October 1999 Forwards LER 99-008-00 Re Turbine Trip That Occurred While Performing Main Turbine Emergency Trip Test.Commitments Made by Licensee Are Listed in Corrective Actions Section of LER NOC-AE-000674, Forwards Requested Estimates of Needs for Operator Licensing Exams,Per AL-99-03, Operator Licensing National Exam Schedule1999-10-12012 October 1999 Forwards Requested Estimates of Needs for Operator Licensing Exams,Per AL-99-03, Operator Licensing National Exam Schedule NOC-AE-000625, Requests Partial Relief from ASME Section XI Visual Exam Requirements of IWA-5242(a).Relief Request Is Based on Provisions of Draft ASME Section XI Code Case N-616,which Is Expected to Be Published in Near Future1999-10-0707 October 1999 Requests Partial Relief from ASME Section XI Visual Exam Requirements of IWA-5242(a).Relief Request Is Based on Provisions of Draft ASME Section XI Code Case N-616,which Is Expected to Be Published in Near Future NOC-AE-000610, Requests Relief from ASME Section XI Code Nondestructive Exam Requirements of IWA-5250(a)(2) for Second Inservice Insp Interval,Per Provisions of 10CFR50.55a(3)(i)1999-10-0707 October 1999 Requests Relief from ASME Section XI Code Nondestructive Exam Requirements of IWA-5250(a)(2) for Second Inservice Insp Interval,Per Provisions of 10CFR50.55a(3)(i) NOC-AE-000653, Requests Relief from ASME Section XI Code Requirements of Table IWE-2500-1 for VT-3 Visual Exam of Seals & Gaskets on Airlocks,Hatches & Other Devices Required to Assure Containment leak-tight Integrity,Per 10CFR50.55a(a)(3)(i)1999-10-0707 October 1999 Requests Relief from ASME Section XI Code Requirements of Table IWE-2500-1 for VT-3 Visual Exam of Seals & Gaskets on Airlocks,Hatches & Other Devices Required to Assure Containment leak-tight Integrity,Per 10CFR50.55a(a)(3)(i) ML20217C3221999-10-0707 October 1999 Forwards Insp Repts 50-498/99-16 & 50-499/99-16 on 990808-0918.No Violations Noted.Insp Generally Characterized by safety-conscious Operations,Sound Engineering & Maint Practices & Careful Radiological Work Controls 05000499/LER-1999-006, Forwards LER 99-006-00,re Entry Into TS 3.0.3.Licensee Commitments Listed in Corrective Actions Section of Attachment1999-09-30030 September 1999 Forwards LER 99-006-00,re Entry Into TS 3.0.3.Licensee Commitments Listed in Corrective Actions Section of Attachment ML20212L1651999-09-30030 September 1999 Responds to STP Nuclear Operating Co 981012 & s Which Provided Update to TS Bases Pages B 3/4 8-14 Through B 3/4 8-17.NRC Staff Found Change Consistent with TS 3/4.8.2 DC Sources. Staff Found & Deleted Typographical Error NOC-AE-000664, Forwards Rev 1 to STP Electric Generating Station Unit 1 Cycle 9 COLR & Rev 1 to STP Electric Generating Station Unit 2 Cycle 7 Colr1999-09-30030 September 1999 Forwards Rev 1 to STP Electric Generating Station Unit 1 Cycle 9 COLR & Rev 1 to STP Electric Generating Station Unit 2 Cycle 7 Colr ML20212J7141999-09-29029 September 1999 Forwards Insp Repts 50-498/99-15 & 50-499/99-15 on 990920-24 at South Texas Project Electric Generating Station.No Violations Noted.Insp Covered Requalification Training Program & Observation of Requalification Activities NOC-AE-000646, Informs NRC That STP Nuclear Operating Co Is Y2K Ready IAW Nei/Nusmg 97-07 Guidelines & Also Provides Response to NRC Ltr1999-09-28028 September 1999 Informs NRC That STP Nuclear Operating Co Is Y2K Ready IAW Nei/Nusmg 97-07 Guidelines & Also Provides Response to NRC Ltr ML20212J0651999-09-27027 September 1999 Discusses Licensee 980330 Response to GL 97-06, Degradation of SG Internals. Concludes That Response to GL Provides Reasonable Assurance That Condition of SG Internals in Compliance with Current Licensing Bases for Facility ML20212F1791999-09-24024 September 1999 Discusses 990923 Meeting Conducted in Region IV Ofc Re Status of Activities to Support Confirmatory Order, ,modifying OL & to Introduce New Director,Safety Quality Concerns Program.List of Attendees Encl ML20212E9091999-09-23023 September 1999 Discusses GL 98-01, Year 2000 Readiness of Computer Sys at Npps, Supplement 1 & STP Nuclear Operating Co Response for STP Dtd 990629.Understands That at Least One Sys or Component Listed May Have Potential to Cause Transient ML20212F2111999-09-22022 September 1999 Forwards Review of SG 90-day Rept, South Texas Unit-2 Cycle 7 Voltage-Based Repair Criteria Rept, Submitted by Util on 990119 NOC-AE-000633, Forwards Rev 3 to SG-99-04-005, STP 1RE08 Outage Condition Monitoring Rept & Final Operational Assessment. Rept Satisfies Reporting Requirements of NEI 97-06,dtd Dec 19971999-09-21021 September 1999 Forwards Rev 3 to SG-99-04-005, STP 1RE08 Outage Condition Monitoring Rept & Final Operational Assessment. Rept Satisfies Reporting Requirements of NEI 97-06,dtd Dec 1997 NOC-AE-000634, Forwards Addl Info Re GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Povs. MOV design-basis Review Checklist,Encl1999-09-21021 September 1999 Forwards Addl Info Re GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Povs. MOV design-basis Review Checklist,Encl NOC-AE-000649, Forwards Current Annual Financial Data for STP Electric Generating Station Per 10CFR50.71(b),acting on Behalf of Central Power & Light Co,City of Austin,Tx,City Public Svc Board of San Antonio & Hl&P1999-09-21021 September 1999 Forwards Current Annual Financial Data for STP Electric Generating Station Per 10CFR50.71(b),acting on Behalf of Central Power & Light Co,City of Austin,Tx,City Public Svc Board of San Antonio & Hl&P 05000499/LER-1999-005, Forwards LER 99-005-00,re Esfa Following Loss of Power to Standby Transformer 2 Due to Electrical Fault.Licensee Commitments Are Listed in Corrective Actions Section of LER1999-09-20020 September 1999 Forwards LER 99-005-00,re Esfa Following Loss of Power to Standby Transformer 2 Due to Electrical Fault.Licensee Commitments Are Listed in Corrective Actions Section of LER ML20212D9171999-09-16016 September 1999 Informs That on 990818,NRC Completed Midcycle PPR of South Texas Project & Identified No Areas in Which Performance Warranted Insp Beyond Core Insp Program.Details of Insp Plan Through Mar 2000 & Historical Listing of Plant Issues,Encl ML20216F5471999-09-15015 September 1999 Discusses 990914 Meeting Conducted at Region Iv.Meeting Was Requested by Staff to Introduce New Management Organization to Region IV & to Discuss General Plant Performance & Mgt Challenges IR 05000498/19990121999-09-14014 September 1999 Forwards Insp Repts 50-498/99-12 & 50-499/99-12 on 990816-19.Three Violations Occurred & Being Treated as Ncvs. Areas Examined During Insp Included Portions of Access Authorization & Physical Security Programs 05000498/LER-1999-007, Forwards LER 99-007-00 Re Train 'B' CR Makeup & Cleanup Filtration Sys Being Inoperable for Greater than Aot.Util Intends to Append Addl Info Section of LER with Brief Description of Test Results,Rather than Submit Separate LER1999-09-13013 September 1999 Forwards LER 99-007-00 Re Train 'B' CR Makeup & Cleanup Filtration Sys Being Inoperable for Greater than Aot.Util Intends to Append Addl Info Section of LER with Brief Description of Test Results,Rather than Submit Separate LER ML20211P8201999-09-0909 September 1999 Forwards SE Authorizing 990224 Submittal of First 10-year Interval ISI Program Plan - Relief Request RR-ENG-24,from ASME Section XI Code,Table IWC-2500-1 NOC-AE-000638, Forwards License Renewal Applications & Certifications of Medical Exam for Seven Listed Licensed Operators at Stp,Per 10CFR55.57.Encl Withheld,Per 10CFR2.790(a)(6)1999-09-0909 September 1999 Forwards License Renewal Applications & Certifications of Medical Exam for Seven Listed Licensed Operators at Stp,Per 10CFR55.57.Encl Withheld,Per 10CFR2.790(a)(6) ML20211P7671999-09-0909 September 1999 Forwards SER Authorizing Licensee 990517 Alternative Proposed in Relief Request RR-ENG-2-8 to Code Case N-491-2 for Second 10-year Insp Interval of South Texas Project, Units 1 & 2,pursuant to 10CFR50.55a(a)(3)(i) ML20211P7871999-09-0909 September 1999 Forwards Safety Evaluation Re First 10-yr Interval Inservice Insp Program Plan Request for Relief RR-ENG-31 IR 05000498/19990141999-09-0303 September 1999 Forwards Insp Repts 50-498/99-14 & 50-499/99-14 on 990627-0807.Apparent Violations Identified & Being Treated as Noncited Violations Consistent with App C of Enforcement Policy NOC-AE-000562, Requests Relief from Contruction Code non-destructive Exam Requirements for Repair/Replacement Activities During Second Inservice Insp Interval of Units 1 & 2,IAW Provisions of 10CFR50.55a(a)(3)(i)1999-08-31031 August 1999 Requests Relief from Contruction Code non-destructive Exam Requirements for Repair/Replacement Activities During Second Inservice Insp Interval of Units 1 & 2,IAW Provisions of 10CFR50.55a(a)(3)(i) ML20212A4351999-08-27027 August 1999 Discusses Investigation Rept OI-4-1999-009 Re Activites at South Texas Project.Oi Investigation Initiated in Response to Alleged Employment Discrimination Complaint. Allegation Not Substantiated.No Further Action Planned NOC-AE-000617, Forwards semi-annual Fitness for Duty Program Performance Rept for 990101-990630,IAW 10CFR26.71(d)1999-08-26026 August 1999 Forwards semi-annual Fitness for Duty Program Performance Rept for 990101-990630,IAW 10CFR26.71(d) ML20211J2511999-08-26026 August 1999 Discusses Proposed TS Change on Replacement SG Water Level Trip Setpoint for Plant,Units 1 & 2 NOC-AE-000585, Provides Notification That South Texas Project Has Completed Integrity Evaluation of Units 1 & 2 Reactor Coolant Pump Casings Required by Paragraph (D) of Code Case N-4811999-08-25025 August 1999 Provides Notification That South Texas Project Has Completed Integrity Evaluation of Units 1 & 2 Reactor Coolant Pump Casings Required by Paragraph (D) of Code Case N-481 ML20211F4421999-08-24024 August 1999 Forwards SE Authorizing Licensee 990513 Request for Relief RR-ENG-2-13,seeking Relief from ASME B&PV Code Section Xi,Exam Vessel shell-to-flange Welds for Second ISI Intervals ML20211F5031999-08-23023 August 1999 Forwards SE Authorizing Licensee 990315 Request for Relief RR-ENG-30,seeking Relief from ASME B&PV Code,Section Xi,Nde Requirements Applicable to Stp,Unit 2 SG Welds ML20212A4391999-08-17017 August 1999 Discusses Investigation Rept OI-4-1999-023 Re Activities at South Texas Project.Oi Investigation Initiated in Response to Alleged Employment Discrimination for Initiating Condition Report to Document Unauthorized Work Practices ML20210U1271999-08-16016 August 1999 Forwards Insp Repts 50-498/99-08 & 50-499/99-08 on 990517-21 & 0607-10.No Violations Noted.Corrective Action Program Was Reviewed ML20211A9501999-08-12012 August 1999 Discusses 990720-21 Workshop Conducted in Region IV Ofc,Re Exchange of Info in Area of Use of Risk Insights in Regulatory Activities.List of Attendees,Summary of Topic & Issues,Agenda & Copies of Handouts Encl ML20211B7881999-08-10010 August 1999 Transmits Summary of Two Meetings with Risk-Informed TS Task Force in Rockville,Md on 990514 & 0714 ML20210L1461999-08-0303 August 1999 Informs That NRC Plans to Administer Gfes of Written Operator Licensing Exam on 991006.Requests Submittal of Ltr Identifying Individuals Taking Exam,Personnel Allowed Access to Exams & Mailing Address for Exams NOC-AE-000603, Informs of Addition of Restriction to SRO License 42658, for KM Espinoza,Effective 990721,per 10CFR50.74.Encl Info Withheld,Per 10CFR2.790(a)(6)1999-07-29029 July 1999 Informs of Addition of Restriction to SRO License 42658, for KM Espinoza,Effective 990721,per 10CFR50.74.Encl Info Withheld,Per 10CFR2.790(a)(6) NOC-AE-000470, Forwards Amend 12 to STP Fire Hazards Analysis Rept. Summary of Changes Made Under Provision of 10CFR50.59 Also Encl1999-07-28028 July 1999 Forwards Amend 12 to STP Fire Hazards Analysis Rept. Summary of Changes Made Under Provision of 10CFR50.59 Also Encl NOC-AE-000599, Forwards STP Unit 1,Cycle 9 Startup Testing Summary Rept. No New Licensing Commitments Contained in Ltr1999-07-28028 July 1999 Forwards STP Unit 1,Cycle 9 Startup Testing Summary Rept. No New Licensing Commitments Contained in Ltr NOC-AE-000589, Forwards Rev to 1RE08 ISI Summary Repts for Repairs & Replacements & for Sys Pressure Tests,Corecting Date of End of Insp Interval Provided in Item 9 of from NIS-1 from 09/24/99 to 09/24/20001999-07-26026 July 1999 Forwards Rev to 1RE08 ISI Summary Repts for Repairs & Replacements & for Sys Pressure Tests,Corecting Date of End of Insp Interval Provided in Item 9 of from NIS-1 from 09/24/99 to 09/24/2000 ML20210F3851999-07-26026 July 1999 Forwards Exam Repts 50-498/99-301 & 50-499/99-301 on 990706- 15.Exam Included Evaluation of 9 Applicants for SO Licenses & 8 Applicants for RO Licenses 1999-09-09 Category:INCOMING CORRESPONDENCE MONTHYEARNOC-AE-000675, Forwards Clarification on Items Included in 990531 Response to RAI Re Proposed License Amend Associated with Operator Action for Sbloca,As Requested1999-10-21021 October 1999
[Table view]Forwards Clarification on Items Included in 990531 Response to RAI Re Proposed License Amend Associated with Operator Action for Sbloca,As Requested NOC-AE-000680, Forwards Rev 5 to 0PGP03-ZV-0001, Severe Weather Plan1999-10-20020 October 1999 Forwards Rev 5 to 0PGP03-ZV-0001, Severe Weather Plan NOC-AE-000683, Forwards 30-day Rept Concerning Significant Changes to Accepted Large Break Loss of Coolant Accident ECCS Evaluation Model for South Tx Project,Units 1 & 2,IAW 10CFR50.46(a)(3)(ii)1999-10-19019 October 1999 Forwards 30-day Rept Concerning Significant Changes to Accepted Large Break Loss of Coolant Accident ECCS Evaluation Model for South Tx Project,Units 1 & 2,IAW 10CFR50.46(a)(3)(ii) NOC-AE-000674, Forwards Requested Estimates of Needs for Operator Licensing Exams,Per AL-99-03, Operator Licensing National Exam Schedule1999-10-12012 October 1999 Forwards Requested Estimates of Needs for Operator Licensing Exams,Per AL-99-03, Operator Licensing National Exam Schedule 05000498/LER-1999-008, Forwards LER 99-008-00 Re Turbine Trip That Occurred While Performing Main Turbine Emergency Trip Test.Commitments Made by Licensee Are Listed in Corrective Actions Section of LER1999-10-12012 October 1999 Forwards LER 99-008-00 Re Turbine Trip That Occurred While Performing Main Turbine Emergency Trip Test.Commitments Made by Licensee Are Listed in Corrective Actions Section of LER NOC-AE-000625, Requests Partial Relief from ASME Section XI Visual Exam Requirements of IWA-5242(a).Relief Request Is Based on Provisions of Draft ASME Section XI Code Case N-616,which Is Expected to Be Published in Near Future1999-10-0707 October 1999 Requests Partial Relief from ASME Section XI Visual Exam Requirements of IWA-5242(a).Relief Request Is Based on Provisions of Draft ASME Section XI Code Case N-616,which Is Expected to Be Published in Near Future NOC-AE-000610, Requests Relief from ASME Section XI Code Nondestructive Exam Requirements of IWA-5250(a)(2) for Second Inservice Insp Interval,Per Provisions of 10CFR50.55a(3)(i)1999-10-0707 October 1999 Requests Relief from ASME Section XI Code Nondestructive Exam Requirements of IWA-5250(a)(2) for Second Inservice Insp Interval,Per Provisions of 10CFR50.55a(3)(i) NOC-AE-000653, Requests Relief from ASME Section XI Code Requirements of Table IWE-2500-1 for VT-3 Visual Exam of Seals & Gaskets on Airlocks,Hatches & Other Devices Required to Assure Containment leak-tight Integrity,Per 10CFR50.55a(a)(3)(i)1999-10-0707 October 1999 Requests Relief from ASME Section XI Code Requirements of Table IWE-2500-1 for VT-3 Visual Exam of Seals & Gaskets on Airlocks,Hatches & Other Devices Required to Assure Containment leak-tight Integrity,Per 10CFR50.55a(a)(3)(i) 05000499/LER-1999-006, Forwards LER 99-006-00,re Entry Into TS 3.0.3.Licensee Commitments Listed in Corrective Actions Section of Attachment1999-09-30030 September 1999 Forwards LER 99-006-00,re Entry Into TS 3.0.3.Licensee Commitments Listed in Corrective Actions Section of Attachment NOC-AE-000664, Forwards Rev 1 to STP Electric Generating Station Unit 1 Cycle 9 COLR & Rev 1 to STP Electric Generating Station Unit 2 Cycle 7 Colr1999-09-30030 September 1999 Forwards Rev 1 to STP Electric Generating Station Unit 1 Cycle 9 COLR & Rev 1 to STP Electric Generating Station Unit 2 Cycle 7 Colr NOC-AE-000646, Informs NRC That STP Nuclear Operating Co Is Y2K Ready IAW Nei/Nusmg 97-07 Guidelines & Also Provides Response to NRC Ltr1999-09-28028 September 1999 Informs NRC That STP Nuclear Operating Co Is Y2K Ready IAW Nei/Nusmg 97-07 Guidelines & Also Provides Response to NRC Ltr NOC-AE-000633, Forwards Rev 3 to SG-99-04-005, STP 1RE08 Outage Condition Monitoring Rept & Final Operational Assessment. Rept Satisfies Reporting Requirements of NEI 97-06,dtd Dec 19971999-09-21021 September 1999 Forwards Rev 3 to SG-99-04-005, STP 1RE08 Outage Condition Monitoring Rept & Final Operational Assessment. Rept Satisfies Reporting Requirements of NEI 97-06,dtd Dec 1997 NOC-AE-000634, Forwards Addl Info Re GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Povs. MOV design-basis Review Checklist,Encl1999-09-21021 September 1999 Forwards Addl Info Re GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Povs. MOV design-basis Review Checklist,Encl NOC-AE-000649, Forwards Current Annual Financial Data for STP Electric Generating Station Per 10CFR50.71(b),acting on Behalf of Central Power & Light Co,City of Austin,Tx,City Public Svc Board of San Antonio & Hl&P1999-09-21021 September 1999 Forwards Current Annual Financial Data for STP Electric Generating Station Per 10CFR50.71(b),acting on Behalf of Central Power & Light Co,City of Austin,Tx,City Public Svc Board of San Antonio & Hl&P 05000499/LER-1999-005, Forwards LER 99-005-00,re Esfa Following Loss of Power to Standby Transformer 2 Due to Electrical Fault.Licensee Commitments Are Listed in Corrective Actions Section of LER1999-09-20020 September 1999 Forwards LER 99-005-00,re Esfa Following Loss of Power to Standby Transformer 2 Due to Electrical Fault.Licensee Commitments Are Listed in Corrective Actions Section of LER 05000498/LER-1999-007, Forwards LER 99-007-00 Re Train 'B' CR Makeup & Cleanup Filtration Sys Being Inoperable for Greater than Aot.Util Intends to Append Addl Info Section of LER with Brief Description of Test Results,Rather than Submit Separate LER1999-09-13013 September 1999 Forwards LER 99-007-00 Re Train 'B' CR Makeup & Cleanup Filtration Sys Being Inoperable for Greater than Aot.Util Intends to Append Addl Info Section of LER with Brief Description of Test Results,Rather than Submit Separate LER NOC-AE-000638, Forwards License Renewal Applications & Certifications of Medical Exam for Seven Listed Licensed Operators at Stp,Per 10CFR55.57.Encl Withheld,Per 10CFR2.790(a)(6)1999-09-0909 September 1999 Forwards License Renewal Applications & Certifications of Medical Exam for Seven Listed Licensed Operators at Stp,Per 10CFR55.57.Encl Withheld,Per 10CFR2.790(a)(6) NOC-AE-000562, Requests Relief from Contruction Code non-destructive Exam Requirements for Repair/Replacement Activities During Second Inservice Insp Interval of Units 1 & 2,IAW Provisions of 10CFR50.55a(a)(3)(i)1999-08-31031 August 1999 Requests Relief from Contruction Code non-destructive Exam Requirements for Repair/Replacement Activities During Second Inservice Insp Interval of Units 1 & 2,IAW Provisions of 10CFR50.55a(a)(3)(i) NOC-AE-000617, Forwards semi-annual Fitness for Duty Program Performance Rept for 990101-990630,IAW 10CFR26.71(d)1999-08-26026 August 1999 Forwards semi-annual Fitness for Duty Program Performance Rept for 990101-990630,IAW 10CFR26.71(d) NOC-AE-000585, Provides Notification That South Texas Project Has Completed Integrity Evaluation of Units 1 & 2 Reactor Coolant Pump Casings Required by Paragraph (D) of Code Case N-4811999-08-25025 August 1999 Provides Notification That South Texas Project Has Completed Integrity Evaluation of Units 1 & 2 Reactor Coolant Pump Casings Required by Paragraph (D) of Code Case N-481 NOC-AE-000603, Informs of Addition of Restriction to SRO License 42658, for KM Espinoza,Effective 990721,per 10CFR50.74.Encl Info Withheld,Per 10CFR2.790(a)(6)1999-07-29029 July 1999 Informs of Addition of Restriction to SRO License 42658, for KM Espinoza,Effective 990721,per 10CFR50.74.Encl Info Withheld,Per 10CFR2.790(a)(6) NOC-AE-000599, Forwards STP Unit 1,Cycle 9 Startup Testing Summary Rept. No New Licensing Commitments Contained in Ltr1999-07-28028 July 1999 Forwards STP Unit 1,Cycle 9 Startup Testing Summary Rept. No New Licensing Commitments Contained in Ltr NOC-AE-000470, Forwards Amend 12 to STP Fire Hazards Analysis Rept. Summary of Changes Made Under Provision of 10CFR50.59 Also Encl1999-07-28028 July 1999 Forwards Amend 12 to STP Fire Hazards Analysis Rept. Summary of Changes Made Under Provision of 10CFR50.59 Also Encl 05000498/LER-1999-006, Forwards LER 99-006-00 Re Automatic Reactor Trip Due to over-temp delta-temp Actuation.Licensee Commitments Are Listed in Corrective Actions Section of LER1999-07-26026 July 1999 Forwards LER 99-006-00 Re Automatic Reactor Trip Due to over-temp delta-temp Actuation.Licensee Commitments Are Listed in Corrective Actions Section of LER NOC-AE-000589, Forwards Rev to 1RE08 ISI Summary Repts for Repairs & Replacements & for Sys Pressure Tests,Corecting Date of End of Insp Interval Provided in Item 9 of from NIS-1 from 09/24/99 to 09/24/20001999-07-26026 July 1999 Forwards Rev to 1RE08 ISI Summary Repts for Repairs & Replacements & for Sys Pressure Tests,Corecting Date of End of Insp Interval Provided in Item 9 of from NIS-1 from 09/24/99 to 09/24/2000 NOC-AE-000582, Forwards 1RE08 ISI Summary Rept for Welds & Component Supports of STP Electric Generating Station,Unit 1. Summary Rept Satisfies Reporting Requirements of IWA-6000 of Section XI for Welds & Component Supports1999-07-26026 July 1999 Forwards 1RE08 ISI Summary Rept for Welds & Component Supports of STP Electric Generating Station,Unit 1. Summary Rept Satisfies Reporting Requirements of IWA-6000 of Section XI for Welds & Component Supports NOC-AE-000597, Forwards voltage-based Criteria 90-day Rept for SG Tube Exam Performed Under NRC GL 95-05 During Refueling Outage 1RE08. Rept Contains Info Required by Section 6.b of Attachment 2 to GL 95-051999-07-23023 July 1999 Forwards voltage-based Criteria 90-day Rept for SG Tube Exam Performed Under NRC GL 95-05 During Refueling Outage 1RE08. Rept Contains Info Required by Section 6.b of Attachment 2 to GL 95-05 NOC-AE-000598, Forwards Four Copies of 1RE08 Refueling Outage ISI Summary Rept for Steam Generator Tubing1999-07-23023 July 1999 Forwards Four Copies of 1RE08 Refueling Outage ISI Summary Rept for Steam Generator Tubing NOC-AE-00586, Forwards Results of Control Rod Testing,In Response to NRC Bulletin 96-01, Control Rod Insertion Problems, Dtd 960308.Core Map Provided to Assist in Understanding Test Data1999-07-21021 July 1999 Forwards Results of Control Rod Testing,In Response to NRC Bulletin 96-01, Control Rod Insertion Problems, Dtd 960308.Core Map Provided to Assist in Understanding Test Data NOC-AE-000595, Forwards Chapters 1.0 & 16.0 to Operations QA Plan for South Texas Project.Rev Is Strictly Administrative & All Content Was Previously Submitted to NRC on 990503 & 9906151999-07-21021 July 1999 Forwards Chapters 1.0 & 16.0 to Operations QA Plan for South Texas Project.Rev Is Strictly Administrative & All Content Was Previously Submitted to NRC on 990503 & 990615 NOC-AE-000518, Requests Exemption from Various Special Treatment Requirements of 10CFR50,as Described in Encls to Ltr.Stp Believes That Pilot Application Will Assist NRC in Development & Implementation of risk-informed 10CFR501999-07-13013 July 1999 Requests Exemption from Various Special Treatment Requirements of 10CFR50,as Described in Encls to Ltr.Stp Believes That Pilot Application Will Assist NRC in Development & Implementation of risk-informed 10CFR50 NOC-AE-000536, Submits Request for Exemption from Requirements of 10CFR50.34(b)(11),10CFR50,App A,Gdc 2 & 10CFR100,App a, Section VI(a)(3) Re Maint of Seismic Instrumentation.Revised Page to Procedure OERP01-ZV-IN01 Included1999-07-13013 July 1999 Submits Request for Exemption from Requirements of 10CFR50.34(b)(11),10CFR50,App A,Gdc 2 & 10CFR100,App a, Section VI(a)(3) Re Maint of Seismic Instrumentation.Revised Page to Procedure OERP01-ZV-IN01 Included NOC-AE-000580, Forwards Response to NRC 990415 RAI Re Implementation of Commitments Related to GL 89-10, Safety-Related MOV Testing & Surveillance & GL 96-05, Periodic Verification of Design Basis Capability of Safety-Related Movs1999-07-13013 July 1999 Forwards Response to NRC 990415 RAI Re Implementation of Commitments Related to GL 89-10, Safety-Related MOV Testing & Surveillance & GL 96-05, Periodic Verification of Design Basis Capability of Safety-Related Movs NOC-AE-000574, Forwards ISI Summary Repts for Repairs & Replacements & for Sys Pressure Tests Performed Between 971004 & Completion of Eighth RO on 9904281999-07-0606 July 1999 Forwards ISI Summary Repts for Repairs & Replacements & for Sys Pressure Tests Performed Between 971004 & Completion of Eighth RO on 990428 NOC-AE-000557, Requests Relief from ASME Section XI Code Nondestructive Exam Requirements of App III,III-3410 for Second ISI Interval.Proposed Alternatives for Ultrasonic Exam of Piping Sys Welds,Attached1999-07-0606 July 1999 Requests Relief from ASME Section XI Code Nondestructive Exam Requirements of App III,III-3410 for Second ISI Interval.Proposed Alternatives for Ultrasonic Exam of Piping Sys Welds,Attached NOC-AE-000498, Requests Relief from ASME Section XI Code Nondestructive Exam Requirements Applicable to SG Main Steam Nozzle inside- Radius Sections.Attachment Includes Discussion of Basis & Justification for Request & Implementation Schedule1999-07-0606 July 1999 Requests Relief from ASME Section XI Code Nondestructive Exam Requirements Applicable to SG Main Steam Nozzle inside- Radius Sections.Attachment Includes Discussion of Basis & Justification for Request & Implementation Schedule NOC-AE-000573, Requests Relief from Requirements of ASME Section XI Code Case N-498,exempting Isolated Class 1 Reactor Vessel Head Vent Atmospheric Vent Piping & Valve from Being Tested at Full RCS Pressure1999-07-0606 July 1999 Requests Relief from Requirements of ASME Section XI Code Case N-498,exempting Isolated Class 1 Reactor Vessel Head Vent Atmospheric Vent Piping & Valve from Being Tested at Full RCS Pressure NOC-AE-000541, Submits Response to GL 98-01,Suppl 1, Y2K Readiness of Computer Systems at Npps. Readiness Disclosure for STP, Encl1999-06-29029 June 1999 Submits Response to GL 98-01,Suppl 1, Y2K Readiness of Computer Systems at Npps. Readiness Disclosure for STP, Encl NOC-AE-000571, Forwards Final Operating Exam Matls for STP Exam Scheduled for 990705.Revised Operating Exam Outline & post-validation Change Summary Has Been Included.Without Encls1999-06-24024 June 1999 Forwards Final Operating Exam Matls for STP Exam Scheduled for 990705.Revised Operating Exam Outline & post-validation Change Summary Has Been Included.Without Encls NOC-AE-000512, Responds to NRC 981201 Telcon Re Jco 93-0004,per Revised MSLB Analysis1999-06-23023 June 1999 Responds to NRC 981201 Telcon Re Jco 93-0004,per Revised MSLB Analysis NOC-AE-000560, Forwards LER 99-S02-00,re Failure to Maintain Positive Control of Vital Area Security Key.Licensee Commitments Are Found in Corrective Action Section of LER1999-06-23023 June 1999 Forwards LER 99-S02-00,re Failure to Maintain Positive Control of Vital Area Security Key.Licensee Commitments Are Found in Corrective Action Section of LER 05000498/LER-1999-005, Forwards LER 99-005-00,re Failure to Meet Requirements of TS Surveillance 3.7.1.2 Action B for Auxiliary FW Sys.Only Commitments Contained in Ltr Are Located in Corrective Action Section of LER1999-06-17017 June 1999 Forwards LER 99-005-00,re Failure to Meet Requirements of TS Surveillance 3.7.1.2 Action B for Auxiliary FW Sys.Only Commitments Contained in Ltr Are Located in Corrective Action Section of LER NOC-AE-000565, Forwards Amended Pages for Insertion Into South Texas Project Nuclear Operating Co Previously Submitted Response to NRC Rai.New Pages Include Expanded Answer to Question 4.b1999-06-16016 June 1999 Forwards Amended Pages for Insertion Into South Texas Project Nuclear Operating Co Previously Submitted Response to NRC Rai.New Pages Include Expanded Answer to Question 4.b NOC-AE-000548, Forwards Response to RAI Re Proposed Amends on Replacement SG Water Level Trip Setpoint Differences for Stp,Units 1 & 2.Nothing Contained in Response Should Be Considered Commitment Unless So Specified in Separate Correspondence1999-06-16016 June 1999 Forwards Response to RAI Re Proposed Amends on Replacement SG Water Level Trip Setpoint Differences for Stp,Units 1 & 2.Nothing Contained in Response Should Be Considered Commitment Unless So Specified in Separate Correspondence NOC-AE-000561, Forwards Change QA-042 to Operations QAP, Rev 13, Reflecting Current Organizational Alignment for STP & Culminating Organizational Realigment That Has Been Taking Place During Past Several Months1999-06-15015 June 1999 Forwards Change QA-042 to Operations QAP, Rev 13, Reflecting Current Organizational Alignment for STP & Culminating Organizational Realigment That Has Been Taking Place During Past Several Months NOC-AE-0559, Forwards STP Commitment Change Summary Rept for Period 981209-990610.Rept Lists Each Commitment for Which Change Was Made During Reporting Period & Provides Basis for Each Change1999-06-15015 June 1999 Forwards STP Commitment Change Summary Rept for Period 981209-990610.Rept Lists Each Commitment for Which Change Was Made During Reporting Period & Provides Basis for Each Change NOC-AE-000499, Forwards Relief Request RR-ENG-2-3,proposing to Perform Alternative Ultrasonic Examination from Outside Surface of Skirt Attachment Weld as Described in Encl,In Lieu of Surface Examination from Inside Pressurizer Skirt1999-06-0909 June 1999 Forwards Relief Request RR-ENG-2-3,proposing to Perform Alternative Ultrasonic Examination from Outside Surface of Skirt Attachment Weld as Described in Encl,In Lieu of Surface Examination from Inside Pressurizer Skirt NOC-AE-000502, Forwards Relief Request RR-ENG-2-6,proposing That Boroscopic VT-1 Visual Examination Be Allowed as Alternative to Section XI Surface Examination of Pump Casing Welds,Or Portions of Welds within Pits1999-06-0909 June 1999 Forwards Relief Request RR-ENG-2-6,proposing That Boroscopic VT-1 Visual Examination Be Allowed as Alternative to Section XI Surface Examination of Pump Casing Welds,Or Portions of Welds within Pits NOC-AE-000500, Forwards Relief Request RR-ENG-2-4,proposing to Perform Alternative Ultrasonic Examination from Outside & End Surfaces of Reactor Vessel Closure Head Nuts,As Described in Encl in Lieu of Surface Examination of Threaded Region1999-06-0909 June 1999 Forwards Relief Request RR-ENG-2-4,proposing to Perform Alternative Ultrasonic Examination from Outside & End Surfaces of Reactor Vessel Closure Head Nuts,As Described in Encl in Lieu of Surface Examination of Threaded Region NOC-AE-000545, Forwards Response to NRC 990416 RAI Re Util Proposed Amend on Operator Action for Small Break Loca, .Draft EOP Re Small Break Loca,Encl to Aid Discussion of Proposed Amend1999-05-31031 May 1999 Forwards Response to NRC 990416 RAI Re Util Proposed Amend on Operator Action for Small Break Loca, .Draft EOP Re Small Break Loca,Encl to Aid Discussion of Proposed Amend 1999-09-09 Category:STATE/LOCAL GOVERNMENT TO NRC MONTHYEARML20151C1541988-02-10010 February 1988
[Table view]FOIA Request for Records to Be Available at PDR Re Safety Allegations Concerning Facility ML20235J0641987-06-25025 June 1987 Supports Gap Motion for Special Project Team Operating Independently of Region IV or V Stello for Insp & Enforcement of Plant & Citizens Concerned About Nuclear Power Motion to Reopen Licensing Hearings.Served on 870714 ML20153C4601987-06-24024 June 1987 Expresses Concern Re Malfeasance of Region IV Concerning Plant.Supports Gap Motion for Special Project Team Operating Idependently & Also Supports Citizens Concerned About Nuclear Power Motion to Reopen Hearing ML20153C5731987-06-18018 June 1987 Comments Supporting Gap Motion for Special Project Team Which Can Operate Independently of Region IV & Also Support Citizens Concerned About Nuclear Power Motion to Reopen Plant Licensing Hearings ML20216J8851987-06-10010 June 1987 Urges Favorable Action on Gap Petition Requesting Establishment of Independent Review Team to Investigate Worker Allegations & Intervenor Citizens Concerned About Nuclear Power,Inc Motion to Reopen Record.Served on 870630 ML20205J0271987-03-23023 March 1987 Requests Copies of Application Tx 87-03-23-0007-50 Re Grant Assistance for Facility Be Sent to Texas Air Control Board, Atty General Ofc,Texas Water Commission,Public Utility Commission & Houston-Galveston Area Council for Comments ML20214P0101986-11-26026 November 1986 Offers No Further Comments on Fes.Response to Comments Re Emergency Preparedness Plans Appreciated ML20205T4931986-06-0505 June 1986 Comments on Des.Emergency Preparedness Plans Inadequate & Require Coordination W/Affected Local Govt Units ML20155K6131986-05-21021 May 1986 Forwards Comments on Des.Emergency Preparedness Plans Incomplete.Evacuation Measures Should Be Reviewed & Coordinated W/Affected Governmental Units ML20203P3581986-04-29029 April 1986 Requests Addl 10 Days to Respond W/Formal Review Comments on Des ML20137X0951986-02-26026 February 1986 Advises That No Response Will Be Provided to ASLB 860210 Order Inviting Response to 860207 Memorandum & Order Requesting Addl Info.No Active Role Will Be Taken in Further Development of Record ML20137E9721985-07-11011 July 1985 Discusses Interim Environ Surveillance Program Under Cooperative Agreement NRC-31-83-671.Proposed State Program Will Be Implemented by End of 1985 ML20052C0181982-04-27027 April 1982 Requests Listed Changes Be Made to Svc List.Svc List Encl ML19351A2111981-06-15015 June 1981 Requests to Make Limited Appearance Statement at 810622 Hearing ML19343B6681980-09-26026 September 1980 Forwards Executed Stipulation Re License Conditions ML19332A5261980-09-11011 September 1980 Notifies That City of Austin Has Reached Tentative Agreement to Settle W/Nrc & DOJ Re Proposed License Conditions. Settlement Contingent on Final Wording of Draft Document. Final Version Projected for 800915 ML20080T2921980-06-0303 June 1980 Requests Info Re Public Hearing on Insp of Facilities ML19305D3611980-04-0707 April 1980 Forwards Lower Co River Authority Data Re South Tx Interconnected Sys Interchange for 1979.Data Should Provide Index Re Types & Magnitude of Member Interchange within South Tx Interconnected Sys ML19309F7891980-04-0303 April 1980 Forwards Public Utils Board of City of Brownsville,Tx 800403 Opposition for Extension of Procedural Dates.Requests Early Prehearing Conference to Resolve Critical Issues Unless Motion Is Denied ML20072P1181979-12-0404 December 1979 Notifies That Prosecution Was Declined in Matter of Facilities.Fbi Found No Substantive Violations ML19209B1141979-09-0505 September 1979 Submits Aug 1979 Discovery Rept.City of Austin Has Neither Initiated Nor Received Any Discovery Requests.Certificate of Svc Encl ML19249D5161979-08-0808 August 1979 Advises of Termination of Active Participation in Proceeding Due to 790824 Transfer to San Francisco Field Ofc,Antitrust Div ML19249D9241979-08-0202 August 1979 Notifies That City of Austin,Tx Has Neither Initiated Nor Received Any Discovery Requests During Jul 1979.Certificate of Svc Encl ML19207A4751979-07-0202 July 1979 Notifies That City of Austin,Tx Has Not Initiated Nor Received Any Discovery Requests During June 1979. Certificate of Svc Encl ML19248C9231979-05-0808 May 1979 Submits Discovery Rept for Apr 1979.No Discoveries Initiated or Received ML20114E7811979-05-0707 May 1979 Requests Lpdr for Austin Public Library ML19274E6241979-03-0101 March 1979 Notifies of Objection to Motion to Compel Fuller Answers & Production by Doj.Interrogatories from City of Brownsville, Tx Received.Offer Made to Both Parties to Inspect Austin'S Files.Certificate of Svc Encl ML19282B1391979-02-0606 February 1979 Answered DOJ Discovery Request in Jan 1979 & Received Interrogatories.Answers Due W/Documents (Ref Encl Agreement).Certificate of Svc Encl ML19261B5931979-01-0404 January 1979 City Received Interrogatories & Request for Documents on 781205 from Dept of Justice.These May Be Produced at Same Time as Those of City of San Antonio.Seek Until mid-Jan 1979 to Complete Request.Certificate of Svc Encl ML19274D8171979-01-0404 January 1979 Requests Deadline for Response to or Objection to Interrogatories & Document Requests by Dept of Justice Be Changed from 790104 to 790115.Certificate of Svc Encl ML19322A0841978-12-0404 December 1978 Advises That During Nov 1978,City of Austin,Tx Neither Initiated Nor Received Any Discovery Requests ML20062G5551978-11-30030 November 1978 Requests Info Re Location of Pwr Lines in Wharton Co & List of Agencies That Have Authority Over Pwr Line Easement Locations ML20062E9281978-11-0606 November 1978 During Aug-Oct 1978,City of Austin Neither Initiated Nor Received Any Discovery Requests Re Subj Facil.W/Cert of Svc 1988-02-10 |
Text
,
E'
. ,r .
OFFICE OF PUBLIC UTILITY COUNSEL .~ . s- ~ .m.1. 7 7s, mm-I l
l M MSGd February 10, 1988 fR$EDOM OF INFORMAT10M 6CI REQUES Mr. Dennie H. Grimsley, Director [ dD ' # "M 7 1 Division of Rules and Records Office of Administration and
@ 2.g 4/h F f j Resources Management U.S. Nuclear Regulatory Commission
. Washington. 0.C. 20555 Re: F0IA Request for Records Concerning Safety Allegations, South Texas Project
Dear Mr. Grimsley:
1 Pursuant to the Freedom of Information Act and 10 CFR Part 9. Subpart A.
"Freedom of Information Act Regulations", please make available at the Commission's Washington. 0.C., Pub'.ic Document Room single copies of records in the following categories:
A. All records related to safety allegations concerning the South Texas Project that are currently being investigated by the NRC. According to published reports (see, for example, "NRC Investigating South Texas Safety Allegations", TNSIDE N.R.C. , 1/18/88, at 12-13), there are some 650 specific allegations. This request includes, but is not limited to, records documenting the allegations, records evaluating the safety significance of the allegations, utility records concerning the allegations, and all other records related to the allegations.
B. All records related to the establishment by NRC of an investigation team to review the allegations. The investigation team is reportedly headed by Jose Calvo (NRR), and includes eight other members from NRR and two from the Of fice of Enforcement. This request includes, but is not limited to, records related to the establishment of the investigation team, the procedures used by the investigation team, the records provided to 8804120189 880210 -
~Estabbshed to represont the unterests of rescential and sman commecial consumers"
\
r -
. , 4 .Mir. Grimsley February 10, 1988 the team to initiate and conduct the investigation, and all other records related to the activities of the investigation team.
We request a waiver of fees pursuant to 10 CFR 9.41 because the documents will be used by a state agency as part of an official investigation.
1 If you or any members of your staff have any questions concerning this j request, please contact the undersigned directly by telephone'at 512/345-9900. !
Your prompt attention to this request will be appreciated. 1 1
Sincerely,
/$1/A tat /E1 Barbara Day Deputy Fublic Counsel !
BD:id I
l l
l l